Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:A . 0.875B . 1.14C . 0.952D . 0.833E . 1.2
Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:
A . 0.875
B . 1.14
C . 0.952
D . 0.833
E . 1.2
相关考题:
Using the situation stated in the Special window, what is the schedule variance for Case #8?A . 1000B . 2000C . -1000D . -2000E . 0.
Using the situation stated in the Special window, what is present value of $1000 at 12% at the end of 5 years?A . ¥3,605.00B . ¥0.57C . ¥567.00D . ¥892.86E . ¥3.61
Using the situation stated in the Special window, what is net present value of an annual income flow of $1600 at 14% over the next three years?A . ¥3,713.60B . ¥0.68C . ¥1,080.00D . ¥476.19E . ¥2.32
Using the situation stated in the Special window, what is the labor rate cost variance?A . ¥5,500.00B . ¥1,500.00C . ¥-100.00D . ¥-0.10E . ¥5,600.00
Using the situation stated in the Special window, what is the total price variance for direct material?A . ¥140.00B . ¥736.00C . ¥0.02D . ¥-350.00E . ¥5,850.00
Using the situation stated in the Special window, what is the total variable costs for producing one widget?A . ¥1,020B . ¥1,010C . ¥1,015D . ¥20E . None of the above.
Using the situation stated in the Special window, the labor rate cost variance is:A . ¥66,927B . ¥68,329C . ¥386D . ¥-0E . ¥18.36
Using the situation stated in the Special window, the total price variance of direct material is:A . ¥80,245B . ¥-4,236C . ¥-3,479D . ¥1E . ¥83,994.00
Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.A . Become worse, become worseB . Become worse, improvedC . Improved, increasedD . Improved, become worseE . None of the above are correct
Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent.A . Over, 16.66B . Under, 16.66C . Over, 10.0D . Under, 10.0E . None of the above.
Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:A . 1.1B . 0.9C . 0.956D . 1.15E . 0.869
Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?A . Element PB . Element QC . Element RD . Element SE . None of the above.
Using the situation stated in the Special window, which WBS element is behind schedule but under budget?A . Element PB . Element QC . Element RD . Element SE None of the above.
Using the situation stated in the Special window, what is the cost performance index for Case #9?A . 1.1B . 1.91C . 0.83D . 1.2E . None of the above
101 Using the situation stated in the Special window, which WBS element is behind schedule but under budget?A. Element PB. Element QC. Element RD. Element SE. None of the above
102 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?A. Element PB. Element QC. Element RD. Element SE. None of the above
103 Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:A. 0.875B. 1.14C. 0.952D. 0.833E. 1.20
104 Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:A. 1.10B. 0.90C. 0.956D. 1.15E. 0.869
106 Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.A. Become worse, become worseB. Become worse, improvedC. Improved, increasedD. Improved, become worseE. None of the above are correct
108 Using the situation stated in the Special window, the labor rate cost variance is:A. $66,927B. $68,329C. $386D. -$0.22E. $18.36
109 Using the situation stated in the Special window, what is the total fixed costs for manufacturing the widgets?A. $3,000B. $27,000C. $27,270D. $1,335E. $1,000
124 Using the situation stated in the Special window, what is the total variable costs for producing one widget?A. $1,020B. $1,010C. $1,015D. $20.00E. None of the above
126 Using the situation stated in the Special window, what is the labor rate cost variance?A. $5500.00B. $1500.00C. -$100.00D. -$0.10E. $5600.00
130 Using the situation stated in the Special window, what is the schedule variance for Case #8? A. 1000B. 2000C. -1000D. -2000E. 0
132 Using the situation stated in the Special window, what is the cost performance index for Case #9?A. 1.10B. 1.91C. 0.83D. 1.20E. None of the above
The cost performance index(CPI) is the ratio of earned value to () and can be used to estimate the projected cost of completing the project.A.cost varianceB.planned costC.planned costD.actual cost
The cost performance index(CPI) is the ratio of earned value to ( ) and can be used to estimate the projected cost of completing the project.A.cost variance B.planned cost C.Planned valueD.actual cost