一旦为一个完整网络计算出活动历时,顺推法(forwardpass)与逆推法(backwardpass)就会提供()A、活动的总时差(float)B、只有最早开始(early start)与最晚开始时间(late Start)C、关键路径(critical path)D、A和C
一旦为一个完整网络计算出活动历时,顺推法(forwardpass)与逆推法(backwardpass)就会提供()
- A、活动的总时差(float)
- B、只有最早开始(early start)与最晚开始时间(late Start)
- C、关键路径(critical path)
- D、A和C
相关考题:
Which of the following is indicative of negative float?A.The late start date is earlier than the early start date.B.The critical path supports the imposed end date.C.The early finish date is equal to the late finish date.D.When leads are employed in the schedule.E.The project is sinking.
● Which of the following is indicative of negative float?A The late start date is earlier than the early start date.B The critical path supports the imposed end date.C The early finish date is equal to the late finish date.D When leads are employed in the schedule.E The project is sinking.
一旦制定出网络逻辑图,项目经理将会对网络进行顺推计算然后逆推计算。这样做将会提供关于的信息并且可确认()。 A.每项活动的时差,关键路线B.每项活动的时差,高风险活动C.人力短缺,高风险活动D.高风险活动,非关键路线
一旦为一个完整网络计算出活动历时,顺推法(forwardpass)与逆推法(backwardpass)就会提供() A.活动的总时差(float)B.只有最早开始(early start)与最晚开始时间(late Start)C.关键路径(critical path)D.A和C
一旦制定出网络逻辑图,项目经理将会对网络进行顺推计算然后逆推计算。这样做将会提供关于的信息并且可确认()。A、每项活动的时差,关键路线B、每项活动的时差,高风险活动C、人力短缺,高风险活动D、高风险活动,非关键路线
单选题一旦为一个完整网络计算出活动历时,顺推法(forwardpass)与逆推法(backwardpass)就会提供()A活动的总时差(float)B只有最早开始(early start)与最晚开始时间(late Start)C关键路径(critical path)DA和C
多选题关于制定网络进度计划的逆推法,下列叙述正确的是()。A从项目网络最右边开始B从项目网络最左边开始C计算每个活动最迟开始和最迟结束时间D计算每个活动最早开始和最早结束时间E比正推法要准确
单选题可用以确定项目各项活动最早、最晚的开始时间和完成时间的是()。A关键路径法BPERT图C横道图法D网络图