168 A work breakdown structure:A. assures all work is identified.B. subdivides the project into manageable segments.C. provides the project sponsor with a time-phase task summary.D. both A and B.E. All of the above.
168 A work breakdown structure:
A. assures all work is identified.
B. subdivides the project into manageable segments.
C. provides the project sponsor with a time-phase task summary.
D. both A and B.
E. All of the above.
相关考题:
GiventhatastaticmethoddoIt()inaclassWorkrepresentsworktobedone,whatblockofcodewillsucceedinstartinganewthreadthatwilldothework?CODEBLOCKa:Runnabler=newRunnable(){publicvoidrun(){Work.doIt();}};Threadt=newThread(r);t.start();CODEBLOCKb:Threadt=newThread(){publicvoidstart(){Work.doIt();}};t.start();CODEBLOCKc:Runnabler=newRunnable(){publicvoidrun(){Work.doIt();}};r.start();CODEBLOCKd:Threadt=newThread(newWork());t.start();CODEBLOCKe:Runnablet=newRunnable(){publicvoidrun(){Work.doIt();}};t.run();
若有以下说明和语句,则以下引用方式中不正确的是()。 struct worker { int no; char *name; }work, *p=work;A.work.noB.(*p).noC.p->noD.work->no
2、若有以下说明和语句,则引用方式不正确的是? struct worker{ int no; char *name; }work, *p=work;A.work.noB.(*p).noC.p->noD.work->no
若有以下说明和语句,则引用方式不正确的是? struct worker{ int no; char *name; }work, *p=work;A.work.noB.(*p).noC.p->noD.work->no