A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks mostlikely, and 12 weeks pessimistically. which would appear on the chart ( ) .A.4 weeksB.5 weeksC.6 weeksD.7 weeks

A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks mostlikely, and 12 weeks pessimistically. which would appear on the chart ( ) .

A.4 weeks
B.5 weeks
C.6 weeks
D.7 weeks

参考解析

解析:

相关考题:

Assume that you have a network where an activity on the critical path can be crashed by two weeks. If the activity is actually crashed by two weeks, then:A.The project's schedule will be reduced by weeks.B.The available slack on the noncritical paths will increase.C.A new critical path may appear after the crash.D.All of the above.E.A and B only.

The major difference between PERT and CPM networks is:A.PERT requires three time estimates whereas CPM requires one time estimate.B.PERT is used for construction projects whereas CPM is used for R D.C.PERT addresses only time whereas CPM also includes cost and resource availability.D.PERT requires computer solutions whereas CPM is a manual technique.E.PERT is measured in days whereas CPM uses weeks or months.

Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.A . 2B . 3C . 4D . 5E . 7

Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.A . 2, 10B . 4, 12C . 6, 14D . 7, 15E . 9, 17

Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.A . 11, 13B . 12, 14C . 13, 15D . 14, 16E . 15, 17

A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:A . 4 weeksB . 5 weeksC . 6 weeksD . 7 weeksE . None of the above.

124 A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:A. 4 weeksB. 5 weeksC. 6 weeksD. 7 weeksE. None of the above

170 Assume that you have a network where an activity on the critical path can be crashed by two weeks. If the activity is actually crashed by two weeks, then:A. The project's schedule will be reduced by 2 weeks.B. The available slack on the noncritical paths will increase.C. A new critical path may appear after the crash.D. All of the above.E. A and B only

117 Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.A. 11, 13B. 12, 14C. 13, 15D. 14, 16E. 15, 17

119 Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.A. 2, 10B. 4, 12C. 6, 14D. 7, 15E. 9, 17

2 Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.A. 2B. 3C. 4D. 5E. 7

● Assume that you have a network where an activity on the critical path can be crashed by two weeks. If the activity is actually crashed by two weeks, then:A The project's schedule will be reduced by 2 weeks.B The available slack on the noncritical paths will increase.C A new critical path may appear after the crash.D All of the above.E A and B only.

I would rather __ two weeks earlier. A.you should come hereB.you come hereC.you must comeD.you came

It was three weeks later ____ he heard the news.A which B that C after D when

_______ another three weeks, I would have been able to finish the experiment.A. GivenB. GivingC. To giveD. Having given

tom____to america with his parents. They____back in two weeks. A)have gone;will comeB)has gone;will comeC)have been;will comeD)havebeen; come

I would rather()two weeks earlier.A. you should come hereB. you came hereC. you had come here

Tom () since he lost his job three weeks ago. A、has employedB、was unemployedC、had been unemployedD、has been unemployed

The train()just three weeks() complete a journey that()six weeks by sea.A. spent…on; takes in toB. pay…for; takes on toC. took…to; takes up to

III读理解. (20分)ADear John,Thank you very much for your letter. I am glad that you enjoyed your holiday with me.We enjoyed having you and your sister here. We hope that you will both be able to come again next ear. Perhaps you'll be'able to stay longer next time you come. A week is not really long enough, is it? If your school has five weeks holiday next year, perhaps you'll be able to stay with us for two or three weeks.We have been back at school for three weeks now. It feels like three months ! I expect that you are both working very hard now that you are in Grade Eight. I shall have to work hard next year when I am in Grade Eight. Tom and Ann won’t be in Grade Eight until 2011.They went for a picnic yesterday, but I didn't go with them because I cut my foot and I couldn't walk very well. They went to an island and enjoyed themselves there. Do you still re’member the island? That's where all five of us spent the last day of our holiday.Tom, Ann and I send our best wishes to Betty and you. We hope to see you soon.Yours sincerely,Michael( )21.________ stayed with Michael for a holiday.A. Only JohnB. Tom and AnnC. John and his sisterD. Only Tom

You and I shall get a ______ holiday of two and three weeks.A.respectfulB.respectiveC.respectableD.respecting

单选题What is Mr. Weeks proud of?AAll his students have become famous persons.BAll his students often write to him.CSome of his students have been famous.DHe’s been a teacher for twenty-six years.

单选题When did Jacky experience his ordeal?ALast FridayB2 weeks agoC3 weeks ago

单选题Tom()since he lost his job three weeks ago.Ahas employedBwas unemployedChad been unemployedDhas been unemployed

单选题How long do the English courses last?A4 days.B2 weeks.C3 weeks.D4 weeks.

单选题Which of the following is the best version of sentence 1 (reproduced below)?Mike Reynolds who is the author of the book, The New Girl came to our school to speak about his book, which tells about him portraying a woman for six weeks.A(As it is now)BMike Reynolds, the author of The New Girl, spoke at our school about his book, in which he describes how he portrayed a woman for six weeks.CMike Reynolds, the author of The New Girl, came to our school and told us about his book, where he portrayed a woman for six weeks.DThe author of The New Girl, Mike Reynolds came to our school to speak, in it he portrayed a woman for six weeks,EThe author of The New Girl, Mike Reynolds, spoke at our school about his book, that portrays a woman for six weeks.

单选题Final exams were incredibly comprehensive, and went on for two weeks, which length made it seem as if they would never end.Acomprehensive, and went on for two weeks, which length madeBcomprehensive and since they went on for two weeks, that madeCcomprehensive and, since they went on for two weeks, to makeDcomprehensive and went on for two weeks, which madeEcomprehensive and, by going on for two weeks, it made