单选题Companycom has successfully established their p5 LPAR environment on a POWER5 p5 590 running AIX 5.2. They are now ready to move to Virtual IO. What would be required to do Virtual IO?()AApply APAR IY62262 to the current AIX 5.2 Maintenance level 04. Virtual IO Server is not required. BPurchase Advanced POWER Virtualization software, upgrade to AIX 5.3 maintenance level 1 and apply APAR IY60349. Virtual IO Server is not required. CVerify that there are enough resources to add a Virtual IO Server, upgrade to AIX 5.3 with APAR IY60349, create a Virtual IO Server after applying APAR IY62262. DVerify that there are enough resources to add a Virtual IO Server, create a Virtual IO Server and apply APAR IY62262, verify that the system is at AIX 5.2 with Maintenance level 04.
单选题
Companycom has successfully established their p5 LPAR environment on a POWER5 p5 590 running AIX 5.2. They are now ready to move to Virtual IO. What would be required to do Virtual IO?()
A
Apply APAR IY62262 to the current AIX 5.2 Maintenance level 04. Virtual IO Server is not required.
B
Purchase Advanced POWER Virtualization software, upgrade to AIX 5.3 maintenance level 1 and apply APAR IY60349. Virtual IO Server is not required.
C
Verify that there are enough resources to add a Virtual IO Server, upgrade to AIX 5.3 with APAR IY60349, create a Virtual IO Server after applying APAR IY62262.
D
Verify that there are enough resources to add a Virtual IO Server, create a Virtual IO Server and apply APAR IY62262, verify that the system is at AIX 5.2 with Maintenance level 04.
参考解析
解析:
暂无解析
相关考题:
Companycom has a p690 and currently has eight LPARs. They have purchased a p5 590 and wish to migrate their eight LPARs to the new server. The LPARs are running either AIX 5.2 or AIX 5.3 with the current maintenance. What is the LEAST disruptive method for this activity?()A、New install of AIXB、Migrate the 7040-61DC、Utilize alt_disk_installD、Use the enterprise back up strategy
Companycom has a system running AIX 5.2 and wants to upgrade to AIX 5.3. What method would provide the quickest recovery if the upgrade failed?()A、Use alt_disk_installB、Backup image to NIM serverC、Backup using mksysb to DVD-RAMD、Apply the upgrade and do not commit
Companycom has a p5 590 that has their production LPAR, their Tivoli Storage Manager (TSM) LPAR, and several other LPARs. What method would provide connectivity between the production LPAR, and the TSM LPAR, but be isolated from the other LPARs in the system without utilizing a Virtual IO Server or physical adapter resources?()A、Use shared memory and semaphores to transfer the data to the TSM LPARB、Provide gigabit Ethernet adapters in each LPAR and run a crossover cableC、Create a Virtual Ethernet between the production server and the TSM LPARsD、Create a Virtual Ethernet between the TSM server LPAR and the non-production LPARs
Companycom is migrating from p670 systems running AIX 5.2 to p5 595 systems running AIX 5.3. They will be changing out only the system units. They will re-use the existing 61D drawers and adapters with the new p5 595 systems. What compatibility issue must be considered?() A、APV features are not supported for some legacy POWER4 adaptersB、APV will require the most current maintenance level for AIX 5.2C、APV features will require that legacy POWER4 adapters be updated with new microcodeD、The Virtual IO Server must run AIX 5.3 and the LPARs can run either AIX 5.2 or AIX 5.3
Companycom has a p690 server with unused fiber (HBA) host bus adapters (feature code 6228) that they would like to reuse. They are interested in implementing Advanced Power Virtualization features particularly Virtual IO. What is the best way to proceed?()A、Upgrade the p690 to a p5 590 server running AIX 5.3B、Upgrade the p690 server to AIX 5.3 and implement Advanced Power VirtualizationC、Purchase a p5 590 with minimum resources and simply reuse the p690 unused fiber HBA adaptersD、Purchase a p5 590 that has all the needed resources and adapters for Advanced Power Virtualization
A client has an existing Logical Partition (LPAR) on a p650 running AIX 5.2 and will be porting this LPAR to a p5 590. A mksysb has been run to tape, and a compatible tape drive is available and allocated to the target LPAR on the p5 590. What additional resource needs to be available on the p5 590?()A、A CD or DVD with installation mediaB、An internal SCSI adapter in the target LPARC、An Ethernet adapter for access to an FTP serverD、Advanced Power Virtualization feature of the p5 590
Companycom has a Linux LPAR on a p5 570 server. The 3rd party storage subsystem devices are not supported by Linux. How would access be provided to the storage subsystem devices for this Linux LPAR?()A、Daisy chain the unsupported 3rd party storage subsystem devices with the local SCSI disk drive B、Assuming the 3rd party storage subsystem has AIX support, enable access through a Virtual IO Server C、Assuming the 3rd party storage subsystem has AIX support, implement the Linux partition within an AIX partition D、3rd party storage is not an option for p5 570 servers and therefore only IBM disk subsystems can be considered as a solution
Companycom is planning on upgrading from a pSeries S85 running AIX 4.3.3 to a p5 570 with an HMC. The new server will run AIX 5L 5.2. What should be performed prior to the migration?()A、Verify the ISV application runs on AIX 5.2B、Power4 to POWER5 upgrades are not supported without a application recompileC、Check the placement and size of the boot logical volume and disk space requirements on the S85D、AIX 4.3.3 to AIX 5L 5.2 migrations are perfectly compatible so nothing needs to be checked
Companycom wants the application server LPAR to communicate with the database LPAR on a p5 590 without using network adapters. What does the customer need to install?()A、VIO ServerB、AIX 5.2 ML4C、Shared Ethernet AdapterD、AIX 5.3 with Advanced Power Virtualization
Companycom has successfully established their p5 LPAR environment on a POWER5 p5 590 running AIX 5.2. They are now ready to move to Virtual IO. What would be required to do Virtual IO?()A、Apply APAR IY62262 to the current AIX 5.2 Maintenance level 04. Virtual IO Server is not required. B、Purchase Advanced POWER Virtualization software, upgrade to AIX 5.3 maintenance level 1 and apply APAR IY60349. Virtual IO Server is not required. C、Verify that there are enough resources to add a Virtual IO Server, upgrade to AIX 5.3 with APAR IY60349, create a Virtual IO Server after applying APAR IY62262. D、Verify that there are enough resources to add a Virtual IO Server, create a Virtual IO Server and apply APAR IY62262, verify that the system is at AIX 5.2 with Maintenance level 04.
