127 The budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) _____ budget.A. Unauditable.B. Undistributed.C. Preauthorized.D. Contingency.E. In-process
127 The budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) _____ budget.
A. Unauditable.
B. Undistributed.
C. Preauthorized.
D. Contingency.
E. In-process