The way a project manager sends and receives information depends upon:A How others relate to the project managerB The project manager's level in the organizational hierarchyC the size and nature of the projectD the project manager's salary and ageE the number of projects going on at one time in the company

The way a project manager sends and receives information depends upon:

A How others relate to the project manager

B The project manager's level in the organizational hierarchy

C the size and nature of the project

D the project manager's salary and age

E the number of projects going on at one time in the company


相关考题:

The quality objectives are approved in the conceptual stage of the project by the:A . Project EngineerB . Project ManagerC . Functional ManagerD . Quality Assurance ManagerE . Project Owner

Control chart theory is based on the differentiation of the causes of variations in quality. Variations may be produced by assignable causes. All of the following are examples of assignable causes except:A . differences among machines.B . differences among workers.C . differences among materials.D . differences in each of these factors over time.E . None of the above (all are examples)

The Quality Risk _____ .A is minimized through continuous monitoring.B is considered a long term risk.C will be reflected in the in-service life of the project result.D B and CE All of the above.

11 To determine whether or not the employee correctly understands the message, the project manager needs to:A. reduce the filteringB. eliminate barriersC. obtain feedbackD. use more than one mediumE. use all of the above.

一般来说在成本合同中对全同方进行补偿的依据是 ( )A.实际花费与合同方付出的努力有关B.完成合同所需的时间C.合同中列出的需交付的产品及服务D.所使用的资源数量

111 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?A. 0B. 1C. 2D. 3E. 4

一个项目的启动费用是$1,500。在第一年末,损失$100的可能性是 0.3,而收入$2,000 的可能性是0.7。在第二年末损失$200的可能性是0.4而收入$5,000的可能性是 0.6。假如年利率为10%,计算项目的净现值是多少?a. $3,254。b. $2,158c. $450d. (-$200)

你的公司,一个会议管理鹟,正要向 新的领域发展。目前政府部门发出了一个有关历史性研究的部标邀请,你们公司投了标,并且最终竞标成功。而你被任命这个项目的经理,成为政府部门的第一个历史性研究项目的项目经理。然而不幸的是,你的工作成果没有满足政府对于历史性研究的标准。公司的主席刚刚从政府机关的签约官收到正式通知,因此,这个项目将立即中止。现在你必须A、 将项目从开始到目前的这段时间内已有的成果交给合同管理部门的技术代表B、 记录获得的经验教训并且为记录作索引C、 对项目已经完成的工作记录,明确已经到达的水平和程度D、 关闭项目办公室并且将所有的项目成员重新分配到新的岗位上

假设时范围启动过程的有效输出,执行项目前,每个假设必须被确定为:A、 约束条件B、 风险C、 可交付结果D、 问题

权变措施是指A、对负面风险事件的一个应急反应B、当没有预料到的事情发生时遵循一个行动计划C、对风险管理计划中描述的风险的具体回应D、一个前瞻性的、有计划的风险应对措施

PRET和CPM的主要区别在于PERT:( )A.在计算进度计划时使用分布的平均值(预期值)B.计算时差时使用最可能估算C.通过计算时差来确定哪些活动的进度最不灵活D.在图中包括了非序列活动,如回环或条件分支