某工作的ES=4d,EF=8d,LS=7d,LF=11d,则该工作的总时差为()。A.2dB.3dC.4dD.6d
某工作的ES=4d,EF=8d,LS=7d,LF=11d,则该工作的总时差为()。
A.2d
B.3d
C.4d
D.6d
参考答案和解析
B 解析:工作总时差TFi-j=LSi-j,-ESi-j=7-4=3(d)。
相关考题:
The range of time allowed for an activity to be completed in is the _____.A.Planned time (Duration).B.Float time (LS - ES, or LF - EF).C.Critical time (when ES = LS, or EF = LF).D.Scheduled time (LF - ES).E.Event.
153 The range of time allowed for an activity to be completed in is the _____.A. Planned time (Duration).B. Float time (LS - ES, or LF - EF).C. Critical time (when ES = LS, or EF = LF).D. Scheduled time (LF - ES).E. Event
35 The range of time allowed for an activity to be completed in is the _____.A. Planned time (Duration).B. Float time (LS - ES, or LF - EF).C. Critical time (when ES = LS, or EF = LF).D. Scheduled time (LF - ES).E. Event.
● The range of time allowed for an activity to be completed in is the _____.A Planned time (Duration).B Float time (LS - ES, or LF - EF).C Critical time (when ES = LS, or EF = LF).D Scheduled time (LF - ES).E Event.
已知某建设工程网络计划中A工作的自由时差为5d,总时差为7d。监理工程师在检查施工进度时发现只有该工作实际进度拖延,且影响总工期3d,则该工作实际进度比计划进度拖延()d。A、3B、5C、8D、10
某工程双代号网络计划如下图所示(时间单位-天),图中已标出各项工作的最早开始时间ES 和最迟开始时间LS。该计划表明( )。A.工作1 一 3的总时差和自由时差相等B.工作2 — 6的总时差和自由时差相等C.工作2 — 4和工作3 — 6均为关键工作D.工作3 — 5的总时差和自由时差分别为2和 O天E.工作5 — 7的总时差和自由时差相等
下列关于总时差与自由时差的描述中错误的是( )。A.对于同一项工作而言,总时差不会超过自由时差B.TF=LF-EF=LS-ESC.工作的自由时差是指在不影响其紧后工作最早开始时间的前提下,本工作可利用的机动时间D.工作的总时差是指在不影响总工期的前提下,本工作可以利用的机动时间
单选题已知A工作的紧后工作有B和C,B工作的LS=14天,ES=10天;C工作的LF=l6天,EF=14天;A工作的自由时差为5天,则A工作的总时差TF为()天。A0B5C7D9