单选题Companycom has seven days of vmstat data on four p5 590 production LPARs of four processors each. The data shows that all four LPARs have periodic utilizations of 90-95% lasting several minutes in duration. However, the average utilizations of the four LPARs were between 15-30%. The vmstat data shows that the peak utilizations of each LPAR do not occur at the same time. Which of the following should be set up?()AA shared pool with four capped LPARsBA shared pool with four uncapped LPARsCFour dedicated LPARs and use DLPAR to manage resources effectivelyDThe server in SMP mode and use WLM to manage resources effectively

单选题
Companycom has seven days of vmstat data on four p5 590 production LPARs of four processors each. The data shows that all four LPARs have periodic utilizations of 90-95% lasting several minutes in duration. However, the average utilizations of the four LPARs were between 15-30%. The vmstat data shows that the peak utilizations of each LPAR do not occur at the same time. Which of the following should be set up?()
A

A shared pool with four capped LPARs

B

A shared pool with four uncapped LPARs

C

Four dedicated LPARs and use DLPAR to manage resources effectively

D

The server in SMP mode and use WLM to manage resources effectively


参考解析

解析: 暂无解析

相关考题:

You can have days with more or fewer than twenty-four hours, and ______ with more or fewer than seven days. A、yearsB、monthsC、seasonsD、weeks

A network design shows that R1 has four different possible paths from itself to the Data Center subnets.Which one of the following commands is most likely to show you all the possible next - hop IP addresses for these four possible routes?()A. show ip eigrp topologyB. show ip eigrp topology all - linksC. show ip route eigrpD. show ip route eigrp all - linksE. show ip eigrp topology all - learned

Companycom has seven days of vmstat data on four p5 590 production LPARs of four processors each. The data shows that all four LPARs have periodic utilizations of 90-95% lasting several minutes in duration. However, the average utilizations of the four LPARs were between 15-30%. The vmstat data shows that the peak utilizations of each LPAR do not occur at the same time. Which of the following should be set up?()A、A shared pool with four capped LPARsB、A shared pool with four uncapped LPARsC、Four dedicated LPARs and use DLPAR to manage resources effectivelyD、The server in SMP mode and use WLM to manage resources effectively

Companycom has a p690 and currently has eight LPARs. They have purchased a p5 590 and wish to migrate their eight LPARs to the new server. The LPARs are running either AIX 5.2 or AIX 5.3 with the current maintenance. What is the LEAST disruptive method for this activity?()A、New install of AIXB、Migrate the 7040-61DC、Utilize alt_disk_installD、Use the enterprise back up strategy

Companycom wants to reduce the number of copper, Ethernet adapters on their 4 way p5 570 running AIX 5.3 used in each of the four LPARs. Companycom has one database LPAR, two application LPARs, and one web LPAR. Only the Web LPAR needs to communicate with the outside world. What is the minimum number of Ethernet adapters that should be provided to ensure redundancy and no single point of failure?()A、One single port Ethernet adapterB、Four dual port Ethernet adaptersC、Two single port Ethernet adaptersD、Eight single port Ethernet adapters

Companycom is implementing a pair of Virtual IO Servers to service four LPARs. If each operating system image requires 15GB of disk space, what is the minimum amount of SCSI resource necessary?()A、Two SCSI paths and two 73GB SCSI disksB、Two SCSI paths and two 36GB SCSI disksC、Four SCSI paths and four 73GB SCSI disksD、Two dual port SCSI RAID adapters with two 73GB SCSI disks

Companycom has a p5 590 that has their production LPAR, their Tivoli Storage Manager (TSM) LPAR, and several other LPARs. What method would provide connectivity between the production LPAR, and the TSM LPAR, but be isolated from the other LPARs in the system without utilizing a Virtual IO Server or physical adapter resources?()A、Use shared memory and semaphores to transfer the data to the TSM LPARB、Provide gigabit Ethernet adapters in each LPAR and run a crossover cableC、Create a Virtual Ethernet between the production server and the TSM LPARsD、Create a Virtual Ethernet between the TSM server LPAR and the non-production LPARs

Companycom has the following: 8 x 1.65GHz CPUs 16GB Memory 4 LPARs LPAR 1: Test/Dev 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 2: QA 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 3: Prod 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 4: Web App 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, SUSE Linux Utilization over a 30 day period LPAR 1: Average utilization was 15%, Peak utilization was 100% LPAR 2: Average utilization was 25%, Peak utilization was 100% LPAR 3: Average utilization was 50%, Peak utilization was 90% LPAR 4: Average utilization was 35%, Peak utilization was 100% If the customer has a requirement for all four LPARs moved to a p5 590 and to have dedicated CPU resources. Which of the following would best describe the profile requirements?()A、LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 2.0 B、LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT on, min CPU 2.0, max CPU 3.0, desired CPU 3.0 C、LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 3.0 LPARs 3 and 4, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 2.0 D、LPARs 1 and 2, SMT off, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT off, min CPU 1.0, max CPU 3.0, desired CPU 3.0

