单选题Companycom is purchasing a p5 590 which was configured with 60 Amp line cords. They have just indicated that their large datacenter is already wired for 100 Amp power circuits in the location where the server will be installed. What would be the recommended action?()AUse the 60 Amp line cordsBChange the 100 Amp connector to a 60 Amp circuitCSubmit an RPQ to order the p5 590 with 100 Amp power cordsDChange the configuration and order the p5 590 with the 100 Amp power cords

单选题
Companycom is purchasing a p5 590 which was configured with 60 Amp line cords. They have just indicated that their large datacenter is already wired for 100 Amp power circuits in the location where the server will be installed. What would be the recommended action?()
A

Use the 60 Amp line cords

B

Change the 100 Amp connector to a 60 Amp circuit

C

Submit an RPQ to order the p5 590 with 100 Amp power cords

D

Change the configuration and order the p5 590 with the 100 Amp power cords


参考解析

解析: 暂无解析

相关考题:

Companycom is purchasing a p5 595 as part of a large server consolidation. They are planning on using micropartitioning and Virtual IO to consolidate small machines. They used the rPerf numbers for AIX 5.3 to size their solutions. They discovered that their application is not yet certified on AIX 5.3, so they will have to use AIX 5.2. What changes should be made to their configuration?()A、Increase memoryB、Add more adaptersC、Increase both processors and adaptersD、Increase the number of processors by 20 - 30%

Companycom is considering a partitioned solution which will require cumulative rPerf total of 150. The original sizing came back recommending a 32-way p5 590. However, they have a requirement for future scalability and availability is important. Which of the following would be the best reason to recommend a p5 595?()A、The p5 595 would allow for CODB、The p5 595 includes the Advanced Power Virtualization hardware and softwareC、The p5 595 is priced the same as the p5 590 given the same number/type of CPUsD、The p5 595 performance would be equivalent to the p5 590 given the same number/type of CPUs

A customer wants to take advantage of IBM’s Micro-Partitioning capabilities for their new AIX applications.   The pSeries technical specialist should recommend purchasing which of the following?()A、p5 hardware, AIX 5.2, Virtual I/O ServerB、POWER4 hardware, AIX 5.3, Virtual I/O Server,C、p5 hardware, AIX 5.3, Advanced POWER Virtualization featureD、POWER4 hardware, AIX 5.2, Advanced POWER Virtualization feature

Companycom is currently using a p690 and has just ordered a p5 590. They prefer to run in full system partition mode, since their application will utilize all the resources in the machine, and they don't want the overhead of an LPAR. What is the best response to the customer about the POWER5 capabilities?()A、POWER5 runs in an SMP mode as defaultB、POWER5 can run in a full system mode the same as the p690C、POWER5 can run in full system mode with the purchase of PLMD、POWER5 can run in a full system mode, but it is in LPAR mode

Companycom has a p690 server with unused fiber (HBA) host bus adapters (feature code 6228) that they would like to reuse. They are interested in implementing Advanced Power Virtualization features particularly Virtual IO. What is the best way to proceed?()A、Upgrade the p690 to a p5 590 server running AIX 5.3B、Upgrade the p690 server to AIX 5.3 and implement Advanced Power VirtualizationC、Purchase a p5 590 with minimum resources and simply reuse the p690 unused fiber HBA adaptersD、Purchase a p5 590 that has all the needed resources and adapters for Advanced Power Virtualization

Companycom is purchasing a 64-way p5 595. They have determined the location for the server is in a datacenter which does not have a raised floor. Which of the following would best meet the server requirements?()A、The server must be installed into a location with a raised floor for optimum system cooling and cable management.B、The server should be purchased as a p5 590 and then upgraded to a p5 595. This will eliminate the need for a raised floor environment.C、The server should be purchased as 32-way p5 595 and then upgraded to a 64-way. This will eliminate the need for a raised floor environment.D、The server can be installed into a location without a raised floor if an RPQ is obtained. It is a strong IBM recommendation for a raised floor, not a requirement.

Companycom wants the application server LPAR to communicate with the database LPAR on a p5 590 without using network adapters. What does the customer need to install?()A、VIO ServerB、AIX 5.2 ML4C、Shared Ethernet AdapterD、AIX 5.3 with Advanced Power Virtualization

Companycom has successfully established their p5 LPAR environment on a POWER5 p5 590 running AIX 5.2. They are now ready to move to Virtual IO. What would be required to do Virtual IO?()A、Apply APAR IY62262 to the current AIX 5.2 Maintenance level 04. Virtual IO Server is not required. B、Purchase Advanced POWER Virtualization software, upgrade to AIX 5.3 maintenance level 1 and apply APAR IY60349. Virtual IO Server is not required. C、Verify that there are enough resources to add a Virtual IO Server, upgrade to AIX 5.3 with APAR IY60349, create a Virtual IO Server after applying APAR IY62262. D、Verify that there are enough resources to add a Virtual IO Server, create a Virtual IO Server and apply APAR IY62262, verify that the system is at AIX 5.2 with Maintenance level 04.

