The cost of construction as _______ as the construction period has already increased twofold over previous estimates.A.good B.well C.fine D.far

The cost of construction as _______ as the construction period has already increased twofold over previous estimates.

A.good
B.well
C.fine
D.far

参考解析

解析:

相关考题:

Which of the following is referred to as sunk cost:A . management reserveB . contingency fundC . cost budgeted for construction under waterD . expended funds over which there is no further controlE . forecasted budget over-runs

65 Which of the following is referred to as sunk cost:A. management reserveB. contingency fundC. cost budgeted for construction under waterD. expended funds over which there is no further controlE. forecasted budget over-runs

The construction of the new building will cost () 1,000,000 dollars, and it’s not easy to get so much money. A.at lastB.at mostC.at leastD.at large

Which order of steps is followed in carrying out the project?A. Assessment-Prototype-Design-Construction.B. Assessment-Design-Prototype-Construction.C. Design-Assessment-Prototype-Construction.D. Design-Prototype-Assessment-Construction.

(c) State the specific inquiries you should make of Robson Construction Co’s management relevant to itsaccounting for construction contracts. (6 marks)

The construction of the bridge () due to the snowstorm. A.suspendB.suspendingC.has been suspendedD.suspended

We are of course() that the period for completion of your project has already been exceeded .A. knowB. to knowC. awareD. sure

_____ that they eventually reduce the amount of labor needed on construction sites by 90 percent.A:So clever are the construction robotsB:Such construction robots are cleverC:So clever the construction robots areD:Such clever construction robots are

Which of the following is a benefit of NAS over SAN?() A. Higher data integrityB. Lower cost of implementationC. Higher redundancyD. Increased performance

The use of liners in riveted construction is eliminated by using ______.A.lapped constructionB.strapped constructionC.joggled constructionD.belted construction

What is the period of validity of the SOLAS required Cargo Ship Safety Construction Certificate?A.12 monthsB.24 monthsC.48 monthsD.60 months

In vessel construction,a greater number of watertight bulkheads results in ______.A.increased capacity to set flooding boundariesB.decreased capacity to set flooding boundariesC.reduced compartmentationD.greater deck load capacity

Expansion at EverallAfter four consecutive years of record-breaking growth, Everall Technologies has announced plans to 41 its office facilities on Warner Road. The company has added over 200 employees in the last ten years alone, and is desperately in need of more space.According to an Everall spokesperson, the construction firm chosen to undertake the project is Build Lite Inc., and the work is estimated to take a little over a year to complete.42in the plans are a four-storey sales center, an auditorium with seating for 500, and a parking lot able to accommodate up to 1,200 vehicles. Both Everall and Build Lite have declined to43the cost of the project at this time. However, independent analysts predict it could reach over $10 million.阅读以上短文,回答191-193题。第41题答案是__________A.submitB.expandC.releaseD.organize

Construction on a new wing at the Markunas Museum ____as soon as additional funding has been arranged.A.has been resumedB.to be resumingC.was resumedD.will resume

The phrase“boys and girls”is a(n)( ) A.subordinate endocentric construction B.coordinate endocentric construction C.subordinate exocentric construction D.coordinate exocentric construction

So far the construction of the two new bridges over the river ().A、have been completedB、has been completedC、has completedD、have completed

Which of the following is a benefit of NAS over SAN?()A、Higher data integrityB、Lower cost of implementationC、Higher redundancyD、Increased performance

A System x administrator is considering new storage subsystems. Which is a benefit of SAS over Solid State of the following?()A、Higher transfer speedsB、Increased power consumption with Solid StateC、Increased bandwidthD、Cost per MB

单选题What is the period of validity of the SOLAS required Cargo Ship Safety Construction Certificate? ()A12 monthsB24 monthsC48 monthsD60 months

单选题The use of liners in riveted construction is eliminated by using().Alapped constructionBstrapped constructionCjoggled constructionDbelted construction

单选题The construction of the new bridge has been()for two weeks because of the bad weather.AdevotedBdevelopedCdependedDdelayed

单选题Which of the following is a benefit of NAS over SAN?()A Higher data integrityB Lower cost of implementationC Higher redundancyD Increased performance

单选题The trend nowadays is to build the frame box as a separate fabricated construction and then, after stress relieving and machining the mating surfaces, to mount it on the ().This has the advantage of saving weight.AseatingBbedplateCentablatureDcylinder block

单选题So far the construction of the two new bridges over the river ().Ahave been completedBhas been completedChas completedDhave completed

填空题Worldwide rainfall over land has increased by about one percent.____

单选题In ship construction,frame spacing is().Agreater at the bow and sternBreduced at the bow and sternCuniform over the length of the vesselDuniform over the length of the vessel,with the exception of the machinery spaces,where it is reduced due to increased stresses

单选题Il est sûr et certain. En ce qui concerne de la structure de cette phrase, il s’agit de _____.Ala construction pléonastiqueBla construction elliptiqueCla construction antiphrastiqueDla construction détachée