单选题Which material should NOT be used to secure cargo on deck for a voyage().ASteel chainBWire ropeCSteel strappingDFiber rope

单选题
Which material should NOT be used to secure cargo on deck for a voyage().
A

Steel chain

B

Wire rope

C

Steel strapping

D

Fiber rope


参考解析

解析: 暂无解析

相关考题:

Can we use this material for the decoration of the exhibition hall?A.Yes. Any available material will do for this jobB.Yes. Water-proof material for the decoration of the hall will be used for the interior decorationC.No. Fire-proof materials should be used for the interior decorationD.No. Only highly-cost materials should be used for the interior decoration

Please kindly arrange for shore workers to do ______ during loading the heavy cargo on deck as soon as possible.A.the work of using lines and chains to secure the cargo on boardB.the lash workC.the work of putting dunnage,keeping the cargo in position and not move when the ship is rolling and pitchingD.the lashing work

To "shore up" the main deck for the stowage of deck cargo means to ______.A.weld pad eyes on deck in proper position to secure the cargoB.strengthen the main deck by placing pillars underneath it in the tween-decksC.distribute the weight of the cargo by placing fore-and-aft planks on the main deckD.package the cargo in wooden crates so it will not damage the deck

A "chock" is a ______.A.deck fitting used to secure mooring linesB.casting fitted at the side of a weather deck,used as a fairleadC.sharp block of wood used to support hygroscopic cargoD.smoke pipe for the galley stove

In the stowage of deck cargo,cribbing is ______.A.Placed on deck to support the cargoB.Separation pieces used to keep cylinders upright and steadyC.Shims for stowing baled cargoD.Nets placed across the hatch opening to keep the cargo from falling in the hatch

You are loading a cargo of bagged coffee beans.To keep cargo leakage from being contaminated by the ship's structure,you should ______.A.use separation cloths between the deck and cargoB.place the cargo on a layer of spaced dunnageC.hose down the deck before loading the cargoD.use bag-on-bag stowage

Cargo handlers should take the following precautions with the exception of ______ to avoid damage from shifting.A.Keep the loads as close to the rail or deck as possibleB.If cargo is likely to settle,make provisions to secure it after it has settledC.Thoroughly secure and shore all cargo so that it cannot moveD.hen stowing cargo,avoid leaving empty paces

It is possible,and sometimes necessary,to strengthen the deck of a vessel for carriage of deck cargo by ______.A.placing bunker on the deckB.building a stage on which to place the cargoC.welding steel feet to the deck,on which the cargo is placedD.erecting vertical pillars under the deck to support the cargo

If an electric cargo winch is being used to lift a draft of cargo and the engine room loses all power,which will occur ________.A.A pawl,forced by a spring mechanism,will engage the teeth of the bull gear and hold the loadB.An electromagnetic brake will hold the load where it is suspendedC.The load will fall rapidly to the deck unless the foot brake is engagedD.The load will slowly lower to the deck under control of the drag of the winch motor

Cribbing is ______.A.wooden blocks or dunnage placed between a deck load and the deckB.the chains and shackles used to secure a deck cargoC.a crate in which a deck cargo is packagedD.cardboard separation pieces placed between deck loads to prevent chafing

Get ready for ()the cargo on deck.A、lashing and secureB、lash and securingC、lashing and securingD、lash and secure

The ()(桶装货) should be loaded by cargo net.A、bagged cargoB、drummed cargoC、cased cargoD、deck cargo

单选题Petroleum cargo tanks should not be topped off at deck level when loading on a cold day because().Aa subsequent temperature rise will cause the cargo to overflowBair pockets may cause the cargo to bubble out of the ullage holeCthe increased viscosity of the product requires higher loading pressure which increases the chances of a spillDthe tank valve may be stiff and a spill will occur before the valve can be closed

单选题Cargo handlers should take the following precautions with the exception of()to avoid damage from shifting.AKeep the loads as close to the rail or deck as possibleBIf cargo is likely to settle,make provisions to secure it after it has settledCThoroughly secure and shore all cargo so that it cannot moveDhen stowing cargo,avoid leaving empty paces

单选题It is possible,and sometimes necessary,to strengthen the deck of a vessel for carriage of deck cargo by().Aplacing bunker on the deckBbuilding a stage on which to place the cargoCwelding steel feet to the deck,on which the cargo is placedDerecting vertical pillars under the deck to support the cargo

单选题A chock is a().Adeck fitting used to secure mooring linesBcasting fitted at the side of a weather deck,used as a fairleadCsharp block of wood used to support hygroscopic cargoDsmoke pipe for the galley stove

单选题()is used for lifting cargo.AA mooring winchBA windlassCA deck craneDA lifeboat

单选题()is used for lifting cargo.AA mooring winchBA windlassCA deck craneDA lifeboat engine

单选题In the stowage of deck cargo, cribbing is().Aplaced on deck to support the cargoBseparation pieces used to keep cylinders upright and steadyCshims for stowing balded cargoDnets placed across the hatch opening to keep the cargo from falling in the hatch

单选题To “shore up” the main deck for the stowage of deck cargo means to().Aweld pad eyes on deck in proper position to secure the cargoBstrengthen the main deck by placing pillars underneath it in the tween-decksCdistribute the weight of the cargo by placing fore-and-aft planks on the main deckDpackage the cargo in wooden crates so it will not damage the deck

单选题Which protocol should be used to establish a secure terminal connection to a remote network device? Select the best response.()AARPBSSHCTelnetDWEPESNMPv1FSNMPv2

单选题Separation cloths may be used to().Aabsorb moisture from hygroscopic cargoesBfill gaps between layers of cargoCwrap cargo that leaks from packagingDkeep bagged cargo leakage from contacting the deck

单选题Please kindly arrange for shore workers to do()during loading the heavy cargo on deck as soon as possible.Athe work of using lines and chains to secure the cargo on boardBthe lash workCthe work of putting dunnage,keeping the cargo in position and not move when the ship is rolling and pitchingDthe lashing work

单选题A deck fitting,used to secure line or wire rope,consisting of a single body with two protruding horns is called a().AbittBbollardCcapstanDcleat

单选题Personnel who are moving or handling material aboard ship should NOT follow which of the listed practices?()Asignaling that all personnel are clear before lifting or lowering materialBExamining material for sharp edges or protruding points before handlingCClosing, tagging, or securing valves that permit entrance of steam, water, or air into a fitting or other equipmentDThrowing materials from high places to the deck

单选题A chock().Ais a deck fitting used to shackle gear to the deckBpermits easy jettisoning of deck cargo in an emergencyCprevents stress concentration in the bulwarkDprovides openings through the bulwark for mooring lines

单选题Cribbing is().Awooden blocks or dunnage placed between a deck load and the deckBthe chains and shackles used to secure a deck cargoCa crate in which a deck cargo is packagedDcardboard separation pieces placed between deck loads to prevent chafing