单选题A customer has a 16-core Power 570 with 64 GB RAM. They have 2 VIO servers and 4 LPARs, all running very heavy database applications. Storage is virtualized. The storage is SAN based and configured via MultiPath IO on the LPARs. The users are complaining about poor  performance. The VIO servers are reporting low CPU load and little memory usage. The LPARs show 100% disk busy time and are running very slowly, approximately 6-10MB/sec. The SAN reports LUN utilization of less that 20% busy time.  What should be done to resolve this problem? ()A Configure MPIO load balancing on the LPARs.B Increase the SCSI queue depth per hdisk device.C Increase the number of virtual SCSI devices per LPAR by 2.D Increase the path priority on both virtual SCSI devices on the LPARs.

单选题
A customer has a 16-core Power 570 with 64 GB RAM. They have 2 VIO servers and 4 LPARs, all running very heavy database applications. Storage is virtualized. The storage is SAN based and configured via MultiPath IO on the LPARs. The users are complaining about poor  performance. The VIO servers are reporting low CPU load and little memory usage. The LPARs show 100% disk busy time and are running very slowly, approximately 6-10MB/sec. The SAN reports LUN utilization of less that 20% busy time.  What should be done to resolve this problem? ()
A

 Configure MPIO load balancing on the LPARs.

B

 Increase the SCSI queue depth per hdisk device.

C

 Increase the number of virtual SCSI devices per LPAR by 2.

D

 Increase the path priority on both virtual SCSI devices on the LPARs.


参考解析

解析: 暂无解析

相关考题:

A customer needs to create a number of LPARs on a new POWER6 server with some LPARs requiring a dedicated network and other LPARs utilizing Virtual Ethernet via a VIO server.Which limitation must be considered when planning the system configuration?()A.A VIO server requires a dedicated LHEA port.B.There is a limit of 32 LPARs per virtual LAN.C.Two VIO servers will be required. A single VIO server can only provide virtual storage or virtual Ethernet.D.Two VIO servers will be required. One to provide virtual networking and another to provide dedicated networking.

Which are the two main uses of a VIO server?() A.Virtualize network and memory to LPARs.B.Virtualize network and storage to LPARs.C.Virtualize memory and processors to LPARs.D.Virtualize storage and processors to LPARs.

A customer is running Microsoft Windows 2003, Sun Solaris, and IBM AIX with a total capacity of20 TB. This customer needs high availability for e-business applications. The servers are currently connected to two EMC Symmetrix subsystems that are running RAID 1. The customer wants to consolidate all storage into an IBM System Storage DS8700.How many Fibre Channel drive sets are needed to satisfy the total capacity for this customer?()A. 8 drive sets of 300 GB drivesB. 4 drive sets of 300 GB drivesC. 14 drive sets of 146 GB drivesD. 18 drive sets of 146 GB drives

A customer is running Microsoft Windows 2003, Sun Solaris, and IBM AIX with a total capacity of20 TB. This customer needs high availability for e-business applications. The servers are currently connected to two EMC Symmetrix subsystems that are running RAID 1. The customer wants to consolidate all storage into an IBM System Storage DS8700. How many Fibre Channel drive sets are needed to satisfy the total capacity for this customer?()A、8 drive sets of 300 GB drivesB、4 drive sets of 300 GB drivesC、14 drive sets of 146 GB drivesD、18 drive sets of 146 GB drives

The systems administrator of a large manufacturer has POWER5 and POWER6 servers, each with LPARs running AIX 6.1.  They are running several workloads including SAP, DNS, Oracle, DB2 and WebSphere Application Server, and plan to consolidate onto one POWER7 server.   How can the system administrator determine how much benefit Active Memory Expansion (AME) could provide for the consolidated system?()A、Run amepat now on all of the existing LPARs.B、Run amepat after consolidation on all LPARs.C、Run amepat now on all existing LPARs running on the POWER6 servers.D、Run amepat now on all existing LPARs running database applications.

A customer needs 2 TB of high availability storage for eBusiness applications. Their servers arecurrently connected to two EMC Symmetrix subsystems that are running RAID 1. They want toconsolidate all of the RAID 1 storage into an IBM System Storage DS6800. Which configurationsatisfies these capacity requirements?()A、Two disk drive sets of 300 GB drivesB、Four disk drive sets of 146 GB drivesC、Eight disk drive sets of 73 GB drivesD、Nine disk drive sets of 146 GB drives

A customer wants to hold all enterprise data on their DS4000 system.  Several servers were added after they purchased another company.  The servers that have to be run are:       (1)An Oracle database running on a HP-UX server   (2)Several virtual machines running on VMWare ESX server       (3)A Microsoft cluster running Exchange 2000 server   Which of these new servers can be integrated with the DS4000?()A、DS4000 storage does not support HP-UX, so the HP-UX server cannot be integrated.All other new servers can be used.B、An Exchange cluster needs local disks, so the DS4000 cannot be used for this.All other new servers can be used.C、When equipped with proper HBA’s and subsystem device drivers, all new servers can operate with the DS4000 storage device.D、VMWare ESX can use the DS4000 storage; however, the virtual machines running in it will not have access to this storage other than via a virtual disk.All other new servers can be used.

