单选题In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()AStrongmatrixBProjectizedCProjectcoordinatorDWeakmatrix

单选题
In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
A

Strongmatrix

B

Projectized

C

Projectcoordinator

D

Weakmatrix


参考解析

解析: 暂无解析

相关考题:

A program can best be described as:AA grouping of related activities which last two years or moreBThe first major subdivision of a projectCA grouping of projects, similar in nature, which support a product or product line and have no definable end pointDA product lineEAnother name for a project

Which of the following would most likely increase the accuracy of estimating the project cost?A . Pricing out the work at lower levels in the work breakdown structure.B . Using historical data.C . Talking to people who have worked on similar projects.D . All of the above.E . A and C only.

Which of the following would most likely not be an essential objective of a project team kick-off meetingA . Create a project technology master planB . Get team members to know one anotherC . Identify project problem areasD . Obtain individual and group commitmentsE . Identify the project coordinator

Which of the following organizational forms would be likely to have an individual with the title of Vice President for Project Management?A . Classical / traditionalB . Pure projectC . MatrixD . Project coordinatorE . None of the above

Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?A . MatrixB . Pure projectC . Project coordinatorD . Project expediterE . Classical/traditional

The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form. does the project manager probably have the easiest time in integrating work?A . MatrixB . ClassicalC . ExpediterD . CoordinatorE . Pure project

Project Risk _____ .A should not be calculated for small projects.B is the probability of each risk event minus the sum of the consequences of potential risk events.C is the cumulative effect of uncertain occurrences which will adversely affect project objectives.D cannot be quantified for first time projects.E B or D

87 Which of the following would most likely increase the accuracy of estimating the project cost? A. Pricing out the work at lower levels in the work breakdown structure.B. Using historical data.C. Talking to people who have worked on similar projects.D. All of the above.E. A and C only.

160 The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form. does the project manager probably have the easiest time in integrating work? A. MatrixB. ClassicalC. ExpediterD. CoordinatorE. Pure project

4 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?A. MatrixB Pure projectC. Project coordinatorD. Project expediterE. Classical/traditional

30 Which of the following organizational forms would be likely to have an individual with the title of Vice President for Project Management?A. Classical / traditionalB. Pure projectC. MatrixD. Project coordinatorE. None of the above

118 Which of the following would most likely not be an essential objective of a project team kick-off meetingA. Create a project technology master planB. Get team members to know one anotherC. Identify project problem areasD. Obtain individual and group commitmentsE. Identify the project coordinator

149 A program can best be described as:A. A grouping of related activities which last two years or moreB. The first major subdivision of a projectC. A grouping of projects, similar in nature, which support a product or product line and have no definable end pointD. A product lineE. Another name for a project

170 Project Risk _____ .A. should not be calculated for small projects.B. is the probability of each risk event minus the sum of the consequences of potential risk events.C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives.D. cannot be quantified for first time projects.E. B or D

86 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?A. MatrixB. Pure projectC. Project coordinatorD. Project expediterE. Classical/traditional

In which form of projects origination would the project manager be likely to exercise the most control over Project resources.() A.StrongmatrixB.ProjectizedC.ProjectcoordinatorD.Weakmatrix

32 jack descried his father, who _____a brave boy many years ago, as a strong-wiled manA. would beB. would have beenC. must beD. must have been

● Which of the following statement related to PMO is not correct? (71)(71)A. The specific form, function, and structure of a PMO is dependent upon the needs of the organization that it supports.B. One of the key features of a PMO is managing shared resources across all projects administered by the PMO.C. The PMO focuses on the specified project objectives.D. The PMO optimizes the use of shared organizational resources across all projects.

Which function is NOT served by building a prototype?A.It takes the place of the final system.B.It assists in gathering software requirements.C.It assists in estimating the cost of the project.D.It is used as the foundation of the larger projects.

involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it,and can be within the same or in another application area.A.MetricsB.MeasurementC.BenchmarkingD.Baseline

Which of the following statement related to PMO is not correct? (71)A.The specific form, function, and structure of a PMO are dependent upon the needs of the organization that it supports.B.One of the key features of a PMO is managing shared resources across all projects administered by the PMO.C.The PMO focuses on the specified project objectives.D.The PMO optimizes the use of shared organizational resources across all projects.

Earned value management(EVM)integrates the scope baseline with the()baseline,along with schedule baseline,to form the performance,which helps the project management team assess and measure project performance and progress.A.qulityB.riskC.changeD.cost

Which of the following statement related to PMO is not correct? ( ) A. The specifiC form, function, and structure of A PMO is dependent upon the needs of the organization that it supports. B.One of the key features of a PMO is managing shareD.resources across all projects administered by the PMO C.The PMO focuses on the specifieD.project objectives. D.The PMO optimizes the use of shared organizational resources across all projects.

Which of the following statement related to PMO is not correct?()A、The specific form, function, and structure of a PMO are dependent upon the needs of the organization that it supports.B、One of the key features of a PMO is managing shared resources across all projects administered by the PMO.C、The PMO focuses on the specified project objectives.D、The PMO optimizes the use of shared organizational resources across all projects.

Which built-in would you use to test whether the CREATE TABLE command issued in the SALES form executed successfully?()A、FORMS_DDL B、DO_SQL C、FORM_SUCCESS D、FORM_NOT_SUCCESSE、DBMS.ERROR_CODE

单选题Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.ABenchmarkingBQuality metricCQuality checklistDBrainstornung

单选题Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools,which involves company actual or planned project practices to those or other projects to generate ideas for improvementand to provide a basis by which to measure performance.ABenchmarkingBQuality metricCQuality checklistDBrainstorming