Which action must be taken when an individual cargo tank is closed off from the inert gas system by the tank isolation valve?A.The tank must be gas freedB.The tank must be ballastedC.The tank must be vented to the atmosphereD.The bypass valve must also be closed

Which action must be taken when an individual cargo tank is closed off from the inert gas system by the tank isolation valve?

A.The tank must be gas freed

B.The tank must be ballasted

C.The tank must be vented to the atmosphere

D.The bypass valve must also be closed


相关考题:

An inert gas system installed on a tanker is designed to ______.A.aid in the stripping and cleaning of cargo tanksB.increase the rate of discharge of cargoC.force toxic and explosive fumes from a cargo tank to vent to the outside atmosphereD.lower the oxygen levels inside cargo tanks,making explosion nearly impossible

How does an inert gas system on a tanker function to prevent explosions in cargo tanks?A.De-energizes the "charged mist" effectB.Maintains a positive pressure on the vent header to cool the flammable vaporsC.Inert gas filters out the flammable vapors from the cargo tank spacesD.Inert gas dilutes the flammable vapor and air concentrations to keep them below the lower explosive limit

A cargo tank that is initially gas freed,can be inerted by introducing inert gas by a process known as ______.A.dilutionB.displacementC.precipitationD.Either A or B

The purpose of inert gas systems aboard tank vessels is to ______.A.allow sufficient oxygen in the tank to sustain lifeB.prevent outside air from entering the tankC.provide increase in cargo discharge pressureD.comply with double hull pollution prevention regulations

Which method is used to supply inert gas from a flue gas system to the cargo tanks?A.Exhaust gas pressure from the stackB.High capacity fanC.Inert gas compressorD.Natural aspiration

You are discharging cargo and the inert gas system is in operation to inert the tanks. The pressure in a tank being discharged starts to drop below the allowable limit. What action should you take?A.Cut in another IG fan to increase gas flowB.Open the pressure control valve until the pressure increasesC.Open the tank isolation valve to the fully open positionD.Reduce the pumping rate

By regulation,cargo tank atmosphere must be inert before and during which operation ________.A.StrippingB.LoadingC.CleaningD.All of the above

Inerting means ______.A.The introduction of inert gas into a tank with the object of reducing the oxygen content to below 8% by volumeB.The introduction of inert gas into a gas free tank for the purpose of reducing the oxygen content to below 8% by volumeC.The introduction of inert gas into a cargo tank during cargo discharge to replace the volume of discharged cargoD.All of the above

The deck water seal of the inert gas system ______.A.Cools the inert gas and prevents soot from entering the cargo tanksB.Acts as an emergency shutdown when inlet pressures exceed the safe working pressureC.Prevents the backflow of hydrocarbon gasses into nonhazardous areasD.Relieves sudden large overpressures in the system

When a non-volatile cargo is carried in a tank that has not been previously gas freed,then that tank shall ______.A.be purged with hydrocarbon gas prior to loadingB.be gas-freed after loading operationsC.not be maintained in an inert conditionD.be maintained in an inert condition

When a tank is to be gas freed after washing,the concentration of hydrocarbon vapour should be reduced by purging the inerted cargo tank with ______.A.the oxygenB.the gasC.the inert gasD.the hydrocarbon vapour

Which statement about inert gas pressures in a cargo tank is TRUE ________.A.The pressures of the inert gas in the tank may create excessive pressure at the pump while dischargingB.Gas pressures should be maintained at the highest permissible level throughout the discharging processC.High gas pressures may cause pyrophoric oxidation in the tankD.High gas pressures may cause loss of suction when stripping

You are planning to use a crude oil washing system.What precaution must be taken with the tank as the source for the washing machines ________.A.It must be debottomed and the level lowered by at least one meterB.The oil in the source tank must be sampled for compatibilityC.The source tank must have been crude oil washed at least once in the past 150 daysD.The inert gas system must lower the oxygen content to a maximum of 12% oxygen in the tank