A network design shows that R1 has four different possible paths from itself to the Data Center subnets. Which one of the following commands is most likely to show you all the possible next - hop IP addresses for these four possible routes?()A、show ip eigrp topologyB、show ip eigrp topology all - linksC、show ip route eigrpD、show ip route eigrp all - linksE、show ip eigrp topology all - learned

A customer has defined their server needs as a four-LPAR 16-way p570 with 64GB of memory, four 10/100/1000 TX LAN adapters, and six fibre channel adapters to external storage in an IBM ESS (Shark).  They like the idea of being able to do SAN maintenance while not incurring downtime.  If all LPARs are production related and similar, which question is most appropriate for the pSeries technical specialist to ask?()A、Would 10/100 Ethernets work as well?B、Should there be eight fibre channel adapters?C、Should there be an async adapter for heartbeat?D、Will all LPARs need access to a common fibre channel tape drive?

A customer has an 8-way p5-570 with eight internal disk drives and AIX 5.2.  Which of the following must be added, if anything, to the configuration to support four LPARs, assuming each LPAR requires twodisk drives?()A、7311-D20 drawer with four disksB、Upgrade to AIX 5.3C、Fiber adapters to attach to SAND、Nothing

Companycom has seven days of vmstat data on a p5 590. The server has a total of four test/dev LPARs and 4 production LPARs of one processor each. On the four test/dev LPARs, the data shows 90-95% peak utilizations with a duration of from 5 to 10 minutes. The average utilizations of all LPARs were between 15-30%. All of the applications have different times when they peak.  What is the best configuration to fully utilize the processor resource?()A、Set up the server in SMP mode and use WLM to manage resources effectivelyB、Set up eight dedicated LPARs and use DLPAR to manage resources effectivelyC、Set up a shared pool with eight capped LPARs including production and test/devD、Set up a shared pool with eight uncapped LPARs with priority weight to Production

The pSeries technical specialist is designing a two LPAR p5-570 with eight total processors.  The system is a test system to run AIX 5.2.  The customer has stated a preference for internal disks for the boot devices.  The customer has said they may later need to run three or four LPARs without increasing the number of processors. What should the pSeries technical specialist tell the customer about the ability of the p5-570 to meet their requirements?()A、It will require additional SCSI adapters and I/O drawers or external disks to support more than two LPARs.B、It has sufficient built-in SCSI controllers and disk enclosures to support four total LPARs by only adding the necessary additional disks.C、It is unable to use internal disks for LPARs and therefore additional adapters I/O drawers or external disks must be used to support all LPARs.D、It can support six LPARs with internal disks but will require special features, cables and an adapter to support the additional LPARs with internal disks.

Companycom has just installed a p5 595 with four uncapped LPARs in a shared processor pool. The system and profile settings are still in their default states. One of the LPARs has an application that is consuming all of the available shared processor resources. Users of this application are complaining about response time. Which of the following changes to the slow LPAR would improve response time?()A、Enable SMTB、Reduce the weightC、Renice the processD、Increase the weight

A customer is looking for a reliable well-performing, cost-effective solution to a growing commercial workload.   Initially, they want to run 12 UDB partitions, each of which would need two processors and 8GB of memory.  They are looking at the p655 and want to start with three LPARS on each p655 node using a total of four nodes.   Each LPAR would need at least 4 x 6239 fibre cards and 2 x 5706 2-port 10/100/1000 Ethernet cards.   At a later date, they want to add an additional LPAR to each node to expand to a total of 16 UDB partitions. Which of the following major limitations of this solution should be mentioned to the customer?()A、The p655 supports only two LPARs.B、The p655 supports only four LPARs.C、There are not enough available slots for three LPARs.D、There are not enough available slots for four LPARs.

单选题A customer has defined their server needs as a four-LPAR 16-way p570 with 64GB of memory, four 10/100/1000 TX LAN adapters, and six fibre channel adapters to external storage in an IBM ESS (Shark).  They like the idea of being able to do SAN maintenance while not incurring downtime.  If all LPARs are production related and similar, which question is most appropriate for the pSeries technical specialist to ask?()AWould 10/100 Ethernets work as well?BShould there be eight fibre channel adapters?CShould there be an async adapter for heartbeat?DWill all LPARs need access to a common fibre channel tape drive?

单选题_____AAbout every four minutes.BAbout every five minutes.CAbout every six minutes.DAbout every seven minutes.

