单选题When is the most critical time of bunkering in regards to oil pollution?()Alining up the systemsBtopping offCstarting deliveryDconnecting hoses and joints

单选题
When is the most critical time of bunkering in regards to oil pollution?()
A

lining up the systems

B

topping off 

C

starting delivery

D

connecting hoses and joints


参考解析

解析: 暂无解析

相关考题:

The range of time allowed for an activity to be completed in is the _____.A.Planned time (Duration).B.Float time (LS - ES, or LF - EF).C.Critical time (when ES = LS, or EF = LF).D.Scheduled time (LF - ES).E.Event.

Bar charts are most appropriate for:A.Comparing actual to planned performance to each activity.B.Showing slack time.C.Showing critical path dependencies.D.Showing which activities can be rearranged in parallel.E.All of the above.

The schedule risk is the _____ .A the accumulated "expected' durations which maintain project completion.B Critical Path adjusted by "high-risk" activity float.C highest risk path that maintains quality.D Critical Path when calculated with "most likely" duration.E highest risk path that contributes the most risk toward the project completion.

112 The schedule risk is the _____ .A. the accumulated "expected' durations which maintain project completion.B. Critical Path adjusted by "high-risk" activity float.C. highest risk path that maintains quality.D. Critical Path when calculated with "most likely" duration.E. highest risk path that contributes the most risk toward the project completion

153 The range of time allowed for an activity to be completed in is the _____.A. Planned time (Duration).B. Float time (LS - ES, or LF - EF).C. Critical time (when ES = LS, or EF = LF).D. Scheduled time (LF - ES).E. Event

35 The range of time allowed for an activity to be completed in is the _____.A. Planned time (Duration).B. Float time (LS - ES, or LF - EF).C. Critical time (when ES = LS, or EF = LF).D. Scheduled time (LF - ES).E. Event.

● The range of time allowed for an activity to be completed in is the _____.A Planned time (Duration).B Float time (LS - ES, or LF - EF).C Critical time (when ES = LS, or EF = LF).D Scheduled time (LF - ES).E Event.

● Bar charts are most appropriate for:A Comparing actual to planned performance to each activity.B Showing slack time.C Showing critical path dependencies.D Showing which activities can be rearranged in parallel.E All of the above.

As () machine tools, we regret to () that we are not able to supply for the time being.A、regarded,sayB、regards,sayingC、regards,sayD、regarded,inform

What attention should be paid when bunkering oil in the USA?

The most crucial time for project risk assessment is (75) .A.when a problem surfacesSXB The most crucial time for project risk assessment is (75) .A.when a problem surfacesB.during the planning phaseC.during the close-out phaseD.after the project schedule has been published

The most crucial time for any bearing with regards to lubrication isA.during low loadsB.after proper oil viscosity is reachedC.during startingD.after cleaning filters

Which of the following is MOST critical when installing a new processor in an existing system?() A. Thermal pasteB. FansC. Drive speedsD. Cable management

The most crucial time for project risk assessment is ( ).A.when a problem surfacesB.during the planning phaseC.during the close-out phaseD.after the project schedule has been published

In reference to accidental oil pollution,the most critical time during bunkering is when ______.A.you first start to receive fuelB.hoses are being blown downC.final topping off is occurringD.hoses are being disconnected

There is always excitement at the Olympic Games when an athlete breaks a previous record oi performance.A:destroys B:beatsC:maintains D:defend

The most crucial time for project risk assessment is ( ).A、when a problem surfacesB、during the planning phaseC、during the close-out phaseD、after the project schedule has been published

Which of the following is the MOST important consideration when purchasing a new server for a mission critical application?()A、RAID 0 compliantB、Notifying all stakeholders of the server upgradeC、Service Level AgreementD、KVM access

Which of the following is MOST critical when installing a new processor in an existing system?()A、Thermal pasteB、FansC、Drive speedsD、Cable management

单选题Which of the followings needs not to be considered during bunkering?()AAll scuppers plugged by carpenterBTanks sounded from time to timeCWatch kept for leakageDTake oil samples

单选题The most crucial time for any bearing with regards to lubrication is ()Aduring low loadsBafter proper oil viscosity is reachedCduring startingDafter cleaning filters

单选题The most likely time for oil pollution while bunkering is when().Afinal topping off is occurringBfirst starting to receive fuelChoses are being blown downDhoses are disconnected and being capped

单选题The most critical part of the bunkering operations, which can result in an oil spill, is when the ()Ahose joints are made upBtanks are being topped offCsystem is being lined upDpumping operation is first started

单选题In reference to accidental oil pollution,the most critical time during bunkering is when ().Ayou first start to receive fuelBhoses are being blown downCfinal topping off is occurringDhoses are being disconnected

多选题Which three tasks can be automatically performed by the Automatic Data Optimization feature ofInformation lifecycle Management (ILM)?()ATracking the most recent read time for a table segment in a user tablespaceBTracking the most recent write time for a table segment in a user tablespaceCTracking insert time by row for table rowsDTracking the most recent write time for a table blockETracking the most recent read time for a table segment in the SYSAUX tablespaceFTracking the most recent write time for a table segment in the SYSAUX tablespace

单选题The temperature of the fuel oil received during bunkering operations is critical in determining the()Aexpansion space to leave in a tankBflash point at which the fuel will burnCtemperature to which the fuel must be heatedDrate at which the fuel can be pumped during transfer operations

单选题Leisure time is a _______ commodity for most professors. Still, _______ manage to curl up with a good book when they have the chance.Ausual; fewBcheap; manyCregular; lessDscarce; a few