A project management technique that is currently in widespread use is the ( ) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.A.Functional decomposition diagramB.Work Breakdown StructureC.Structure ChartD.Organizational Structure

A project management technique that is currently in widespread use is the ( ) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.

A.Functional decomposition diagram
B.Work Breakdown Structure
C.Structure Chart
D.Organizational Structure

参考解析

解析:

相关考题:

● Project Quality Management processes include all the activities of the (71) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.(71)A. projectB. project management teamC. performing organizationD. customer

The purpose of project Risk Management is to:A Identify those factors that will adversely impact project objectives.B Assess the impact of adverse project factors.C Assess the probability of adverse project factors.D A and CE All of the above.

Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.A.ProjectB.project management teamC.performingorganizationD.customer

● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.tA.IntegrationB.ScopeC.ConfigurationD.Requiremen

A project management technique that is currently in widespread use is the(71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called(72) , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide(73), whose purpose is to contain the various pieces of relevant information-feasibility assessments, schedules, needs analysis, and so forth-in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management.(74) was developed to make clear the interdependence between project tasks before those tasks are scheduled.(75) offers the advantage of clearly showing overlapping tasks.A.Structure ChartB.Organizational StructureC.Work Breakdown StructureD.Functional decomposition diagram

Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.A.Developing project charterB.Developing project management planC.Analyzing project risksD.Monitoring and controlling project

A project management technique that is currently in widespread use is the (73). The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.A.Structure ChartB.Organizational StructureC.Work Breakdown StructureD.Functional decomposition diagram

Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.A.performing organizationB.project management teamC.projectD.customer

Project (24) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A.IntegrationB.ScopeC.ConfigurationD.Requirement

● A project management technique that is currently in widespread use is the (71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called (72) , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide (73) , whose purpose is to contain the various pieces of relevant information – feasibility assessments, schedules, needs analysis, and so forth – in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management. (74) was developed to make clear the interdependence between project tasks before those tasks are scheduled. (75) offers the advantage of clearly showing overlapping tasks.

( )is a project management technique for measuring project performance and progress.It has the ability to combine measurements of the project management triangle: scope , time and costs.A.Critical path method(CPM)B.Earned value management(EVM)C.Net present value method (NPVM)D.Expert judgment method(EIM)

( )is a project management technique for measuring projectPerformance progress.It has the ability to combine measurements of the project management triangle: scope,time and costs.A.Critica1 path method(CPM) B.Earned value management(CEV)C.Net present value method(NPVM)D.Expert judgment method(EJM)

( )is a project management technique for measuring project performance and process. It has the ability to combine measurements of the project management triangle; scope time and costs.A.Critica path method(CPM)B.Earned value mangagemengt(EVM)C.Net present value method(NPVM)D.Expert judgment method(EJM)

( )is aproject mangement technique for measuring project performance and proress.it has the ability to combine measurements of the project management triangle;scope.time and costs.A. Critica path method(CPM)B. Earned value mangagemengt(EVM)C. Net present value method(NPVM)D. Expert judgment method(EJM)

()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A:Create scopEB:Project stakeholder managementC:Project scope managementD:Project cost management

( )is aproject mangement technique for measuring project performance and proress.it has the ability to combine measurements of the project management triangle;scope.time and costs.A:Critica path method(CPM)B:Earned value mangagemengt(EVM)C:Net present value method(NPVM)D:Expert judgment method(EJM)

A project is a[temporary](请作答此空)of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).A.taskB.workC.sequenceD.activity

A project is a[temporary]( )of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to(请作答此空)project(s).A.a singleB.a particularC.someD.all

The intention of the ( ) is to schedule,organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there. A.project work breakdown B.project security authentication C.project management D.project flowchart

()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A. Create scopEB. Project stakeholder managementC. Project scope managementD. Project cost management

Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.A、ProjectB、project management teamC、performingorganizationD、customer

Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement

Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement

MOST是Management Operation Standard Technique的缩写,即()。

单选题You have to store user data of 200 KB in an object. Which state management technique to use:()AServer sessionBCookieCViewStateDHidden Field

单选题Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.AProjectBproject management teamCperformingorganizationDcustomer

单选题The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()AEvaluate phase exit milestones using sufficiency criteriaBFlexible entry and exit criteria to minimize schedule delaysCQuality measures reported only to the project steering committeeDMany work teams with few members to maximize the number of deliverable hand-offs