The range of time allowed for an activity to be completed in is the _____.A.Planned time (Duration).B.Float time (LS - ES, or LF - EF).C.Critical time (when ES = LS, or EF = LF).D.Scheduled time (LF - ES).E.Event.
The range of time allowed for an activity to be completed in is the _____.
A.Planned time (Duration).
B.Float time (LS - ES, or LF - EF).
C.Critical time (when ES = LS, or EF = LF).
D.Scheduled time (LF - ES).
E.Event.
相关考题:
153 The range of time allowed for an activity to be completed in is the _____.A. Planned time (Duration).B. Float time (LS - ES, or LF - EF).C. Critical time (when ES = LS, or EF = LF).D. Scheduled time (LF - ES).E. Event
35 The range of time allowed for an activity to be completed in is the _____.A. Planned time (Duration).B. Float time (LS - ES, or LF - EF).C. Critical time (when ES = LS, or EF = LF).D. Scheduled time (LF - ES).E. Event.
● The range of time allowed for an activity to be completed in is the _____.A Planned time (Duration).B Float time (LS - ES, or LF - EF).C Critical time (when ES = LS, or EF = LF).D Scheduled time (LF - ES).E Event.
按工程进度绘制的资金使用计划S曲线必然包括在“香蕉图”内,该“香蕉图”是由工程网络计划中全部工作分别按( )绘制的两条S曲线组成。A:最早开始时间(ES)开始和最早完成时间(EF)完成B:最早开始时间(ES)开始和最迟开始时间(LS)开始C:最迟开始时间(LS)开始和最早完成时间(EF)完成D:最迟开始时间(LS)开始和最迟完成时间(LF)完成
(2013年)按工程进度绘制的资金使用计划S曲线必然包括在“香蕉图”内,该“香蕉图”是由工程网络计划中全部工作分别按()绘制的两条S曲线组成。A.最早开始时间(ES)开始和最早完成时间(EF)完成B.最早开始时间(ES)开始和最迟开始时间(LS)开始C.最迟开始时间(LS)开始和最早完成时间(EF)完成D.最迟开始时间(LS)开始和最迟完成时间(LF)完成
在已知全部工作的( )时,可以按工程进度绘制资金使用计划S 曲线。A.最早开始时间(ES)开始和最早完成时间(EF)完成B.最早开始时间(ES)开始和最迟开始时间(LS)开始C.最迟开始时间(LS)开始和最早完成时间(EF)完成D.最迟开始时间(LS)开始和最迟完成时间(LF)完成
单选题下列关于最早时间和最晚时间的计算公式正确的是()。 ①ES=EF+活动持续时间②EF=ES+活动持续时间③LS=LF-活动持续时间④LF=LS-活动持续时间A①③B①④C②③D②④