The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
A

Riskldentification

B

Quantitative RiskAnalysis

C

Qualitative RiskAnalysis

D

Risk Monitoring and Control


参考解析

解析: 该题的关键词为"analyzes the effect of risk, numerical rating",其语句结构为"The()一process(主语)analyzes(谓语)the effect of risk events(宾语)and assigns(并列谓语)anumerical rating to those risks(并列宾语)",含义为"什么过程分析风险事件的后果,并且为这些风险指定数值级别",容易判断题目描述的是量化风险分析的特点,应该选择选项B。

相关考题:

● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk Analysis.Risk Monitoring and Control

Risk mitigation is the process of _____ .A transferring risk to another party.B reducing uncertainty on the projectC identifying all possible risk eventsD monitoring status and making adjustmentsE All of the above.

Project Risk _____ .A should not be calculated for small projects.B is the probability of each risk event minus the sum of the consequences of potential risk events.C is the cumulative effect of uncertain occurrences which will adversely affect project objectives.D cannot be quantified for first time projects.E B or D

Screening of risk events for potential risk is known as _____ .A problem structuring.B risk identificationC risk quantificationD risk modelingE risk mitigation

Sensitivity analysis can be used in risk analysis to:A Substitute for uncertainty analysis in risk quantificationB estimate the level of risk aversion adopted by managementC estimate the effect of change of one project variable on the overall projectD A and BE All of the above.

Risk event probability is defined as:A the total number of possible events divided into the expectations or frequency of the risk eventB the number of times the risk event may occurC the fraction of the total project tasks which may be affected by the risk eventD the total number of possible events divided into the consequences of the risk event.E A and B

Total Project Risk:A should not be calculated for small projectsB is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.C Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.D A and BE A and C

Total project risk can be defined as:A the sum of the probabilities of project risks events times the sum of consequences of those risksB the sum of the products of each project risk event times its consequencesC the sum of the consequences of all project risk eventsD the sum of the probabilities of all project risk eventsE 1 - the sum of the probabilities of all project risk events.

15 Total project risk can be defined as:A. the sum of the probabilities of project risks events times the sum of consequences of those risksB. the sum of the products of each project risk event times its consequencesC. the sum of the consequences of all project risk eventsD. the sum of the probabilities of all project risk eventsE. 1 - the sum of the probabilities of all project risk events

113 Screening of risk events for potential risk is known as _____ .A. problem structuring.B. risk identificationC. risk quantificationD. risk modelingE. risk mitigation

170 Project Risk _____ .A. should not be calculated for small projects.B. is the probability of each risk event minus the sum of the consequences of potential risk events.C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives.D. cannot be quantified for first time projects.E. B or D

You are working on the cost budget for one project. Which of the following is true() A.This process assigns cost estimates to project activities including risks and contingency plans.B.The cost baseline will be used to measure variances and future project performance.C.This process assigns cost estimates for expected future period operating costs.D.The cost baseline is the expected cost for the project.

A situation in which one of two or more risk events will follow an act, but the precise nature of these events maynot be known and the probabilities of their occurring cannot be objectively assigned, is the definition of:a. Certaintyb. Uncertaintyc. Riskd. Risk adversitye. None of the above

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control

●Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73).(73)A. project management planB. project baselineC. risk response planD. risk baseline

Workarounds are determined during which risk management process? (75).A. Risk identificationB. Quantitative risk analysisC. Plan risk responsesD. Risk monitoring and control

Which software process sorts client login requests and assigns them to a virtual router for RADIUS service?() A.PPPB.AAAC.LCPD.NCP

()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.A.Identity risksB.Control risksC.Plan risk responsesD.Plan risk management

The______process ascertains which risks have the potential Of affecting the proect and documenting the risks' characteristics.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk AnalysisD.Risk Monitoring and Control

( )is not included in Information Security Risk Assessment Process.A.Establishing information security risk criteriaB.Identifying the information security risksC.Formulating an information security risk treatment planD.Analysing the information security risk

You are working on the cost budget for one project. Which of the following is true()A、This process assigns cost estimates to project activities including risks and contingency plans.B、The cost baseline will be used to measure variances and future project performance.C、This process assigns cost estimates for expected future period operating costs.D、The cost baseline is the expected cost for the project.

The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.A、RiskldentificationB、Quantitative Risk AnalysisC、Qualitative Risk AnalysisD、Risk Monitoring and Control

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A、RiskldentificationB、Quantitative RiskAnalysisC、Qualitative RiskAnalysisD、Risk Monitoring and Control

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A、Risk IdentificationB、Quantitative Risk AnalysisC、Qualitative Risk AnalysisD、Risk Monitoring and Control

Which software process sorts client login requests and assigns them to a virtual router for RADIUS service?()A、PPPB、AAAC、LCPD、NCP

单选题You are working on the cost budget for one project. Which of the following is true()AThis process assigns cost estimates to project activities including risks and contingency plans.BThe cost baseline will be used to measure variances and future project performance.CThis process assigns cost estimates for expected future period operating costs.DThe cost baseline is the expected cost for the project.

单选题The()process analyzes the effect of risk events and assigns a numerical rating to those risks.ARisk IdentificationBQuantitative Risk AnalysisCQualitative Risk AnalysisDRisk Monitoring and Control

单选题The()process analyzes the effect of risk events and assigns a numerical rating to those risks.ARiskldentificationBQuantitative RiskAnalysisCQualitative RiskAnalysisDRisk Monitoring and Control