A customer has a 16-core Power 570 with 64 GB RAM. They have 2 VIO servers and 4 LPARs, all running very heavy database applications. Storage is virtualized. The storage is SAN based and configured via MultiPath IO on the LPARs. The users are complaining about poor  performance. The VIO servers are reporting low CPU load and little memory usage. The LPARs show 100% disk busy time and are running very slowly, approximately 6-10MB/sec. The SAN reports LUN utilization of less that 20% busy time.  What should be done to resolve this problem? ()A、 Configure MPIO load balancing on the LPARs.B、 Increase the SCSI queue depth per hdisk device.C、 Increase the number of virtual SCSI devices per LPAR by 2.D、 Increase the path priority on both virtual SCSI devices on the LPARs.

A customer server has the maximum local storage installed. The customer plans to share this new storage with other servers. Which of the following provides that server additional storage?()A、Add External Storage via EXP3000B、Replace current storage with more dense drivesC、Add External Storage via SAND、Add storage expansion blade

A p5 570 customer is currently running AIX 5.3. The customer now wants to add Virtual Ethernet to two of the LPARs. This will enable the application tier can communicate to the database tier without using an external Ethernet card. What is the best way to accomplish this task?()A、Create a VIO serverB、Modify the LPAR profiles to add a Virtual Ethernet adapterC、Buy the Advanced Power Virtualization feature and enter a authorization code at the HMCD、Buy the Advanced Power Virtualization feature and enter a authorization code at the service processor menu

A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700.  They would like to upgrade and plan for 40 TB capacity.  The customer needs to move to a more scalable storage system to include all servers.Which of the following would be most appropriate to ask first?()A、What are the plans for Disaster Recovery? B、What are the plans for data migration? C、Would iSCSI meet your needs? D、How much space is available in the current storage systems?

An IBM Business Partner has sold a DS5020 and new IBM SAN switches to replace a customer EMC storage infrastructure. The customer dissatisfaction has arisen during the installation because according to the DS5020 interoperability matrix, two HP Proliant servers running Exchange have FC HBAs that are not supported. Which of the following is the most probable cause of the customer dissatisfaction()A、The EMC storage specialist has not participated in the TDA meetingB、The FC HBAs are 4 Gbps technologyC、The Technical and Delivery Assessment review actions were not executedD、The customer should have checked that the HBAs are supported according to the HP storage interoperability matrix

A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure. Which solution addresses the customer requirements?()A、Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAsB、Move the existing physical network and storage adapters to the new system and virtualize the I/O using a single VIO Server.C、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC connectors and dual HBAs.D、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC connectors and the other with dual HBAs.

Which are the two main uses of a VIO server?() A、Virtualize network and memory to LPARs.B、Virtualize network and storage to LPARs.C、Virtualize memory and processors to LPARs.D、Virtualize storage and processors to LPARs.

A customer needs to create a number of LPARs on a new POWER6 server with some LPARs requiring a dedicated network and other LPARs utilizing Virtual Ethernet via a VIO server. Which limitation must be considered when planning the system configuration?()A、A VIO server requires a dedicated LHEA port.B、There is a limit of 32 LPARs per virtual LAN.C、Two VIO servers will be required. A single VIO server can only provide virtual storage or virtual Ethernet.D、Two VIO servers will be required. One to provide virtual networking and another to provide dedicated networking.

A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700. They would like to upgrade and plan for 40 TB capacity. The customer needs to move to a more scalable storage system to include all servers. Which of the following would be most appropriate to ask first?()A、What are Disaster RecoveryplansB、What are plans for datamigrationC、What storage system space isavailableD、DoesiSCSI meet the needs

单选题A p5 570 customer is currently running AIX 5.3. The customer now wants to add Virtual Ethernet to two of the LPARs. This will enable the application tier can communicate to the database tier without using an external Ethernet card. What is the best way to accomplish this task?()ACreate a VIO serverBModify the LPAR profiles to add a Virtual Ethernet adapterCBuy the Advanced Power Virtualization feature and enter a authorization code at the HMCDBuy the Advanced Power Virtualization feature and enter a authorization code at the service processor menu

单选题A customer server has the maximum local storage installed. The customer plans to share this new storage with other servers. Which of the following provides that server additional storage?()AAdd External Storage via EXP3000BReplace current storage with more dense drivesCAdd External Storage via SANDAdd storage expansion blade

