名词解释题危险性(risk)

名词解释题
危险性(risk)

参考解析

解析: 暂无解析

相关考题:

● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk Analysis.Risk Monitoring and Control

In acceptance sampling, if the sample size is kept the same but the acceptance number is increased, which of the following will be true:A . buyer's risk will decreaseB . vendor's risk will decreaseC . producer's risk will decreaseD . consumer's risk will increaseE . C and D only

Screening of risk events for potential risk is known as _____ .A problem structuring.B risk identificationC risk quantificationD risk modelingE risk mitigation

The schedule risk is the _____ .A the accumulated "expected' durations which maintain project completion.B Critical Path adjusted by "high-risk" activity float.C highest risk path that maintains quality.D Critical Path when calculated with "most likely" duration.E highest risk path that contributes the most risk toward the project completion.

Risk Event Status is defined as _____ .A Risk Probability x Amount At Stake.B the severity of the consequences.C how likely the event is to occur with risk.D (Cost + Benefit + Business Risk) / Insurable Risk.E B and C

Risk event probability is defined as:A the total number of possible events divided into the expectations or frequency of the risk eventB the number of times the risk event may occurC the fraction of the total project tasks which may be affected by the risk eventD the total number of possible events divided into the consequences of the risk event.E A and B

In Project Risk Management, Risk Response may include actions to:A reduce the probability of risk eventsB change the scope, budget, schedule or quality specifications of the projectC reduce the consequences or severity of impacts of a potential risk eventD A and CE All of the above.

Total Project Risk:A should not be calculated for small projectsB is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.C Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.D A and BE A and C

Risk can be divided into two basic types; business risk and pure (or insurable risk). Of the following, which one(s) fall(s) under business risk?A liability lossB direct property lossC profit lossD personnel-related lossE B and C

Total project risk can be defined as:A the sum of the probabilities of project risks events times the sum of consequences of those risksB the sum of the products of each project risk event times its consequencesC the sum of the consequences of all project risk eventsD the sum of the probabilities of all project risk eventsE 1 - the sum of the probabilities of all project risk events.

Giving a part of project work to a contractor is an example of:A risk mitigationB risk assignmentC risk delegationD risk deflectionE risk assumption

196 Giving a part of project work to a contractor is an example of:A. risk mitigationB. risk assignmentC. risk delegationD. risk deflectionE. risk assumption

70 Risk Event Status is defined as _____ .A. Risk Probability x Amount At Stake.B. the severity of the consequences.C. how likely the event is to occur with risk.D. (Cost + Benefit + Business Risk) / Insurable Risk.E. B and C

113 Screening of risk events for potential risk is known as _____ .A. problem structuring.B. risk identificationC. risk quantificationD. risk modelingE. risk mitigation

In Project Risk Management, Risk Response may include actions to:A. reduce the probability of risk eventsB. change the scope, budget, schedule or quality specifications of the projectC. reduce the consequences or severity of impacts of a potential risk eventD. A and CE. All of the above

John Pentanol was appointed as risk manager at HZ Company a year ago and he decided that his first task was to examine the risks that faced the company. He concluded that the company faced three major risks, which he assessed by examining the impact that would occur if the risk were to materialise. He assessed Risk 1 as being of low potential impact as even if it materialised it would have little effect on the company’s strategy. Risk 2 was assessed as being of medium potential impact whilst a third risk, Risk 3, was assessed as being of very high potential impact.When John realised the potential impact of Risk 3 materialising, he issued urgent advice to the board to withdraw from the activity that gave rise to Risk 3 being incurred. In the advice he said that the impact of Risk 3 was potentially enormous and it would be irresponsible for HZ to continue to bear that risk.The company commercial director, Jane Xylene, said that John Pentanol and his job at HZ were unnecessary and that risk management was ‘very expensive for the benefits achieved’. She said that all risk managers do is to tell people what can’t be done and that they are pessimists by nature. She said she wanted to see entrepreneurial risk takers in HZ and not risk managers who, she believed, tended to discourage enterprise.John replied that it was his job to eliminate all of the highest risks at HZ Company. He said that all risk was bad and needed to be eliminated if possible. If it couldn’t be eliminated, he said that it should be minimised.(a) The risk manager has an important role to play in an organisation’s risk management.Required:(i) Describe the roles of a risk manager. (4 marks)(ii) Assess John Pentanol’s understanding of his role. (4 marks)(b) With reference to a risk assessment framework as appropriate, criticise John’s advice that HZ shouldwithdraw from the activity that incurs Risk 3. (6 marks)(c) Jane Xylene expressed a particular view about the value of risk management in HZ Company. She also said that she wanted to see ‘entrepreneurial risk takers’.Required:(i) Define ‘entrepreneurial risk’ and explain why it is important to accept entrepreneurial risk in businessorganisations; (4 marks)(ii) Critically evaluate Jane Xylene’s view of risk management. (7 marks)

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control

Workarounds are determined during which risk management process? (75).A. Risk identificationB. Quantitative risk analysisC. Plan risk responsesD. Risk monitoring and control

Setting redundant components in subsystem to handle with the risks brought by the defaults of original components, what kind of risk response strategy is this ? ( 75 ).A.Risk avoidanceB.Risk acceptanceC.Risk mitigationD.Contingency plan

setting redundant components in subsystem to handle with the risks brought by the defaultsof original components,what kind of risk response strategy is this?()A.risk avoidanceB.risk acceptanceC.risk mitigationD.contingency plan

()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.A.Identity risksB.Control risksC.Plan risk responsesD.Plan risk management

如果将T3101设置抬高,可能会造成什么影响?()A.risk of SDCCH CongestioB.risk of PCH CongestioC.risk of TCH CongestioD.risk of AGCH Congestio

setting redundant components in subsystem to handle with the risks brought by the defaults of original components,what kind of risk response strategy is this?()A、risk avoidanceB、risk acceptanceC、risk mitigationD、contingency plan

如果将T3101设置抬高,可能会造成什么影响?()A、risk of SDCCH CongestioB、risk of PCH CongestioC、risk of TCH CongestioD、risk of AGCH Congestio

The general additional risks including()are covered in all risks coverage.A、risk of shortageB、risk of leakageC、strikes riskD、risk of rust

单选题The()process analyzes the effect of risk events and assigns a numerical rating to those risks.ARisk IdentificationBQuantitative Risk AnalysisCQualitative Risk AnalysisDRisk Monitoring and Control

名词解释题危险性管理(risk management)

名词解释题危险性(risk)