( )is the process of implementing risk response plants,tracking?identified risks,monitoring residual risk,identifying new risk,and ecaluating risk process effectiveness throughout the project.A.Identity risksB.Control risksC.Plan risk responsesD.Plan risk management

( )is the process of implementing risk response plants,tracking?identified risks,monitoring residual risk,identifying new risk,and ecaluating risk process effectiveness throughout the project.

A.Identity risks
B.Control risks
C.Plan risk responses
D.Plan risk management

参考解析

解析:

相关考题:

Risk mitigation is the process of _____ .A transferring risk to another party.B reducing uncertainty on the projectC identifying all possible risk eventsD monitoring status and making adjustmentsE All of the above.

26 Risk mitigation is the process of _____ .A. transferring risk to another party.B. reducing uncertainty on the projectC. identifying all possible risk eventsD. monitoring status and making adjustmentsE. All of the above.

108 Risk mitigation is the process of _____ .A. transferring risk to another party.B. reducing uncertainty on the projectC. identifying all possible risk eventsD. monitoring status and making adjustmentsE. All of the above

Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses

The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control

●Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73).(73)A. project management planB. project baselineC. risk response planD. risk baseline

Setting redundant components in subsystem to handle with the risks brought by the defaults of original components, what kind of risk response strategy is this ? ( 75 ).A.Risk avoidanceB.Risk acceptanceC.Risk mitigationD.Contingency plan

setting redundant components in subsystem to handle with the risks brought by the defaultsof original components,what kind of risk response strategy is this?()A.risk avoidanceB.risk acceptanceC.risk mitigationD.contingency plan

()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.A.Identity risksB.Control risksC.Plan risk responsesD.Plan risk management

The______process ascertains which risks have the potential Of affecting the proect and documenting the risks' characteristics.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk AnalysisD.Risk Monitoring and Control

The(75)process analyzes the effect of risk events and assigns a numerical rating to those risks.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk AnalysisD.Risk Monitoring and Control

()is the process of identifying individual project risks as well as source of overall project risk,and documenting their characteristics.A.identify risksB.monitor risksC.implement risks responsesD.plan risk management

Managing risk and documenting them is very important in project planning process.You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the(73) .A.project management planB.project baselineC.riskresponse planD.risk baseline

setting redundant components in subsystem to handle with the risks brought by the defaults of original components,what kind of risk response strategy is this? ( ) . A.risk avoidance B.risk acceptance C.risk mitigation D.contingency plan

The ( ) process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring anD.Control

( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality. A.Quantitative Risk Analysis B.Qualitative Risk Analysis C.Enterprise Environmental Factors D.Risk Management Plan

setting redundant components in subsystem to handle with the risks brought by the defaults of original components,what kind of risk response strategy is this?()A、risk avoidanceB、risk acceptanceC、risk mitigationD、contingency plan

The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.A、RiskldentificationB、Quantitative Risk AnalysisC、Qualitative Risk AnalysisD、Risk Monitoring and Control

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A、RiskldentificationB、Quantitative RiskAnalysisC、Qualitative RiskAnalysisD、Risk Monitoring and Control

()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.A、Quantitative Risk AnalysisB、Qualitative Risk AnalysisC、Enterprise Environmental FactorsD、Risk Management Plan

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A、Risk IdentificationB、Quantitative Risk AnalysisC、Qualitative Risk AnalysisD、Risk Monitoring and Control

The general additional risks including()are covered in all risks coverage.A、risk of shortageB、risk of leakageC、strikes riskD、risk of rust

单选题The()process analyzes the effect of risk events and assigns a numerical rating to those risks.ARiskldentificationBQuantitative RiskAnalysisCQualitative RiskAnalysisDRisk Monitoring and Control

单选题The()process analyzes the effect of risk events and assigns a numerical rating to those risks.ARisk IdentificationBQuantitative Risk AnalysisCQualitative Risk AnalysisDRisk Monitoring and Control

单选题The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.ARiskldentificationBQuantitative Risk AnalysisCQualitative Risk AnalysisDRisk Monitoring and Control

单选题()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.AQuantitative Risk AnalysisBQualitative Risk AnalysisCEnterprise Environmental FactorsDRisk Management Plan