单选题A customer needs 2 TB of high availability storage for eBusiness applications. Their servers arecurrently connected to two EMC Symmetrix subsystems that are running RAID 1. They want toconsolidate all of the RAID 1 storage into an IBM System Storage DS6800. Which configurationsatisfies these capacity requirements?()ATwo disk drive sets of 300 GB drivesBFour disk drive sets of 146 GB drivesCEight disk drive sets of 73 GB drivesDNine disk drive sets of 146 GB drives

单选题A customer wants to hold all enterprise data on their DS4000 system.  Several servers were added after they purchased another company.  The servers that have to be run are:       (1)An Oracle database running on a HP-UX server   (2)Several virtual machines running on VMWare ESX server       (3)A Microsoft cluster running Exchange 2000 server   Which of these new servers can be integrated with the DS4000?()ADS4000 storage does not support HP-UX, so the HP-UX server cannot be integrated.All other new servers can be used.BAn Exchange cluster needs local disks, so the DS4000 cannot be used for this.All other new servers can be used.CWhen equipped with proper HBA’s and subsystem device drivers, all new servers can operate with the DS4000 storage device.DVMWare ESX can use the DS4000 storage; however, the virtual machines running in it will not have access to this storage other than via a virtual disk.All other new servers can be used.

单选题A customer has a 16-core Power 570 with 64 GB RAM. They have 2 VIO servers and 4 LPARs, all running very heavy database applications. Storage is virtualized. The storage is SAN based and configured via MultiPath IO on the LPARs. The users are complaining about poor  performance. The VIO servers are reporting low CPU load and little memory usage. The LPARs show 100% disk busy time and are running very slowly, approximately 6-10MB/sec. The SAN reports LUN utilization of less that 20% busy time.  What should be done to resolve this problem? ()A Configure MPIO load balancing on the LPARs.B Increase the SCSI queue depth per hdisk device.C Increase the number of virtual SCSI devices per LPAR by 2.D Increase the path priority on both virtual SCSI devices on the LPARs.

单选题A customer needs to create a number of LPARs on a new POWER6 server with some LPARs requiring a dedicated network and other LPARs utilizing Virtual Ethernet via a VIO server. Which limitation must be considered when planning the system configuration?()AA VIO server requires a dedicated LHEA port.BThere is a limit of 32 LPARs per virtual LAN.CTwo VIO servers will be required. A single VIO server can only provide virtual storage or virtual Ethernet.DTwo VIO servers will be required. One to provide virtual networking and another to provide dedicated networking.

单选题Which are the two main uses of a VIO server?()AVirtualize network and memory to LPARs.BVirtualize network and storage to LPARs.CVirtualize memory and processors to LPARs.DVirtualize storage and processors to LPARs.

单选题A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700. They would like to upgrade and plan for 40 TB capacity. The customer needs to move to a more scalable storage system to include all servers. Which of the following would be most appropriate to ask first?()AWhat are Disaster RecoveryplansBWhat are plans for datamigrationCWhat storage system space isavailableDDoesiSCSI meet the needs

单选题A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700.  They would like to upgrade and plan for 40 TB capacity.  The customer needs to move to a more scalable storage system to include all servers.Which of the following would be most appropriate to ask first?()AWhat are the plans for Disaster Recovery? BWhat are the plans for data migration? CWould iSCSI meet your needs? DHow much space is available in the current storage systems?

单选题An IBM Business Partner has sold a DS5020 and new IBM SAN switches to replace a customer EMC storage infrastructure. The customer dissatisfaction has arisen during the installation because according to the DS5020 interoperability matrix, two HP Proliant servers running Exchange have FC HBAs that are not supported. Which of the following is the most probable cause of the customer dissatisfaction()AThe EMC storage specialist has not participated in the TDA meetingBThe FC HBAs are 4 Gbps technologyCThe Technical and Delivery Assessment review actions were not executedDThe customer should have checked that the HBAs are supported according to the HP storage interoperability matrix

单选题A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure. Which solution addresses the customer requirements?()AMove the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAsBMove the existing physical network and storage adapters to the new system and virtualize the I/O using a single VIO Server.CMove the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC connectors and dual HBAs.DMove the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC connectors and the other with dual HBAs.

单选题The systems administrator of a large manufacturer has POWER5 and POWER6 servers, each with LPARs running AIX 6.1.  They are running several workloads including SAP, DNS, Oracle, DB2 and WebSphere Application Server, and plan to consolidate onto one POWER7 server.   How can the system administrator determine how much benefit Active Memory Expansion (AME) could provide for the consolidated system?()ARun amepat now on all of the existing LPARs.BRun amepat after consolidation on all LPARs.CRun amepat now on all existing LPARs running on the POWER6 servers.DRun amepat now on all existing LPARs running database applications.