Parametric cost estimating involvesA.using the WBS to do bottom up estimatesB.defining the perimeters of the life-cycleC.calculating the individual estimates of work packagesD.using a statistical model to estimate costsE.A and C

Parametric cost estimating involves

A.using the WBS to do bottom up estimates

B.defining the perimeters of the life-cycle

C.calculating the individual estimates of work packages

D.using a statistical model to estimate costs

E.A and C


相关考题:

Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.A . Definitive, bottom up.B . Analogy, top down.C . Parametric, bottom up.D . Parametric, top down.E . Analogy, bottom up.

The three most common types of project cost estimates are:A . Order of magnitude, parametric, and budget.B . Parametric, definitive and top down.C . Order of magnitude, definitive and bottom up.D . Order of magnitude, budget and definitive.E . Analogy, parametric and top down.

140 The three most common types of project cost estimates are:A. Order of magnitude, parametric, and budget.B. Parametric, definitive and top down.C. Order of magnitude, definitive and bottom up.D. Order of magnitude, budget and definitive.E. Analogy, parametric and top down

168 Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.A. Definitive, bottom up.B. Analogy, top down.C. Parametric, bottom up.D. Parametric, top down.E. Analogy, bottom up

22 The three most common types of project cost estimates are:A. Order of magnitude, parametric, and budget.B. Parametric, definitive and top down.C. Order of magnitude, definitive and bottom up.D. Order of magnitude, budget and definitive.E. Analogy, parametric and top down

50 Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.A. Definitive, bottom up.B. Analogy, top down.C. Parametric, bottom up.D. Parametric, top down.E. Analogy, bottom up.

目前在数字系统的设计中,主要采用Bottom-UP设计为主。() 此题为判断题(对,错)。

Teachers who adont the __________model for reading comprehension may start teaching a textby introducing new vocabulary and structures.A.parallelB.serialC.too-downD.bottom-up

当一国电信管制机构希望用标杆法进行成本测算时,其核心工作就是()。A:建立成本分摊系统B:建立Top-Down模型C:找到“成本标杆”D:建立Bottom-Up模型

开展物质在用量研究可采用Bottom-up 和Top-down 方法() A study of material in-use stock can be carried out by using either the bottom-up or top-down method()