Using the figure in the Special Window, what is the probability of success for Project B?A 0.3B 0.2C 0.35D 0.15E 0.12

Using the figure in the Special Window, what is the probability of success for Project B?

A 0.3

B 0.2

C 0.35

D 0.15

E 0.12


相关考题:

Using the situation stated in the Special window, what is the schedule variance for Case #8?A . 1000B . 2000C . -1000D . -2000E . 0.

Using the situation stated in the Special window, what is present value of $1000 at 12% at the end of 5 years?A . ¥3,605.00B . ¥0.57C . ¥567.00D . ¥892.86E . ¥3.61

Using the situation stated in the Special window, what is the total price variance for direct material?A . ¥140.00B . ¥736.00C . ¥0.02D . ¥-350.00E . ¥5,850.00

Using the situation stated in the Special window, what is the total variable costs for producing one widget?A . ¥1,020B . ¥1,010C . ¥1,015D . ¥20E . None of the above.

Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.A . 2B . 3C . 4D . 5E . 7

Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.A . 2, 10B . 4, 12C . 6, 14D . 7, 15E . 9, 17

Using the figure in the Special window, The Critical path is _____ weeks.A . 21B . 22C . 23D . 24E . 25

Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?A . PB . QC . RD . SE . T

Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?A . 0B . 1C . 2D . 3E . 4

Using the figure in the Special window, The critical path is:A . A-B-GB . C-GC . C-DD . E-FE . A-B-G and C-D

Using the situation stated in the Special window, what is the cost performance index for Case #9?A . 1.1B . 1.91C . 0.83D . 1.2E . None of the above

Using the scenario in the special window, the project manager appears to be a _____ manager.A . 1, 9B . 9, 1C . 1, 1D . 9, 9E . 5, 5

Using the scenario in the special window, the project manager:A will probably spend the weekend reviewing the data.B Won't ask for the report again.C Has a preference for written communication.D Has chosen an inappropriate medium.E Is experiencing communication overload.

Using the diagram in the Special window, what is the probability that Alternative I will be adopted and completed below budget:A 1.4B 0.8C 0.2D 0.12E None of the above

110 Using the figure in the Special window, The critical path is:A. A-B-GB. C-GC. C-DD. E-FE. A-B-G and C-D

111 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?A. 0B. 1C. 2D. 3E. 4

112 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?A. PB. QC. RD. SE. T

116 Using the diagram in the Special window, what is the probability that Alternative I will be adopted and completed below budget:A. 1.4B. 0.8C. 0.2D. 0.12E. None of the above

117 Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.A. 11, 13B. 12, 14C. 13, 15D. 14, 16E. 15, 17

118 Using the figure in the Special Window, what is the probability of success for Project B?A. 0.30B. 0.20C. 0.35D. 0.15E. 0.12

120 Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.A. 2B. 3C. 4D. 5E. 7

124 Using the situation stated in the Special window, what is the total variable costs for producing one widget?A. $1,020B. $1,010C. $1,015D. $20.00E. None of the above

128 Using the situation stated in the Special window, what is present value of $1000 at 12% at the end of 5 years?A. $3605.00B. $0.57C. $567.00D. $892.86E. $3.61

138 Using the scenario in the special window, the project manager appears to be a _____ manager. A. 1, 9B. 9, 1C. 1, 1D. 9, 9E. 5, 5

139 Using the scenario in the special window, the project manager:A. will probably spend the weekend reviewing the data.B. Won't ask for the report again.C. Has a preference for written communication.D. Has chosen an inappropriate medium.E. Is experiencing communication overload

200 Using the figure in the Special Window, what is the probability of success for Project B?A. 0.30B. 0.20C. 0.35D.0.15E.0.12

20 Using the scenario in the special window, the project manager appears to be a _____ manager.A. 1, 9B. 9, 1C. 1, 1D. 9, 9E. 5, 5