单选题()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.APlannedvalueBEarned valueCActualcostDCostvariance

单选题
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
A

Plannedvalue

B

Earned value

C

Actualcost

D

Costvariance


参考解析

解析: 该题的关键词为"budgeted amount for the work actually completed",其语句结构为"()(主语)is(谓语)the budgeted amount for the work actually completed",含义为"什么是实际完成工作对应的预算",容易判断该语句正是挣值( Earned value)的定义。

相关考题:

The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:A . Multiplying the actual hours worked on the project by the budgeted labor rate.B . Multiplying the budgeted hours to complete the task by the budgeted labor rate.C . Dividing the actual hours required to complete the task by the budgeted labor rate.D . Cannot be determined.E . None of the above

159 The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:A. Multiplying the actual hours worked on the project by the budgeted labor rate.B. Multiplying the budgeted hours to complete the task by the budgeted labor rate.C. Dividing the actual hours required to complete the task by the budgeted labor rate.D. Cannot be determined.E. None of the above

()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period. A.PlannedvalueB.Earned valueC.ActualcostD.Costvariance

is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A.WBS CreationB.Scope definitionC.Project acceptanceD.Scope verification

is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.A.Planned valueB.Earned valueC.Actual costD.Cost variance

The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned

With his work completed, the manager stepped back to his seat, feeling pleased()he was a man of action.A. whichB. whatC. that

______ of making progress, my work actually seems to be going backwards. A. In spiteB. In caseC. IncludingD. Instead

The work______ be completed before this weekend.A、oughtB、mustC、had better toD、should to

Which of the folloeing represents the estimated value of the work actually accomplished?( 75 )A.ACB.CVC.PVD.EV

The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).A.Cost Variance B.Schedule Variance C.Earned Value D.Cost Performed Index

is the budgeted amount for the work actually completed on the schedule acticity or WBS comonent during a given period。A.Planned valueB.Actual costC.Earned valueD.Cost variance

It has meant that in the first place the amount of benefits must be small lest people’s willingness to work and support themselves suffers.

The information is circulated through communication processes.( )is not included in Work Performance Information.A.The status of deliverablesB.Implementation status for change requestsC.Forecasted estimates to completeD.Work performance report

There is still an immense amount of work to be done.A:muchB:enormousC:little D:extensive

The difference value between Budgeted Cost for Work Performed and Actual Cost for Work Performed is ( ). A.Cost Variance B.Schedule Variance C.EarneD.Value D.Cost PerformeD.Index

I tried()the book in a few days, but actually I couldn't, just because of too much work for me.A、finishB、finishingC、to have finishedD、finished

What is the purpose of an explicit "deny any" statement at the end of an ACL?()A、none,since it is implicitB、to enable Cisco IOS IPS to work properly;however,it is the deny all traffic entry that is actually requiredC、to enable Cisco IOS Firewall to work properly;however,it is the deny all traffic entry that is actually requiredD、to allow the log option to be used to log any matchesE、to prevent sync flood attacksF、to prevent half-opened TCP connections

()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A、Project acceptanceB、Scope verificationC、Scope definitionD、WBS Creation

Which of the following recovery plan test results would be most useful to management? 下列哪个恢复计划测试的结果将对管理层最有用?()A、amount of work completed. 完成的工作量B、description of each activity. 每个活动的描述C、list of successful and unsuccessful activities. 成功与不成功的活动清单D、elapsed time to perform various activities. 运行时间来执行各种活动

单选题The border was actually two towns, though no one was big enough to amount to anything.Anot oneBneither oneCnoneDnor

单选题()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.APlanned valueBEarned valueCActual costDCost variance

单选题() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.AprojectacceptanceBscopeverificationCscopedefinitionDWBS Creation

单选题What is the purpose of an explicit "deny any" statement at the end of an ACL?()Anone,since it is implicitBto enable Cisco IOS IPS to work properly;however,it is the deny all traffic entry that is actually requiredCto enable Cisco IOS Firewall to work properly;however,it is the deny all traffic entry that is actually requiredDto allow the log option to be used to log any matchesEto prevent sync flood attacksFto prevent half-opened TCP connections

单选题He _____ have completed his work; otherwise, he wouldn’t be enjoying himself by the seaside.AshouldBmustCwouldn’tDcan’t

单选题()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.APlannedvalueBEarned valueCActualcostDCostvariance

单选题What has research shown about the way managers work?AThey work in situations of conflict.BTheir work is completed very quickly.CManagers do many things at the same time.DManagers give orders.

单选题His hard-working spirit attracted and activated others. As a result, the work was completed ahead of schedule.Astrove for Bstirred up Cstripped awayDstretched out