单选题In approximating costs, the estimator considers the possible causes ofvariation of the cost estimates, including()AbudgetBplanCriskDcontract
单选题
In approximating costs, the estimator considers the possible causes ofvariation of the cost estimates, including()
A
budget
B
plan
C
risk
D
contract
参考解析
解析:
该题的关键词为"approximating costs、 causes ofvariation",其语句结构为"the estimator (主语)considers(谓语)the possible causes ofvariation of the cost estimates, including()",含义为"估算人员考虑对成本估算可能造成影响的原因,包括什么"。估算成本考虑不确定性,而不确定性正是风险的一个基本特征,所以选择选项C。
相关考题:
When comparing the cost of competing projects, which of the following is typically NOT considered?A.Opportunity costs.B.Direct costs.C.Sunk costs.D.Indirect costs.E.Burden rates.
The Cost Performance Index (CPI) measures:A.cost of work performed vs planned costs.B.work performed vs cost of work performed.C.work performed vs planned work.D.direct costs vs indirect costs.E.floating costs vs. sunk costs.
Sunk costs are:A.future costs held in reserve.B.costs invested in commodities.C.expended costs over which we have no control.D.expended costs over which we have no more controlE.tax credits
The initial cost of a product and the product's operation and maintenance costs _____ .A . increases perceived value when balanced.B . are incidental to each other because initial costs are "sunk"C . decreases design costs as operation periods increaseD . provides perceived function value and product social dysfunctionE . are integrally related with each other because initial costs are "sunk".
I want to learn() about the industry so that I'm better prepared. A、possible ofB、as much as possibleC、as possible muchD、as possible as much
57 The initial cost of a product and the product's operation and maintenance costs _____ .A. increases perceived value when balanced.B. are incidental to each other because initial costs are "sunk"C. decreases design costs as operation periods increaseD. provides perceived function value and product social dysfunctionE. are integrally related with each other because initial costs are "sunk"
198 Sunk costs are:A. future costs held in reserve.B. costs invested in commodities.C. expended costs over which we have no control.D. expended costs over which we have no more controlE. tax credits
68 The Cost Performance Index (CPI) measures:A. cost of work performed vs planned costs.B. work performed vs cost of work performed.C. work performed vs planned work.D. direct costs vs indirect costs.E. floating costs vs. sunk costs.
We very much appreciate your efforts________ A.our production costs must be no more than 15 percent.B.has done damage to our reputationC.to negotiate with youD.to make this product possible
● In approximating costs, the estimator considers the possible causes ovariation of the cost estimates, including(71) 。A.budgetB.planC.riskD.contract
Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of(70)to facilitate comparisons both within and across projects.The(71 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.A.accuracyB.approximationC.specificationD.summary
Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.A.accuracyB.approxinationC.specificationD.summary
The author considers the bet between the lawyer and the banker.A. interestingB. ridiculousC. capriciousD. instructive
In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including.(71)。A.budgetB.planC.riskD.contract
( )are those costs that cannot be directly traced to a specific project and therefore will be accumulated and allocated equitably over multiple projects by some approved and documented accounting procedure( )是指不能直接追溯到特定项目的成本,因此将通过一些批准和记录的会计程序在多个项目上平均累计和分配。A.Direct costs直接成本B.Operation costs运营成本C.Indirect costs间接成本D.Implement costs实施成本
Estimating schedule activity costs involves developing an approximation of the costs of theresources needed to complete each schedule activity. Cost estimating includes identifying andconsidering various costing alternatives. For example, in most application areas, additional workduring a design phase is widely held to have the potential for reducing the cost of the executionphase and product operations. The cost estimating process considers whether the expectedsavings can offset the cost of the A.project scope statement B.statement of work C.project management plan D.project policy
Which part of the European is still Catholic?( ) A.The southern and eastern two-thirds. B.The northern and western one-third. C.The Spanish-ruled Netherlands. D.The northern part approximating to modern Holland.
We have to get that car fixed ().A、no matter it costs how muchB、no matter how much costs itC、no matter how much it costsD、no matter how much does it cost
单选题It is useful to science considering the earth as an object in space.Ato considerBwhich considers CconsidersDthe consideration of
单选题The court considers a financial()to be an appropriate way of punishing him.AoptionBdutyCobligationDpenalty
单选题The author considers office politics to be _____.Aunwelcome at the workplaceBhad for interpersonal relationshipsCan important factor for personal advancementDindispensable to the development of company culture
单选题A session-scoped attribute, product, is stored by a servlet. That servlet then forwards to a JSP page. This attribute holds an instance of the com.Company. Product class with a name property of “The Matrix” and price property of 39.95. Given the JSP page code snippet: What is the response output of this JSP page code snippet? ()A Default costs 0.0B Default costs 49.95C Default costs 39.95D The Matrix costs 0.0E The Matrix costs 49.95F The Matrix costs 39.95
单选题Please refer to page 57 for additional charges.You should turn to page 57Afor more information about the product.Bto find out extra costs.Cto see about the conditions of possible discount.
单选题Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.空白(2)处填()AactivityBworkCcurrencyDtime
问答题Practice 2 Inadequacy of energy resources or more often of the technologies and organizations for harvesting, converting, and distributing those resources has meant insufficient energy benefits and hence inconvenience, deprivation and constraints on growth. The 1970’s, then, represented a turning point. After decades of constancy or decline in monetary costs—and of relegation of environmental and sociopolitical costs to secondary status—energy was seen to be getting costlier in all respects. It began to be probable that excessive energy costs could pose threats on insufficient supply. It also became possible to think that expanding some forms of energy supply could create costs exceeding the benefits.