110 Using the figure in the Special window, The critical path is:A. A-B-GB. C-GC. C-DD. E-FE. A-B-G and C-D
110 Using the figure in the Special window, The critical path is:
A. A-B-G
B. C-G
C. C-D
D. E-F
E. A-B-G and C-D
相关考题:
Using the WBS shown in the Special window, a typical work package would be:ASoftware developmentBSystems designCCodingDA, B, and CENone of the above.
Using the table in the Special window, Which task is completed?A.dig holeB.remove debrisC.surveyD.set formsE.place concrete
Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.A . 0.5B . 1C . 1.8D . 2.2E . 2.8
Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a taskA . 8B . 8.8C . 9.1D . 9.7E . 10.5
Using the situation stated in the Special window, which WBS element is behind schedule but under budget?A . Element PB . Element QC . Element RD . Element SE None of the above.
Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.A . 2B . 3C . 4D . 5E . 7
Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.A . 2, 10B . 4, 12C . 6, 14D . 7, 15E . 9, 17
Using the figure in the Special window, The Critical path is _____ weeks.A . 21B . 22C . 23D . 24E . 25
Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?A . PB . QC . RD . SE . T
Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?A . 0B . 1C . 2D . 3E . 4
Using the figure in the Special window, The critical path is:A . A-B-GB . C-GC . C-DD . E-FE . A-B-G and C-D
100 Using the situation the the Special window:A. Productivity will increaseB. His decisions will promote high satisfaction among his teamC. His decisions will require less timeD. All of the aboveE. A and C only
101 Using the situation stated in the Special window, which WBS element is behind schedule but under budget?A. Element PB. Element QC. Element RD. Element SE. None of the above
103 Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:A. 0.875B. 1.14C. 0.952D. 0.833E. 1.20
108 Using the situation stated in the Special window, the labor rate cost variance is:A. $66,927B. $68,329C. $386D. -$0.22E. $18.36
111 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?A. 0B. 1C. 2D. 3E. 4
112 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?A. PB. QC. RD. SE. T
114 Using the figure in the Special window, The Critical path is _____ weeks.A. 21B. 22C. 23D. 24E. 25
117 Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.A. 11, 13B. 12, 14C. 13, 15D. 14, 16E. 15, 17
118 Using the figure in the Special Window, what is the probability of success for Project B?A. 0.30B. 0.20C. 0.35D. 0.15E. 0.12
120 Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.A. 2B. 3C. 4D. 5E. 7
121 Using the WBS in the Special window, an instance of a work package is:A. Build houseB. ExcavateC. Prepare FoundationD. B and CE. None of the above
126 Using the situation stated in the Special window, what is the labor rate cost variance?A. $5500.00B. $1500.00C. -$100.00D. -$0.10E. $5600.00
133 Using the WBS shown in the Special window, a typical work package would be:A. Software developmentB. Systems designC. CodingD. A, B, and CE. None of the above
192 Using the figure in the Special window, The critical path is:A. A-B-GB. C-GC. C-DD. E-FE. A-B-G and C-D
200 Using the figure in the Special Window, what is the probability of success for Project B?A. 0.30B. 0.20C. 0.35D.0.15E.0.12
● Using the WBS shown in the Special window, a typical work package would be:A Software developmentB Systems designC CodingD A, B, and CE None of the above.