A client has an existing p5 570 that is directly connected to a HMC. The customer will be purchasing another p5 570. Which of the following solutions would be appropriate to provide HMC connectivity to the second p5 570?()A、Implement a proxy server to provide multiple sources to one destination B、Purchase an additional Ethernet adapter for each p5 570 to provide connectivity between the two C、Purchase a network hub or switch so both p5 570s can connect to the single HMC D、Purchase an additional HMC since multiple HMC are required when more than one POWER5 Enterprise class server is used Purchase an additional HMC since multiple HMC? are required when more than one POWER5 Enterprise class server is used

Companycom is purchasing a p5 590 which was configured with 60 Amp line cords. They have just indicated that their large datacenter is already wired for 100 Amp power circuits in the location where the server will be installed. What would be the recommended action?()A、Use the 60 Amp line cordsB、Change the 100 Amp connector to a 60 Amp circuitC、Submit an RPQ to order the p5 590 with 100 Amp power cordsD、Change the configuration and order the p5 590 with the 100 Amp power cords

A customer purchased a new IBM xSeries x445.  They already have a non-IBM industry standard rack with 14U of open space that is being considered to house the new server.  The rack houses an existing UPS unit for the entire rack.  Which of the following questions is most important to ensure that the power in the datacenter environment is ready for the initial install?()A、Have optional Fibre Channel and Ethernet switches been installed in the server?B、What is the available kVA value of the UPS?C、Are there sufficient empty socket outlets in the UPS?D、What is the impact on the power consumption of the data center cooling system?

A client tried to upgrade the system firmware on a p5 590, but it failed. What is the minimum requirement to update the system firmware from the HMC if inventory scout is already installed?()A、A public internet connectionB、All of the Logical Partitions need to be activeC、One partition must be configured with Service AuthorityD、A local Repository must be configured prior to the update

Companycom is moving their application to a p5 590 and at the same time moving to a new version of the application. The customer knows only about the resource requirements of the old version. Which of the following is the best method to migrate their application to POWER5?()A、Add CPU and memory COD so they have room to grow if requiredB、Make the server configuration twice as large as the current requirementC、Configure the server for the current capacity requirementsD、Make the server configuration a little larger than the current capacity requirements

单选题Companycom is purchasing a p5 595 as part of a large server consolidation. They are planning on using micropartitioning and Virtual IO to consolidate small machines. They used the rPerf numbers for AIX 5.3 to size their solutions. They discovered that their application is not yet certified on AIX 5.3, so they will have to use AIX 5.2. What changes should be made to their configuration?()AIncrease memoryBAdd more adaptersCIncrease both processors and adaptersDIncrease the number of processors by 20 - 30%

单选题A client has an existing p5 570 that is directly connected to a HMC. The customer will be purchasing another p5 570. Which of the following solutions would be appropriate to provide HMC connectivity to the second p5 570?()AImplement a proxy server to provide multiple sources to one destination BPurchase an additional Ethernet adapter for each p5 570 to provide connectivity between the two CPurchase a network hub or switch so both p5 570s can connect to the single HMC DPurchase an additional HMC since multiple HMC are required when more than one POWER5 Enterprise class server is used Purchase an additional HMC since multiple HMC? are required when more than one POWER5 Enterprise class server is used

单选题Companycom has successfully established their p5 LPAR environment on a POWER5 p5 590 running AIX 5.2. They are now ready to move to Virtual IO. What would be required to do Virtual IO?()AApply APAR IY62262 to the current AIX 5.2 Maintenance level 04. Virtual IO Server is not required. BPurchase Advanced POWER Virtualization software, upgrade to AIX 5.3 maintenance level 1 and apply APAR IY60349. Virtual IO Server is not required. CVerify that there are enough resources to add a Virtual IO Server, upgrade to AIX 5.3 with APAR IY60349, create a Virtual IO Server after applying APAR IY62262. DVerify that there are enough resources to add a Virtual IO Server, create a Virtual IO Server and apply APAR IY62262, verify that the system is at AIX 5.2 with Maintenance level 04.