A large customer is consolidating their pSeries systems onto a p5 590. They will have a requirement for a single device (disk, lun) to have multiple paths through different adapters in a single LPAR. The primary applications were written for AIX 5.2. Which of the following would be the recommended solution to satisfy this requirement?()A、Assign the adapters to a Virtual IO partitionB、Use the MPIO function included in AIX 5.2C、Migrate the application to AIX 5.3 and use the MPIO functionD、Set up two Virtual IO partitions and attach both partitions to the device
Companycom has a requirement for an LPAR in their p5 595 to run SUSE Linux. They also require an adapter that is not currently supported in Linux. Which of the following would be the best solution to recommend?()A、Assign the adapter to an IO Hosting partitionB、Use AIX 5L affinity to move the application from SUSE to AIXC、Use AIX 5.3 drivers to install the adapter in the Linux LPARD、Assign the adapter to an AIX 5.3 partition running Linux Affinity
单选题A client has an existing Logical Partition (LPAR) on a p650 running AIX 5.2 and will be porting this LPAR to a p5 590. A mksysb has been run to tape, and a compatible tape drive is available and allocated to the target LPAR on the p5 590. What additional resource needs to be available on the p5 590?()AA CD or DVD with installation mediaBAn internal SCSI adapter in the target LPARCAn Ethernet adapter for access to an FTP serverDAdvanced Power Virtualization feature of the p5 590
单选题Companycom is purchasing a p5 595 as part of a large server consolidation. They are planning on using micropartitioning and Virtual IO to consolidate small machines. They used the rPerf numbers for AIX 5.3 to size their solutions. They discovered that their application is not yet certified on AIX 5.3, so they will have to use AIX 5.2. What changes should be made to their configuration?()AIncrease memoryBAdd more adaptersCIncrease both processors and adaptersDIncrease the number of processors by 20 - 30%
单选题A large customer is consolidating their pSeries systems onto a p5 590. They will have a requirement for a single device (disk, lun) to have multiple paths through different adapters in a single LPAR. The primary applications were written for AIX 5.2. Which of the following would be the recommended solution to satisfy this requirement?()AAssign the adapters to a Virtual IO partitionBUse the MPIO function included in AIX 5.2CMigrate the application to AIX 5.3 and use the MPIO functionDSet up two Virtual IO partitions and attach both partitions to the device
单选题Companycom is planning on upgrading from a pSeries S85 running AIX 4.3.3 to a p5 570 with an HMC. The new server will run AIX 5L 5.2. What should be performed prior to the migration?()AVerify the ISV application runs on AIX 5.2BPower4 to POWER5 upgrades are not supported without a application recompileCCheck the placement and size of the boot logical volume and disk space requirements on the S85DAIX 4.3.3 to AIX 5L 5.2 migrations are perfectly compatible so nothing needs to be checked
单选题Companycom has a p690 server with unused fiber (HBA) host bus adapters (feature code 6228) that they would like to reuse. They are interested in implementing Advanced Power Virtualization features particularly Virtual IO. What is the best way to proceed?()AUpgrade the p690 to a p5 590 server running AIX 5.3BUpgrade the p690 server to AIX 5.3 and implement Advanced Power VirtualizationCPurchase a p5 590 with minimum resources and simply reuse the p690 unused fiber HBA adaptersDPurchase a p5 590 that has all the needed resources and adapters for Advanced Power Virtualization
单选题Companycom has successfully established their p5 LPAR environment on a POWER5 p5 590 running AIX 5.2. They are now ready to move to Virtual IO. What would be required to do Virtual IO?()AApply APAR IY62262 to the current AIX 5.2 Maintenance level 04. Virtual IO Server is not required. BPurchase Advanced POWER Virtualization software, upgrade to AIX 5.3 maintenance level 1 and apply APAR IY60349. Virtual IO Server is not required. CVerify that there are enough resources to add a Virtual IO Server, upgrade to AIX 5.3 with APAR IY60349, create a Virtual IO Server after applying APAR IY62262. DVerify that there are enough resources to add a Virtual IO Server, create a Virtual IO Server and apply APAR IY62262, verify that the system is at AIX 5.2 with Maintenance level 04.
