The strategies for handling risk comprise of two main types: negative risks, and positive risks. The goal Of the plan is to minimize threats and maximize opportunities. When dealing with negative risks,there are three main response strategies______,Transfer, Mitigate.A.ChallengeB.ExploitC.AvoidD.Enhance

The strategies for handling risk comprise of two main types: negative risks, and positive risks. The goal Of the plan is to minimize threats and maximize opportunities. When dealing with negative risks,there are three main response strategies______,Transfer, Mitigate.

A.Challenge

B.Exploit

C.Avoid

D.Enhance


相关考题:

● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk Analysis.Risk Monitoring and Control

Risk can be divided into two basic types; business risk and pure (or insurable risk). Of the following, which one(s) fall(s) under business risk?A liability lossB direct property lossC profit lossD personnel-related lossE B and C

By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:A Significantly reduce project risksB eliminate project risksC provide a rational basis for better decision makingD identify risks, their impact(s), and any appropriate responsesE None of the above.

59 By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:A. Significantly reduce project risksB. eliminate project risksC. provide a rational basis for better decision makingD. identify risks, their impact(s), and any appropriate responsesE. None of the above

84 Risk can be divided into two basic types; business risk and pure (or insurable risk). Of the following, which one(s) fall(s) under business risk?A. liability lossB. direct property lossC. profit lossD. personnel-related lossE. B and C

There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.A.shareB.MitigateC.TransferD.Acceptance

●(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame. and risk tolerance of the project constraints of cost, schedule, scope, and quality.(71)A. Quantitative Risk AnalysisB. Qualitative Risk AnalysisC. Enterprise Environmental FactorsD. Risk Management Plan

2 The risk committee at Southern Continents Company (SCC) met to discuss a report by its risk manager, StephanieField. The report focused on a number of risks that applied to a chemicals factory recently acquired by SCC in anothercountry, Southland. She explained that the new risks related to the security of the factory in Southland in respect ofburglary, to the supply of one of the key raw materials that experienced fluctuations in world supply and also anenvironmental risk. The environmental risk, Stephanie explained, was to do with the possibility of poisonousemissions from the Southland factory.The SCC chief executive, Choo Wang, who chaired the risk committee, said that the Southland factory was importantto him for two reasons. First, he said it was strategically important to the company. Second, it was important becausehis own bonuses depended upon it. He said that because he had personally negotiated the purchase of the Southlandfactory, the remunerations committee had included a performance bonus on his salary based on the success of theSouthland investment. He told Stephanie that a performance-related bonus was payable when and if the factoryachieved a certain level of output that Choo considered to be ambitious. ‘I don’t get any bonus at all until we reacha high level of output from the factory,’ he said. ‘So I don’t care what the risks are, we will have to manage them.’Stephanie explained that one of her main concerns arose because the employees at the factory in Southland were notaware of the importance of risk management to SCC. She said that the former owner of the factory paid less attentionto risk issues and so the staff were not as aware of risk as Stephanie would like them to be. ‘I would like to get riskawareness embedded in the culture at the Southland factory,’ she said.Choo Wang said that he knew from Stephanie’s report what the risks were, but that he wanted somebody to explainto him what strategies SCC could use to manage the risks.Required:(a) Describe four strategies that can be used to manage risk and identify, with reasons, an appropriate strategyfor each of the three risks mentioned in the case. (12 marks)

● There are strategies typically deal with threats or risks that may have negative impacts on project objectives if they occur. Some other strategies are suggested to deal with risks with potentially positive impacts. (74) is a risk response strategy that may be adopted for either threats or opportunities.(74) A. ShareB. MitigateC. TransferD. Acceptance

The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control

● Project()is an uncertain event or condition that ,if it occurs ,has a positive or a negative effect on at least one project objective ,such as time ,cost ,scope or quality()A. risk B. problem C. result D. data

听力原文:M: Can you give an example of types of risks Banks face?W: Yes. The major type of risks is called credit risk. It means a counterpart fails to perform. according to a contractual arrangement.Q: What are they talking about?(13)A.A contractual arrangement.B.A counterpart.C.Many types of risks.D.Credit risk.

Banks in international lending face the risks common to all banks: liquidity risk, interest rate risk, credit (asset) risk, and contingent liabilities risk.A.RightB.WrongC.Doesn't say

The______process ascertains which risks have the potential Of affecting the proect and documenting the risks' characteristics.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk AnalysisD.Risk Monitoring and Control

()is the process of identifying individual project risks as well as source of overall project risk,and documenting their characteristics.A.identify risksB.monitor risksC.implement risks responsesD.plan risk management

The strategies for handling risk comprise of two main types: negative risks,and positive risks. The goal of the plan is to minimize threats and maximize opportunities. When dealing with negative risks, there are three main response strategies – ( ) , Transfer, Mitigate. A.Challenge B.Exploit C.AvoiD. D.Enhance

The ( ) process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring anD.Control

Risks other()All Risks and War Risk can be covered if the extra pr- enium should be borne by the buyer.

setting redundant components in subsystem to handle with the risks brought by the defaults of original components,what kind of risk response strategy is this?()A、risk avoidanceB、risk acceptanceC、risk mitigationD、contingency plan

The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.A、RiskldentificationB、Quantitative Risk AnalysisC、Qualitative Risk AnalysisD、Risk Monitoring and Control

()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.A、Quantitative Risk AnalysisB、Qualitative Risk AnalysisC、Enterprise Environmental FactorsD、Risk Management Plan

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A、Risk IdentificationB、Quantitative Risk AnalysisC、Qualitative Risk AnalysisD、Risk Monitoring and Control

The general additional risks including()are covered in all risks coverage.A、risk of shortageB、risk of leakageC、strikes riskD、risk of rust

单选题Which of the following is true?AAll nicknames have a positive meaning.BAll negatives have a negative meaning.CNicknames are endearing.DAll nicknames can be either positive or negative.

单选题The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.ARiskldentificationBQuantitative Risk AnalysisCQualitative Risk AnalysisDRisk Monitoring and Control

单选题The strategies for handling risk comprise of two main types: negative risks, and positive risks. The goal ofthe plan is to minimize threats and maximize opportunities. When dealing with negative risks, there are three main response strategies(),rransfer ,Mitigate.AChallengeBExploitCAvoidDEnhance

单选题The two main types of load cells used in mooring tension gauges are().Adistortion and compressionBhydraulic and mechanicalCmagnetic and applied torqueDfrictionless and hydraulic

单选题()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.AQuantitative Risk AnalysisBQualitative Risk AnalysisCEnterprise Environmental FactorsDRisk Management Plan