已知某网络计划中某工作的ES=4d,EF=6d,LS=7d,LF=9d,则该工作的总时差为()d。A、2B、3C、4D、6
已知某网络计划中某工作的ES=4d,EF=6d,LS=7d,LF=9d,则该工作的总时差为()d。
- A、2
- B、3
- C、4
- D、6
相关考题:
The range of time allowed for an activity to be completed in is the _____.A.Planned time (Duration).B.Float time (LS - ES, or LF - EF).C.Critical time (when ES = LS, or EF = LF).D.Scheduled time (LF - ES).E.Event.
153 The range of time allowed for an activity to be completed in is the _____.A. Planned time (Duration).B. Float time (LS - ES, or LF - EF).C. Critical time (when ES = LS, or EF = LF).D. Scheduled time (LF - ES).E. Event
35 The range of time allowed for an activity to be completed in is the _____.A. Planned time (Duration).B. Float time (LS - ES, or LF - EF).C. Critical time (when ES = LS, or EF = LF).D. Scheduled time (LF - ES).E. Event.
● The range of time allowed for an activity to be completed in is the _____.A Planned time (Duration).B Float time (LS - ES, or LF - EF).C Critical time (when ES = LS, or EF = LF).D Scheduled time (LF - ES).E Event.
按工程进度绘制的资金使用计划S曲线必然包括在“香蕉图”内,该“香蕉图”是由工程网络计划中全部工作分别按( )绘制的两条S曲线组成。(2013年真题) A、最早开始时间(ES)开始和最早完成时间(EF)完成 B、最早开始时间(ES)开始和最迟开始时间(LS)开始 C、最迟开始时间(LS)开始和最早完成时间(EF)完成 D、最迟开始时间(Ls)开始和最迟完成时间(LF)完成
已知某工程的网络计划中相关资料如下表所示。问题:1.根据上表绘制网络计划图。2.计算总工期,以及网络图中各工作的六个时间参数(ES、EF、LS、LF、TF、FF)。3.写出关键线路(工作表示或节点表示)。
在已知全部工作的( )时,可以按工程进度绘制资金使用计划S 曲线。A.最早开始时间(ES)开始和最早完成时间(EF)完成B.最早开始时间(ES)开始和最迟开始时间(LS)开始C.最迟开始时间(LS)开始和最早完成时间(EF)完成D.最迟开始时间(LS)开始和最迟完成时间(LF)完成
背景已知某工程的网络计划中相关资料如下表所示。问题(1)根据上表中相关资料绘制网络图;(2)计算总工期,以及网络图中各工作的六个时间参数(ES、EF,LS,LF,TF,FF);(3)找出关键线路,并在图中用双箭线标明。
单选题按工程进度绘制的资金使用计划S曲线必然包括在“香蕉图”内,该“香蕉图”是由工程网络计划中全部工作分别按()绘制的两条s曲线组成。A最早开始时间(ES)开始和最早完成时间(EF.完成B最早开始时间(ES)开始和最迟开始时间(Ls)开始C最迟开始时间(LS)开始和最早完成时间(EF.完成D最迟开始时间(LS)开始和最迟完成时间(LF.完成
单选题下列关于最早时间和最晚时间的计算公式正确的是()。 ①ES=EF+活动持续时间②EF=ES+活动持续时间③LS=LF-活动持续时间④LF=LS-活动持续时间A①③B①④C②③D②④