30 As a control tool, the bar chart (Gantt) methods is most beneficial for:A. rearranging conflicting tasksB. depicting actual versus planned tasksC. showing the outer dependencies of tasksD. A and C.E. A and D

30 As a control tool, the bar chart (Gantt) methods is most beneficial for:

A. rearranging conflicting tasks

B. depicting actual versus planned tasks

C. showing the outer dependencies of tasks

D. A and C.

E. A and D


相关考题:

As a control tool, the bar chart (Gantt) methods is most beneficial for:A.rearranging conflicting tasksB.depicting actual versus planned tasksC.showing the outer dependencies of tasksD.A and C.E.A and D

Bar charts are most appropriate for:A.Comparing actual to planned performance to each activity.B.Showing slack time.C.Showing critical path dependencies.D.Showing which activities can be rearranged in parallel.E.All of the above.

An acceptance control chart has limits that are based on the spec. limits for the product rather than limits which differentiate between random and assignable causes. Under which of the following circumstances should a QC manager consider this type chartA . When the engineering tolerance on a dimension greatly exceeds the natural dispersion of the manufacturing processB . When the number of samples outside the current control chart limits become too costly and cumbersome to investigate.C . When a process is subject to constant but stable tool wear.D . A and B.E . A and C

Which quality management tool would be used to determine potential causes of a production problem?A . control chart.B . Ishikawa diagram.C . scatter diagram.D . histogram.E . run chart.

To determine what causes the majority of quality problems in a process, a very useful tool is the:A . cause and effect diagrams.B . flow chart.C . control chart.D . pareto chart.E . trend chart.

153 To determine what causes the majority of quality problems in a process, a very useful tool is the: A. cause and effect diagrams.B. flow chart.C. control chart.D. pareto chart.E. trend chart

169 Which quality management tool would be used to determine potential causes of a production problem?A. control chart.B. Ishikawa diagram.C. scatter diagram.D. histogram.E. run chart

175 Which of the following scheduling methods uses more of the risk management concepts:A. ADMB. PDMC. CPMD. PERTE. Gantt

96 Bar charts are most appropriate for:A. Comparing actual to planned performance to each activity.B. Showing slack time.C. Showing critical path dependencies.D. Showing which activities can be rearranged in parallel.E. All of the above

25 A work breakdown structure is most useful for:A. identifying individual tasks for a projectB scheduling the start of tasksC. developing a cost estimateD. determining potential delaysE. A and C

107 A work breakdown structure is most useful for:A. identifying individual tasks for a projectB. scheduling the start of tasksC. developing a cost estimateD. determining potential delaysE. A and C

112 As a control tool, the bar chart (Gantt) methods is most beneficial for:A. rearranging conflicting tasksB. depicting actual versus planned tasksC. showing the outer dependencies of tasksD. A and C.E. A and D

● As a control tool, the bar chart (Gantt) methods is most beneficial for:A rearranging conflicting tasksB depicting actual versus planned tasksC showing the outer dependencies of tasksD A and C.E A and D

● Bar charts are most appropriate for:A Comparing actual to planned performance to each activity.B Showing slack time.C Showing critical path dependencies.D Showing which activities can be rearranged in parallel.E All of the above.

A graphical bar With buttons that perform. some of the most common commands.A.Title barB.Tool barC.Status barD.Scroll bar

● To determine what causes the majority of quality problems in a process, a very useful tool is the ().()A. cause and effect diagrams B. flow chartC. control chart D. pareto chart

Most rites of passage have three ___, or parts, in the ritual: separation, transition, and incorporation. A. stagesB. proceduresC. tasksD. periods

A()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.A.gantt chartB.project histogramC.milestone chartD.project flowchart

A__(74)__is a type of bar chart that illustrates a project schedulA.It illustrates the start and finish dates of the terminal elements and summary elements of a project.B.Gantt chartC.project histogramD.milestone chartE.project flowchart

A graphical bar with buttons that perform. some of the most common commands.A.TitlebarB.Tool barC.StatusbarD.Scroll bar

( ) is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project. A.gantt chart B.project histogram C.milestone chart D.project flowchart

The cost performance index(CPI) is the ratio of earned value to ( ) and can be used to estimate the projected cost of completing the project. A. cost variance B.planneD.cost C.PlanneD.value D.actual cost

A chart showing all staff positions and responsibilities () prepared by the Vice President.AwasBhasCwereDhave

()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.A、gantt chartB、project histogramC、milestone chartD、project flowchart

Which report will provide information on the most recently completed  plan?()A、 Report 08 - Job HistogramB、 Report 07 - Job History ListingC、 Report 10B - Actual Production DetailD、 Report 11 - Planned Production Schedule

单选题A chart projection depicting the poles and a small area on either side of a connecting meridian,that is sometimes used for star charts,is the().AAzimuthal gnomonic projectionBLambert conformal projectionCTransverse Mercator projectionDPolyconic projection

单选题Which report will provide information on the most recently completed  plan?()A Report 08 - Job HistogramB Report 07 - Job History ListingC Report 10B - Actual Production DetailD Report 11 - Planned Production Schedule