单选题Companycom has a p5 590 that has their production LPAR, their Tivoli Storage Manager (TSM) LPAR, and several other LPARs. What method would provide connectivity between the production LPAR, and the TSM LPAR, but be isolated from the other LPARs in the system without utilizing a Virtual IO Server or physical adapter resources?()AUse shared memory and semaphores to transfer the data to the TSM LPARBProvide gigabit Ethernet adapters in each LPAR and run a crossover cableCCreate a Virtual Ethernet between the production server and the TSM LPARsDCreate a Virtual Ethernet between the TSM server LPAR and the non-production LPARs
单选题Companycom is migrating from p670 systems running AIX 5.2 to p5 595 systems running AIX 5.3. They will be changing out only the system units. They will re-use the existing 61D drawers and adapters with the new p5 595 systems. What compatibility issue must be considered?()AAPV features are not supported for some legacy POWER4 adaptersBAPV will require the most current maintenance level for AIX 5.2CAPV features will require that legacy POWER4 adapters be updated with new microcodeDThe Virtual IO Server must run AIX 5.3 and the LPARs can run either AIX 5.2 or AIX 5.3
单选题Companycom has a requirement for an LPAR in their p5 595 to run SUSE Linux. They also require an adapter that is not currently supported in Linux. Which of the following would be the best solution to recommend?()AAssign the adapter to an IO Hosting partitionBUse AIX 5L affinity to move the application from SUSE to AIXCUse AIX 5.3 drivers to install the adapter in the Linux LPARDAssign the adapter to an AIX 5.3 partition running Linux Affinity
单选题Companycom has a p690 server with unused fiber (HBA) host bus adapters (feature code 6228) that they would like to reuse. They are interested in implementing Advanced Power Virtualization features particularly Virtual IO. What is the best way to proceed?()AUpgrade the p690 to a p5 590 server running AIX 5.3BUpgrade the p690 server to AIX 5.3 and implement Advanced Power VirtualizationCPurchase a p5 590 with minimum resources and simply reuse the p690 unused fiber HBA adaptersDPurchase a p5 590 that has all the needed resources and adapters for Advanced Power Virtualization
单选题Companycom is purchasing a p5 595 as part of a large server consolidation. They are planning on using micropartitioning and Virtual IO to consolidate small machines. They used the rPerf numbers for AIX 5.3 to size their solutions. They discovered that their application is not yet certified on AIX 5.3, so they will have to use AIX 5.2. What changes should be made to their configuration?()AIncrease memoryBAdd more adaptersCIncrease both processors and adaptersDIncrease the number of processors by 20 - 30%
单选题Companycom has a p690 and currently has eight LPARs. They have purchased a p5 590 and wish to migrate their eight LPARs to the new server. The LPARs are running either AIX 5.2 or AIX 5.3 with the current maintenance. What is the LEAST disruptive method for this activity?()ANew install of AIXBMigrate the 7040-61DCUtilize alt_disk_installDUse the enterprise back up strategy
单选题A large customer is consolidating their pSeries systems onto a p5 590. They will have a requirement for a single device (disk, lun) to have multiple paths through different adapters in a single LPAR. The primary applications were written for AIX 5.2. Which of the following would be the recommended solution to satisfy this requirement?()AAssign the adapters to a Virtual IO partitionBUse the MPIO function included in AIX 5.2CMigrate the application to AIX 5.3 and use the MPIO functionDSet up two Virtual IO partitions and attach both partitions to the device
单选题Companycom has a Linux LPAR on a p5 570 server. The 3rd party storage subsystem devices are not supported by Linux. How would access be provided to the storage subsystem devices for this Linux LPAR?()ADaisy chain the unsupported 3rd party storage subsystem devices with the local SCSI disk drive BAssuming the 3rd party storage subsystem has AIX support, enable access through a Virtual IO Server CAssuming the 3rd party storage subsystem has AIX support, implement the Linux partition within an AIX partition D3rd party storage is not an option for p5 570 servers and therefore only IBM disk subsystems can be considered as a solution
单选题Companycom has just purchased a p5 570 with AIX 5.3. The customer would like to add a training LPAR to the system, but no processors are available. All of the partitions are using dedicated resources. The test LPAR is using one processor and has a 90% CPU idle rate. What can be done to setup this training LPAR quickly without disabling their current environment?()AUse AIX 5.3 which supports micro-partitioning for both the test and training LPARSBUse DLPAR to move resources from the test LPAR to training when training is activeCInstall Partition Load Manager to share resources between the test and training environmentsDInstall Advanced Power Virtualization and then use micro-partitioning for both the test and training LPARs