单选题Companycom has seven days of vmstat data on a p5 590. The server has a total of four test/dev LPARs and 4 production LPARs of one processor each. On the four test/dev LPARs, the data shows 90-95% peak utilizations with a duration of from 5 to 10 minutes. The average utilizations of all LPARs were between 15-30%. All of the applications have different times when they peak.  What is the best configuration to fully utilize the processor resource?()ASet up the server in SMP mode and use WLM to manage resources effectivelyBSet up eight dedicated LPARs and use DLPAR to manage resources effectivelyCSet up a shared pool with eight capped LPARs including production and test/devDSet up a shared pool with eight uncapped LPARs with priority weight to Production

单选题A customer is looking for a reliable well-performing, cost-effective solution to a growing commercial workload.   Initially, they want to run 12 UDB partitions, each of which would need two processors and 8GB of memory.  They are looking at the p655 and want to start with three LPARS on each p655 node using a total of four nodes.   Each LPAR would need at least 4 x 6239 fibre cards and 2 x 5706 2-port 10/100/1000 Ethernet cards.   At a later date, they want to add an additional LPAR to each node to expand to a total of 16 UDB partitions. Which of the following major limitations of this solution should be mentioned to the customer?()AThe p655 supports only two LPARs.BThe p655 supports only four LPARs.CThere are not enough available slots for three LPARs.DThere are not enough available slots for four LPARs.

单选题They()the flood after a heroic fight lasting five days and four nights.AconqueredBcombatedCwonDwithdrew

单选题A customer has an 8-way p5-570 with eight internal disk drives and AIX 5.2.  Which of the following must be added, if anything, to the configuration to support four LPARs, assuming each LPAR requires twodisk drives?()A7311-D20 drawer with four disksBUpgrade to AIX 5.3CFiber adapters to attach to SANDNothing

单选题Companycom wants to reduce the number of copper, Ethernet adapters on their 4 way p5 570 running AIX 5.3 used in each of the four LPARs. Companycom has one database LPAR, two application LPARs, and one web LPAR. Only the Web LPAR needs to communicate with the outside world. What is the minimum number of Ethernet adapters that should be provided to ensure redundancy and no single point of failure?()AOne single port Ethernet adapterBFour dual port Ethernet adaptersCTwo single port Ethernet adaptersDEight single port Ethernet adapters

单选题Companycom has a p5 590 that has their production LPAR, their Tivoli Storage Manager (TSM) LPAR, and several other LPARs. What method would provide connectivity between the production LPAR, and the TSM LPAR, but be isolated from the other LPARs in the system without utilizing a Virtual IO Server or physical adapter resources?()AUse shared memory and semaphores to transfer the data to the TSM LPARBProvide gigabit Ethernet adapters in each LPAR and run a crossover cableCCreate a Virtual Ethernet between the production server and the TSM LPARsDCreate a Virtual Ethernet between the TSM server LPAR and the non-production LPARs

单选题Companycom has a p690 and currently has eight LPARs. They have purchased a p5 590 and wish to migrate their eight LPARs to the new server. The LPARs are running either AIX 5.2 or AIX 5.3 with the current maintenance. What is the LEAST disruptive method for this activity?()ANew install of AIXBMigrate the 7040-61DCUtilize alt_disk_installDUse the enterprise back up strategy

单选题Companycom has just installed a p5 595 with four uncapped LPARs in a shared processor pool. The system and profile settings are still in their default states. One of the LPARs has an application that is consuming all of the available shared processor resources. Users of this application are complaining about response time. Which of the following changes to the slow LPAR would improve response time?()AEnable SMTBReduce the weightCRenice the processDIncrease the weight

单选题The pSeries technical specialist is designing a two LPAR p5-570 with eight total processors.  The system is a test system to run AIX 5.2.  The customer has stated a preference for internal disks for the boot devices.  The customer has said they may later need to run three or four LPARs without increasing the number of processors. What should the pSeries technical specialist tell the customer about the ability of the p5-570 to meet their requirements?()AIt will require additional SCSI adapters and I/O drawers or external disks to support more than two LPARs.BIt has sufficient built-in SCSI controllers and disk enclosures to support four total LPARs by only adding the necessary additional disks.CIt is unable to use internal disks for LPARs and therefore additional adapters I/O drawers or external disks must be used to support all LPARs.DIt can support six LPARs with internal disks but will require special features, cables and an adapter to support the additional LPARs with internal disks.

单选题A network design shows that R1 has four different possible paths from itself to the Data Center subnets. Which one of the following commands is most likely to show you all the possible next - hop IP addresses for these four possible routes?()Ashow ip eigrp topologyBshow ip eigrp topology all - linksCshow ip route eigrpDshow ip route eigrp all - linksEshow ip eigrp topology all - learned