单选题Companycom is purchasing a 64-way p5 595. They have determined the location for the server is in a datacenter which does not have a raised floor. Which of the following would best meet the server requirements?()AThe server must be installed into a location with a raised floor for optimum system cooling and cable management.BThe server should be purchased as a p5 590 and then upgraded to a p5 595. This will eliminate the need for a raised floor environment.CThe server should be purchased as 32-way p5 595 and then upgraded to a 64-way. This will eliminate the need for a raised floor environment.DThe server can be installed into a location without a raised floor if an RPQ is obtained. It is a strong IBM recommendation for a raised floor, not a requirement.

单选题Companycom is purchasing a p5 590 which was configured with 60 Amp line cords. They have just indicated that their large datacenter is already wired for 100 Amp power circuits in the location where the server will be installed. What would be the recommended action?()AUse the 60 Amp line cordsBChange the 100 Amp connector to a 60 Amp circuitCSubmit an RPQ to order the p5 590 with 100 Amp power cordsDChange the configuration and order the p5 590 with the 100 Amp power cords

单选题Companycom wants the application server LPAR to communicate with the database LPAR on a p5 590 without using network adapters. What does the customer need to install?()AVIO ServerBAIX 5.2 ML4CShared Ethernet AdapterDAIX 5.3 with Advanced Power Virtualization

单选题Companycom is moving their application to a p5 590 and at the same time moving to a new version of the application. The customer knows only about the resource requirements of the old version. Which of the following is the best method to migrate their application to POWER5?()AAdd CPU and memory COD so they have room to grow if requiredBMake the server configuration twice as large as the current requirementCConfigure the server for the current capacity requirementsDMake the server configuration a little larger than the current capacity requirements

单选题Companycom is purchasing a p5 590 which was configured with 60 Amp line cords. They have just indicated that their large datacenter is already wired for 100 Amp power circuits in the location where the server will be installed. What would be the recommended action?()AUse the 60 Amp line cordsBChange the 100 Amp connector to a 60 Amp circuitCSubmit an RPQ to order the p5 590 with 100 Amp power cordsDChange the configuration and order the p5 590 with the 100 Amp power cords

单选题A client tried to upgrade the system firmware on a p5 590, but it failed. What is the minimum requirement to update the system firmware from the HMC if inventory scout is already installed?()AA public internet connectionBAll of the Logical Partitions need to be activeCOne partition must be configured with Service AuthorityDA local Repository must be configured prior to the update

单选题A customer wants to know what version of DirectX the current workstation has installed. Which of the following command line tools would the customer use?()AeditBsysteminfoCgpedit.mscDdxdiag

单选题Companycom has a p690 server with unused fiber (HBA) host bus adapters (feature code 6228) that they would like to reuse. They are interested in implementing Advanced Power Virtualization features particularly Virtual IO. What is the best way to proceed?()AUpgrade the p690 to a p5 590 server running AIX 5.3BUpgrade the p690 server to AIX 5.3 and implement Advanced Power VirtualizationCPurchase a p5 590 with minimum resources and simply reuse the p690 unused fiber HBA adaptersDPurchase a p5 590 that has all the needed resources and adapters for Advanced Power Virtualization

单选题Companycom is considering a partitioned solution which will require cumulative rPerf total of 150. The original sizing came back recommending a 32-way p5 590. However, they have a requirement for future scalability and availability is important. Which of the following would be the best reason to recommend a p5 595?()AThe p5 595 would allow for CODBThe p5 595 includes the Advanced Power Virtualization hardware and softwareCThe p5 595 is priced the same as the p5 590 given the same number/type of CPUsDThe p5 595 performance would be equivalent to the p5 590 given the same number/type of CPUs

单选题Companycom has just added some new disk drives to a p5 590. The customer needs to know the largest Logical Track Group that these drives will support. What is the best way to locate this information?()AUse lquerypv to read the driveBUse lspv and look at PP Size valueCLook on the outside of the drive itselfDUse bootinfo to find the LTG on the drive

单选题When booting the p5 590 server in full system partition mode, which location is preferred for the fastest boot?()AA SAN deviceBFirst I/O drawerCAny I/O drawer within the main frameDFirst I/O drawer within the expansion frame

单选题Companycom has a p690 and currently has eight LPARs. They have purchased a p5 590 and wish to migrate their eight LPARs to the new server. The LPARs are running either AIX 5.2 or AIX 5.3 with the current maintenance. What is the LEAST disruptive method for this activity?()ANew install of AIXBMigrate the 7040-61DCUtilize alt_disk_installDUse the enterprise back up strategy