You are attempting to parallel two AC generators, and the synchroscope(同步器) pointer is revolving in the fast direction. This indicates that the frequency of the incoming machine is ______.A.higher than the bus frequencyB.lower than the bus frequencyC.the same as the bus frequency but out of phase with itD.the same as the bus frequency and the circuit breaker may be closed at any pointer position

You are attempting to parallel two AC generators, and the synchroscope(同步器) pointer is revolving in the fast direction. This indicates that the frequency of the incoming machine is ______.

A.higher than the bus frequency

B.lower than the bus frequency

C.the same as the bus frequency but out of phase with it

D.the same as the bus frequency and the circuit breaker may be closed at any pointer position


相关考题:

How many generators does the shuttle carry?A.One.B.Two.C.Three.D.Four.

从供选择的答案中选出应填入英语文句中()的正确的答案。Toolboxes and menus in many application programs were (A) for working with the mouse. The mouse controls a pointer on the screen. You move the pointer by (B) the mouse over a flat surface in the direction you want the pointer to move. If you run out of (C) to move the mouse, lift it up and put it down again. The pointer moves only when the mouse is (D) the flat surface. Moving the mouse pointer across the screen does not affect the document, the pointer simply (E) a location on the screen. When you press the mouse button, something happens at the location of the pointer.A: ① assigned ② designed ③ desired ④ expressedB: ① putting ② sliding ③ serving ④ takingC: ① board ② place ③ room ④ tableD: ① getting ② going ③ teaching ④ touchingE: ① constructs ② indicates ③ instructs ④ processes

The ______ controls a pointer On the screen .When you move it,?the pointer moves too.A.menuB.iconC.mouseD.click

( ) can provide an asynchronous link between two ac electric power system with different nominal frequencies. A.The HVDC (high voltage DC) transmissionB.The EHV (extra-high voltage) AC transmissionC.The AC distributionD.Generators

You are attempting to parallel two AC.generators, and the synchroscope pointer revolving in the fast direction.This indicates that the frequency of the incoming machine is A.higher than the bus equencyB.lower than the bus equencyC.the same as the bus frequency but out of phase with itD.same as the bus frequency and the circuit breaker may be closed at

You upgrade your Oracle database in a multiprocessor environment. As a recommended you execute thefollowing script:SQL > @utlrp.sqlWhich two actions does the script perform?() A. Parallel compilation of only the stored PL/SQL codeB. Sequential recompilation of only the stored PL/SQL codeC. Parallel recompilation of any stored PL/SQL codeD. Sequential recompilation of any stored PL/SQL codeE. Parallel recompilation of Java codeF. Sequential recompilation of Java code

You are attempting to parallel two AC generators and the synchroscope pointer is revolving in the slow direction. This indicates that the frequency of the incoming machine isA.higher than the bus frequencyB.lower than the bus frequencyC.file same as file bus frequency but out of phase with itD.the same as the bus frequency, and the circuit breaker may be closed at nay pointer position

When you move the mouse pointer to a(),the pointer's shape usually changes to a pointing hand. A.hyperlinkB.selected textC.selected graphicD.web page

While paralleling two AC generators using synchronizing lamps only, both lamps will go dark when the generators are______.A.running at the same speedB.groundedC.of the same polarityD.in phase

The load sharing characteristics of two diesel generators operating in parallel are mostly dependent on their governor ______.A.load limit settingsB.idle speed settingsC.speed limit settingsD.speed droop settings

When attempting an upstream landing while pushing empty barges ahead in a hard onshore wind,the approach is best made ______.A.With bow out,stern inB.With bow in,stern outC.Parallel to the dock,as close in as possibleD.Parallel to the dock,as far out as possible

Which data synchronization options between two geographical locations are supported by PowerHA SystemMirror?()A、Parallel and SerialB、Serial and AsynchronousC、Parallel and SynchronousD、Synchronous and Asynchronous

You upgrade your Oracle database in a multiprocessor environment. As a recommended you execute thefollowing script:SQL @utlrp.sqlWhich two actions does the script perform?()A、Parallel compilation of only the stored PL/SQL codeB、Sequential recompilation of only the stored PL/SQL codeC、Parallel recompilation of any stored PL/SQL codeD、Sequential recompilation of any stored PL/SQL codeE、Parallel recompilation of Java codeF、Sequential recompilation of Java code

单选题The division of the kilowatt load between two AC generators operating in parallel is controlled by the settings and characteristics of the ().Avoltage regulatorsBfield rheostatsCreverse power relaysDprime mover governors

单选题Which is a function of the voltage regulators used with AC generators?()ATo cut out generators when they are no longer requiredBTo cut in additional generators automatically as requiredCTo divide the KW load equally between generators operating in parallelDTo divide reactive current between generators operating in parallel

单选题While paralleling two AC generators using synchronizing lamps only, both lamps will go dark when the generators are ().Arunning at the same speedBgroundedCof the same polarityDin phase

单选题When measuring AC current flow, you must always connect the meter ()Ain series with the power source and loadBin parallel with the power source and loadCinsuring correct polarityDusing the lowest range possible to prevent instrument damage

单选题You are docking a vessel starboard side to with the assistance of two tugs.You are attempting to hold the vessel off by operating both tugs at right angles to the vessel and at full power.You must ensure that().Asteerageway is not taken offBthe bow doesn't close the dock firstCthe bow closes the dock firstDthe ship has no headway at the time

单选题When two AC generators are being paralleled, the breaker should be closed with the synchroscope pointer mating in the ()Aslow direction, just before the 12 o'clock positionBfast direction, just after the 12 o'clock positionCfast direction, just before the 12 o'clock positionDslow direction, just after the 12 o'clock position

单选题When two DC generators operate in parallel, they are protected against motorizing by()Ablow out coilsBgovernor relayCunder voltage tripsDreverse current trips

单选题If two AC generators are to be operated in parallel, the load is distributed evenly by()Ameans of rheostat the governor settingsBa balance coil excitationCadjusting the governor settingsDchanging excitation

单选题You are attempting to parallel two AC generators, and the syncope pointer is revolving in the fast directionThis indicates that the frequency of the incoming machine is ().Ahigher than the bus frequencyBlower than the bus frequencyCthe same as the bus frequency but out of phase with itDthe same as the bus frequency and the circuit breaker may be closed at any pointer position

单选题You are attempting to parallel two AC generators and the synchroscope pointer is revolving in the slow directionThis indicates that the frequency of the incoming machine is ().Ahigher than the bus frequencyBlower than the bus freouencvCthe same as the bus frequency but out of phase with itDthe same as the bus frequency, and the circuit breaker may be closed at any pointer position

单选题If two AC generators are operated in parallel, the load is distributed evenly by()Aa rheostatBa balancing coilCchanging field excitationDadjusting the governor settings

单选题If two A.C.generators are to be operated in parallel, the load is distributed evenly by()Ameans of rheostat the governor settingsBa balance coil excitationCadjusting the governor settingsDchanging excitation

单选题Prior to closing the breaker when paralleling two AC generators, the recommended practice is to have the frequency of the incoming machine ()Aslightly less than the line frequencyBthe same as the line frequencyCslightly greater than the line frequencyDAll of the above

单选题When paralleling two AC generators, the frequency of the machine coming on-line, immediately prior to closing its breaker, should be ()Aslightly less than the oncoming generator frequencyBthe same as the bus frequencyCslightly greater than the bus frequencyDthe same as the bus voltage