单选题An administrator is planning a two node cluster containing Node1 and Node2 with a single resource groupnamed RG1. RG1 startup policy will be ’Online on Home Node only’. The home node is Node1. If RG1 fails over to Node2 itmust fall back to Node1. Fall back must take place outside of business hours. The agreed time for fall back is20:00. How will this be achieved with minimum action taken by administrator?()AConfigure the resource group with a fallback policy of Fallback to Higher Priority Node Restart Node1 at20:00BConfigure the resource group with a fallback policy of Never Fallback Manually move the resource groupfrom Node2 to Node1 at 20:00CConfigure the resource group with a fallback policy of Fallback To Higher Priority Node Create aDelayed Fallback Timer policy to meet the requirements Allocate this delayed timer policy to theresource group RG1DConfigure the resource group with a fallback policy of Never Fallback Create a Delayed Fallback Timerpolicy to meet the requirement Specify this delayed timer policy as a Fallback Override to the resourcegroup RG1

单选题
An administrator is planning a two node cluster containing Node1 and Node2 with a single resource groupnamed RG1. RG1 startup policy will be ’Online on Home Node only’. The home node is Node1. If RG1 fails over to Node2 itmust fall back to Node1. Fall back must take place outside of business hours. The agreed time for fall back is20:00. How will this be achieved with minimum action taken by administrator?()
A

Configure the resource group with a fallback policy of Fallback to Higher Priority Node Restart Node1 at20:00

B

Configure the resource group with a fallback policy of Never Fallback Manually move the resource groupfrom Node2 to Node1 at 20:00

C

Configure the resource group with a fallback policy of Fallback To Higher Priority Node Create aDelayed Fallback Timer policy to meet the requirements Allocate this delayed timer policy to theresource group RG1

D

Configure the resource group with a fallback policy of Never Fallback Create a Delayed Fallback Timerpolicy to meet the requirement Specify this delayed timer policy as a Fallback Override to the resourcegroup RG1


参考解析

解析: 暂无解析

相关考题:

单选题Which of the following is a requirement for configuring a service IP address using IPAT via Replacement?()AThe service IP must be in the same logical subnet as all boot IP addressesBThe service IP must be in a different logical subnet to all boot IP addressesCThe service IP must be in the same logical subnet as the persistent IP addressesDThe service IP must be in the same logical subnet as one of the boot IP addresses

单选题In which PowerHA smit top level menu is the menu to suspend application monitoring?()AExtended ConfigurationBSystem Management(C-SPOC)CProblem Determination ToolsDInitialization and Standard Configuration

单选题An architect is configuring a PowerHA cluster in the following way:The cluster will consist of two nodes. Each node will have two boot interfaces configured as a single PowerHA network. The cluster is to have asingle resource group with a single service address.Heartbeating over aliased is not to be used. What is the minimum number of subnets required to implement this cluster?()A1B2C3D4

单选题A customer wants to migrate their existing cluster onto new POWER6 hardware, and in addition requires thecluster to be migrated from PowerHA version 5.3 to 5.5. Given that AIX 6.1 and PowerHA 5.5 filesets arealready installed in the new hardware, which of the following methods would allow the customer to maintaintheir current cluster configuration?()AAdd the new nodes to the existing cluster, and perform a rolling migration and remove the original nodesfrom the clusterBAdd the new nodes to the existing cluster, and perform a non-disruptive upgrade and remove the originalnodes from the cluster.CCreate a snapshot of the existing cluster and apply the snapshot to the new cluster. Start cluster serviceson the new cluster and stop the original clusterDCreate a snapshot of the existing cluster and apply the snapshot to the new cluster. Stop cluster serviceson the original cluster and start on the new cluster

单选题An administrator wants to install Web SMIT on a node that is not part of a cluster. Which PowerHA filesetprovides this function?()Acluster.sysmgt.wsmBcluster.es.client.wsmCcluster.es.server.websmDcluster.sysmgt.websm.rte

单选题A customer synchronizes the cluster in a virtualized environment. During the process the following warning isdisplayed: "For nodes with a single Network Interface Card per logical network configured, it is recommended to includethe file ’/usr/es/sbin/cluster/netmon.cf’ with a pingable IP address as described in the PowerHA PlanningGuide". What should the customer do next?()AIgnore the warning as synchronization completed successfully.BPopulate the /usr/es/sbin/cluster/netmon.cf file with one or many IP addresses external to the cluster.CCreate another virtual adapter on each node and set-up PowerHA networking in a more traditional fashionDPopulate the /usr/es/sbin/cluster/netmon.cf file with any of the boot IP addresses on one of the othercluster nodes

单选题An administrator is beginning a set of failover tests. The administrator would like to have clean log files foreach test. Which command will achieve this?()AclcycleBclrefreshCcllogcycleDcllogrotate

单选题Which of the following is required to ensure the completion of all tests within the automated procedure of thecluster test tool?()AApplication monitoring has been configuredBOnly disk heartbeat networks have been usedCCluster nodes are attached to two IP networksDResource Group dependencies have been configured

单选题During a resource group takeover operation, the resource group was found to go into error state. A tail of thehacmp.out file released the following message: Aug 3 12:57:20 EVENT FAILED:// -1: event_error 1 TE_RG_MOVE -1 WARNING:// Cluster PowerHA has beenrunning recovery program ’/usr/es/sbin/cluster/events/rg_move.rp’ for 360 seconds. Please check clusterstatus. What command can the administrator issue to cause the cluster to continue processing?()AclruncmdBclrestartCclcontinueDclresactive

单选题A customer needs to test the failover capabilities of their cluster. Which of the following AIX commands, whenissued from the command line, will simulate a node crash and cause the cluster resource group running onthat server to fail over to another node?()AclstopBhalt -qCshutdown -FDstopsrc -s cluster

单选题A customer needs to test the failover capabilities of their cluster. Which of the following AIX commands, whenissued from the command line, will simulate a node crash and cause the cluster resource group running onthat server to fail over to another node?()AclstopBhalt -qCshutdown -FDstopsrc -s cluster