132 Which of the following is an element of procurement management:A. inspectionB. purchasingC. estimatingD. expeditingE. A, B and D only

132 Which of the following is an element of procurement management:

A. inspection

B. purchasing

C. estimating

D. expediting

E. A, B and D only


相关考题:

Which of the following networking methods allows us to show that the last % of one element cannot be completed until % of a previous element has been completed?A.PERTB.ADMC.PDMD.All of the above.E.A and C only.

Which of the following is considered a direct cost for producing a widget?A . The cost of the materials used to produce a widget.B . The labor costs of the workers who actually produced the widget.C . The rent for the building in which the widget was manufacturedD . The salary of senior management and the project sponsorE . A and B only

It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?A . Direct labor dollarsB . Direct labor hours.C . Overhead rates.D . Procurement costs.E . None of the above.

A(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight, storage and loss.A . Inventory control.B . Materials management.C . Procurement.D . All of the above.E . A and C only.

Formal written communication is mandated for which of the following?A scope changes not part of the original projectB taking exception to a specificationC procurement of raw materialsD All of the above.E A and B only

Which of the following is not a method of government procurement.A AssistanceB sealed biddingC competitive proposalsD acquisitionE small purchases

Which is not an element of procurement management?A PurchasingB ExpenditureC MarketingD InspectionE B and D

Which of the following is an element of procurement management:A inspectionB purchasingC estimatingD expeditingE A, B and D only

Which of the following is an element of procurement management:A. inspectionB. purchasingC. estimatingD. expeditingE. A, B and D only

161 Which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous element has been completed?A. PERTB. ADMC. PDMD. All of the above.E. A and C only

19 It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?A. Direct labor dollarsB. Direct labor hours.C. Overhead rates.D. Procurement costs.E. None of the above

94 Which is not an element of procurement management?A. PurchasingB. ExpenditureC. MarketingD. InspectionE. B and D

177 Formal written communication is mandated for which of the following?A. scope changes not part of the original projectB. taking exception to a specificationC. procurement of raw materialsD. All of the above.E. A and B only

35 Which of the following is considered a direct cost for producing a widget?A. The cost of the materials used to produce a widget.B. The labor costs of the workers who actually produced the widget.C. The rent for the building in which the widget was manufacturedD. The salary of senior management and the project sponsorE. A and B only

84 In which of the following cost estimating techniques are statistics models used:A. nonparametric cost estimatingB. parametric cost estimatingC. life cycle cost estimatingD. bottom-up estimatingE. All of the above.

117 Which of the following is not a method of government procurement.A. AssistanceB. sealed biddingC. competitive proposalsD. acquisitionE. small purchases

132 Which of the following contract types has the highest risk to the contractor:A. Firm fixed price (FFP)B. Time and material (TM)C. Cost plus fixed fee (CPFF)D. Cost plus incentive fee (CPIF)E. A and B only

166 In which of the following cost estimating techniques are statistics models used:A. nonparametric cost estimatingB. parametric cost estimatingC. life cycle cost estimatingD. bottom-up estimatingE. All of the above

14 Which of the following is an element of procurement management:A. inspectionB. purchasingC. estimatingD. expeditingE. A, B and D only

43 Which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous element has been completed?A. PERTB. ADMC. PDMD. All of the above.E. A and C only.

Which of the following is not a valid calendaring syntax element?() A. FREQB. BYHOURC. RUNDATED. INTERVALE. BYMINUTE

Establishing a project ( ) involves listen milestones, activities, and deliverables with intendstart and finish dates^of which the scheduling of employees may be an element.A.cost management planB.risk managementC.scope management planD.management schedule

A network vulnerability scanner is part of which critical element of network and system security?() A. host securityB. perimeter securityC. security monitoringD. policy management

Establishing a project ( ) involves listen milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element A.cost management planB.risk management planC.soope management planD.management schedule

An administrator is looking for the "Open RestrictedShell Terminal" option on the HMC GUI. Under which panel is this option available?()A、HMC Management, but only from a local connection.B、Service Management, but only from a local connection.C、Systems Management, but only from a local connection.D、Systems Management, but only from a remote connection.

Which of the following is not a valid calendaring syntax element?()A、FREQB、BYHOURC、RUNDATED、INTERVALE、BYMINUTE

单选题Which of the following is not a valid calendaring syntax element?()AFREQBBYHOURCRUNDATEDINTERVALEBYMINUTE