3 As project manager, you wish to impose a standard method by which subordinates calculate project costs. Which level of communication should be required for this effort?A. Face-to-faceB. TelephoneC. WrittenD. Non-verbalE. All of the above should be required

3 As project manager, you wish to impose a standard method by which subordinates calculate project costs. Which level of communication should be required for this effort?

A. Face-to-face

B. Telephone

C. Written

D. Non-verbal

E. All of the above should be required


相关考题:

Creation of project objectives:A.allows for data collection and analysis and progress reporting against which standards of performance can be measured.B.is accomplished by selection of measurable variables against which performance can be judged.C.is required before funding of the project by the project sponsor.D.all of the above.E.A and B only

It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?A . Direct labor dollarsB . Direct labor hours.C . Overhead rates.D . Procurement costs.E . None of the above.

Which of the following fall(s) under the responsibilities of a project manager?A . Labor relations with project personnelB . Affirmative actionC . Personnel trainingD . Discrimination and equal employment opportunityE . All of the above

Which of the following time robbers end up creating additional work for the project manager and the project office?A . Failure to delegateB . Changes without notification or directionC . Unreasonable time constraintsD . Over directing peopleE . All of the above

As project manager, you wish to impose a standard method by which subordinates calculate project costs. Which level of communication should be required for this effort?A Face-to-faceB TelephoneC WrittenD Non-verbalE All of the above should be required.

A project manager can exchange information with the project team using which media?A tactileB audioC olfactoryD visualE All of the above.

A project manager trying to communicate accurately to the team should use:A the language of the team membersB the language of the project managerC non-verbal methodsD written memosE All of the above.

When subordinates know pertinent information that is not known by the project manager, the result is:A BlindspotB FacadeC region of influenceD Communication power baseE None of the above

A line manager possesses information which the project team needs, but withholds the information. The results in a(n):A BlindspotB FacadeC region of influenceD Communication power baseE None of the above

164 A line manager possesses information which the project team needs, but withholds the information. The results in a(n):A. BlindspotB. FacadeC. region of influenceD. Communication power baseE. None of the above

174 When subordinates know pertinent information that is not known by the project manager, the result is:A. BlindspotB. FacadeC. region of influenceD. Communication power baseE. None of the above

193 A project manager trying to communicate accurately to the team should use:A. the language of the team membersB. the language of the project managerC. non-verbal methodsD. written memosE. All of the above.

19 It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?A. Direct labor dollarsB. Direct labor hours.C. Overhead rates.D. Procurement costs.E. None of the above

79 Which of the following planning considerations is often overlooked?A. Planning for project termination.B. Qualified project manager assignment.C. Insuring top management support.D. Clearly defined tasks.E. All of the above

116 Which of the following time robbers end up creating additional work for the project manager and the project office?A. Failure to delegateB. Changes without notification or directionC. Unreasonable time constraintsD. Over directing peopleE. All of the above

155 A project manager can exchange information with the project team using which media?A. tactileB. audioC. olfactoryD. visualE. All of the above

193 Creation of project objectives:A. allows for data collection and analysis and progress reporting against which standards of performance can be measured.B. is accomplished by selection of measurable variables against which performance can be judged. C. is required before funding of the project by the project sponsor.D. all of the above.E. A and B only

12 Which of the following fall(s) under the responsibilities of a project manager?A. Labor relations with project personnelB Affirmative actionC. Personnel trainingD. Discrimination and equal employment opportunityE. All of the above

121 As project manager, you wish to impose a standard method by which subordinates calculate project costs. Which level of communication should be required for this effort?A. Face-to-faceB. TelephoneC. WrittenD. Non-verbalE. All of the above should be required

94 Which of the following fall(s) under the responsibilities of a project manager?A. Labor relations with project personnelB. Affirmative actionC. Personnel trainingD. Discrimination and equal employment opportunityE. All of the above

75 A project manager trying to communicate accurately to the team should use:A. the language of the team membersB. the language of the project managerC. non-verbal methodsD. written memosE. All of the above

In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project‘s communication. According to Metcalfe‘s Law, a project with 10 stakeholders has()potential communication channels.A.10B.45C.50D.100

● Which of the following planning considerations is often overlooked?A Planning for project termination.B Qualified project manager assignment.C Insuring top management support.D Clearly defined tasks.E All of the above.

In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.A、10B、45C、50D、100

You work as a Web Developer at Certkiller.com. You are in the process of creating a Webapplication using Microsoft ASP.NET 3.5.  This application will be part of a solution that contains a Windows Communication Foundation (WCF) service project. The Web application will be used to make calls to a service identified in theWCF service project. Management is planning to host the Web application on a separate serverfrom the WCF service. They want the WCF service to perform remotely. You need to add areference to the WCF service.  What should you do?()A、You should add an assembly reference to the project.B、You should add a project reference to the project.C、You should add a Web reference to the project.D、You should add a service reference to the project.

Which is the MOST effective method for generating support for your project plan?()A、Requiring stakeholders to sign-off on project plan componentsB、Requesting input from all stakeholders during the planning processC、Providing an open line of communication regarding the projectD、Clearly illustrating how the project relates to the company’s objectives

The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()A、Data flow modelB、The project critical pathC、Resource loading chartD、WBS (Work Breakdown Structure)