大多质量问题的起因是:( )A.员工不关心B.员工缺乏激励C.管理层不重视D.规范有问题
大多质量问题的起因是:( )
A.员工不关心
B.员工缺乏激励
C.管理层不重视
D.规范有问题
相关考题:
Employee unions would most likely satisfy which level in Maslow's hierarchy of needs?A BelongingB Self-actualizationC EsteemD SafetyE Empowerment
38 A calendar that identifies when a project may be performed on an activity is called a:A. Project calendar.B. Resource calendar.C. Milestone point.D. Key point.E. Work unit
65 Which of the following is referred to as sunk cost:A. management reserveB. contingency fundC. cost budgeted for construction under waterD. expended funds over which there is no further controlE. forecasted budget over-runs
169 Management by Objectives (MBO)A. is a method used to evaluate personnel by objectively comparing them to common performance standardsB. requires a supervisor and a subordinate to jointly establish performance objectivesC. should be the responsibility of the organization's personnel departmentD. should always involve the establishment of objectives that are quantifiableE. B and D
你在管理一个为50岁以上的人开发一种以黄豆子基础的富含镁元素的营养饮料项目。你最近听到客户将你的进度报告称做“古巴比伦国王的密码”,似乎它们是用象形文字写成的,除了埃及考古学者以外没有人能读懂。这种情况能通过什么来避免? ( )A.在项目开始时通知客户他们将收到什么类型的报告B.应用风险管理技术确定客户的问题C.雇用一个专业报告写作者来写标准的报告D.致力于沟通计划
变更要求是一个项目的主要部分,也是项目经理控制范围变更的一种方法。变更要求是—的结果:a. 变更卖主提供的成分的质量b. 一个有益的变更,它发生在范围被批准之后c. 产品描述的一个错误或遗漏d. 一个修改的“做或买”的决定e. 上述所有
活动A历时为3天,开始于4号星期一上午,后续活动B和A的关系为结束一开始。结束一开始关系有3天滞后,活动B历时为4天,星期天为非工作日,从这些数可以得到什么?A、 两个活动总历时为8天B、 活动A开始日期和活动B结束的日历时间为11天C、 活动B结束日期为13号星期三D、 活动A开始日期和活动B结束的日历时间为14天
对项目进行总结后你发现按进度计划要花28000小时,已经挣得25000小时,支付26000小时,正确结论应该是:A、 项目的成本效率非常有利B、 我们需要趋势分析报告C、 项目滞后于进度计划D、 项目超前于进度计划