单选题To ensure the ship’s general stability,().Ashe's loaded a little deeper forwardBshe's loaded a little deeper aftCshe has not any ballast at allDthe cargo is properly distributed throughout the ship
单选题
To ensure the ship’s general stability,().
A
she's loaded a little deeper forward
B
she's loaded a little deeper aft
C
she has not any ballast at all
D
the cargo is properly distributed throughout the ship
参考解析
解析:
暂无解析
相关考题:
Serious loss of reserve buoyancy resulting from flooding any compartment of a ship will always ______.A.increase the trimB.change the free surface effectC.cause a serious listD.decrease ship stability
If your passenger vessel has been issued a stability letter,it must be ______.A.filed in the ship's officeB.posted in a passenger areaC.posted adjacent to the Certificate of InspectionD.posted in the pilothouse
Marks and Nos.,Number and kind of packages,description of goods should be declared in ______.A.SHIP'S STORE LISTB.PERSONAL EFFECTS LISTC.CARGO DECLARATIOND.GENERAL DECLARATION
A claim for cargo damages may be held against the shipowner if such damage is the result of failure of the ship's officers to ______.A.ensure the fitness and safety of cargo spacesB.ensure adequate packaging of the cargoC.prevent delays due to quarantine restrictionsD.correct all defects in the ship's construction
The master of a ship must collect general average contributions for the benefit of those entitled to them,whether they are cargo owners or ship owner,and ______ the Shipowner's lien on the cargo,where necessary,until they are paid.A.exerciseB.takeC.makeD.have
Marks and Nos.,numbers and kinds of packages,description of goods are to be provided in ______.A.Passenger ListB.General DeclarationC.Cargo DeclarationD.Ship's Stores Declaration
()carries not only general cargo but also bulk cargo.A、A bulk carrierB、A multi-purpose shipC、A general cargo shipD、A dry cargo ship
Which narrative regarding loading software is incorrect?()A、The approved Loading Program could substituted the approved Loading Manual and/or Trim and Stability BookletB、A Loading Program is required to have General Approval by classification Society prior to being considered for use on a specific shipC、Following a satisfactory installation test on board the ship the Surveyor will issue a Program Installation TestD、A Loading Program may be provided as a classification requirement or as an Owner’s option
单选题Prior to a ship’s departure from any port () should be tested with deck officer to ensure satisfactory operation.Afire fighting pumpBthe steering gearClife boat engineDthe main engine
单选题The stability which exists after the unintentional flooding of a compartment on a ship is called().Aintact stabilityBinitial stabilityCimmersion stabilityDdamage stability
单选题The Company should ensure that the ship’s personnel are able to () effectively in the execution of their duties related to the SMS.AcommunicateBverifyCauditDevaluate
单选题Sacrifices to meet the particular emergency,such as loss of the ship’s tackle through using it for unusual purposes in order to secure her safety in specially difficult circumstances,()the subject of a general average contribution.AisBbeCwill beDto be
单选题When considering a vessel’s stability,which spaces in a general cargo vessel are the best locations for the carriage of bulk grain? ()ADeep tanksBLower holdsCLower holds at the ends of the vesselD'Tween-decks
单选题The angle of loll is a stability term which applies to a floating ship with().Aoff-center loadingBstiff characteristicsCexcessive pitch or rollDnegative initial stability
单选题()means a plan developed to ensure the application of measures on board the ship designed to protect persons on board, cargo, cargo transport units, ship’s stores or the ship from the risks of a security incident.AShip security planBCompany security planCPort facility security planDNational security plan
单选题If your passenger vessel has been issued a stability letter,it must be ().Afiled in the ship’s officeBposted in a passenger areaCposted adjacent to the Certificate of InspectionDposted in the pilothouse
单选题A load line is assigned to a ship to insure adequate stability and().Amooring tensionBriser tensionClifesaving equipmentDstructural strength
单选题The general benefit of the GMDSS is to().Aenable SAR operations to start with minimum delayBgive facilities to marine communicationCreduce sharply the chances of ship’s sinkingDboth A and C
单选题Traditionally,the signal for fire aboard ship is().Amore than 6 short blasts and 1 long blast on the whistle,and the same signal on the general alarmBcontinuous sounding of the ship's whistle and the general alarm for at least 10 secondsC1 short blast on the whistleDalternating short and long blasts on the ship's whistle
单选题The maximum angle at which the intact stability curves are valid for ship’s is the angle for().Athe limit of positive stabilityBthe limit of small-angle stabilityCmaximum offsetDdownflooding
单选题General radio communications in the global system may()ship’s safety.Abe responsible forBhave an impact onCcommandDgive a guidance to
单选题The stability of a semisubmersible ship would be seriously reduced if flooding occurred in the().Asubmerged hullsBcolumn void spacesCdry mud tanksDballast tanks
单选题Which narrative regarding loading software is incorrect?()AThe approved Loading Program could substituted the approved Loading Manual and/or Trim and Stability BookletBA Loading Program is required to have General Approval by classification Society prior to being considered for use on a specific shipCFollowing a satisfactory installation test on board the ship the Surveyor will issue a Program Installation TestDA Loading Program may be provided as a classification requirement or as an Owner’s option
单选题A serious loss of reserve buoyancy resulting from flooding any compartment of a ship will always().Aincrease the trimBchange the free surface effectCcause a serious listDdecrease ship stability