An inert gas system is designed to reduce the possibility of tank explosions by ______.A.eliminating sparks and fire in the vicinity of cargo tanksB.removing all hydrocarbon gases from the cargo tanksC.blanketing cargo tanks with inert foamD.reducing the oxygen concentration below levels necessary for combustion

单选题The purpose of inert gas systems aboard tank vessels is to().Aallow sufficient oxygen in the tank to sustain lifeBprevent outside air from entering the tankCprovide increase in cargo discharge pressureDcomply with double hull pollution prevention regulations

单选题How does an inert gas system on a tanker function to prevent explosions in cargo tanks? ()ADe-energizes the charged mist effectBMaintains a positive pressure on the vent header to cool the flammable vaporsCInert gas filters out the flammable vapors from the cargo tank spacesDInert gas dilutes the flammable vapor and air concentrations to keep them below the lower explosive limit

单选题The deck water seal of the inert gas system().Acools the inert gas and prevents soot from entering the cargo tanksBacts as an emergency system shutdown when the inlet pressures exceed the safe working pressure in the hazardous zoneCprevents the backflow of hydrocarbon gasses into nonhazardous areasDrelieves sudden large overpressures in the system

单选题An inert gas system is designed to reduce the possibility of tank explosions by().Aeliminating sparks and fire in the vicinity of cargo tanksBremoving all hydrocarbon gases from the cargo tanksCblanketing cargo tanks with inert foamDreducing the oxygen concentration below levels necessary for combustion

单选题A cargo tank that is initially gas freed,can be inerted by introducing inert gas by a process known as().AdilutionBdisplacementCprecipitationDEither A or B

单选题By regulation,cargo tank atmosphere must be inert before and during which operation?()AStrippingBLoadingCCleaningDAll of the above

单选题What action must be taken when an individual cargo tank is closed off from the inert gas system by the tank isolation valve?()AThe tank must be gas freedBThe tank must be ballastedCThe tank must be vented to the atmosphereDThe bypass valve must also be closed

单选题Which action must be taken when an individual cargo tank is closed off from the inert gas system by the tank isolation valve?()AThe tank must be gas freedBThe tank must be ballastedCThe tank must be vented to the atmosphereDThe bypass valve must also be closed

单选题Which step is NOT generally taken when gas-freeing a tank?().AWashing the tank interior with sea waterBApplication of degreasing solventsCRemoval of corrosion products and sludgeDFresh air ventilation

单选题You are discharging cargo and the inert gas system is in operation to inert the tanks. The pressure in a tank being discharged starts to drop below the allowable limit. What action should you take? ()ACut in another IG fan to increase gas flowBOpen the pressure control valve until the pressure increasesCOpen the tank isolation valve to the fully open positionDReduce the pumping rate

单选题An inert gas system installed on a tanker is designed to().Aaid in the stripping and cleaning of cargo tanksBincrease the rate of discharge of cargoCforce toxic and explosive fumes from a cargo tank to vent to the outside atmosphereDlower the oxygen levels inside cargo tanks,making explosion nearly impossible

单选题Inerting means().Athe introduction of inert gas into a tank with the object of reducing the oxygen content to below 8% by volumeBthe introduction of inert gas into a gas free tank for the purpose of reducing the oxygen content to below 8% by volumeCthe introduction of inert gas into a cargo tank during cargo discharge to replace the volume of discharged cargoDAll of the above

单选题Which method is used to supply inert gas from a flue gas system to the cargo tanks?()AExhaust gas pressure from the stackBHigh capacity fanCInert gas compressorDNatural aspiration

单选题The deck water seal of the inert gas system().Acools the inert gas and prevents soot from entering the cargo tanksBacts as an emergency shutdown when inlet pressures exceed the safe working pressureCprevents the backflow of hydrocarbon gasses into nonhazardous areasDrelieves sudden large overpressures in the system