单选题The pSeries technical specialist is discussing a proposed solution for a commercial application that contains the following options: p670, p690, and p5-570. The customer asks why a p655 was not considered as a solution.  The customer’s requirements include the following:   ? Eight 1.5 or 1.7GHz processors   ? 64GB memory   ? 12 fibre adapters   ? 11 network adapters   ? An estimated 25% growth in the next year   What is the most appropriate response to the customer?()AThe p655 is much more expensive than the other solutions.BThe p655 would be at full capacity and would have no room for the growth.CThe p655 is an HPC system and should never be used in a commercial situation.DThe p655 does not support more than 20 adapters so could not accommodate the requirements.

单选题
The pSeries technical specialist is discussing a proposed solution for a commercial application that contains the following options: p670, p690, and p5-570. The customer asks why a p655 was not considered as a solution.  The customer’s requirements include the following:   ? Eight 1.5 or 1.7GHz processors   ? 64GB memory   ? 12 fibre adapters   ? 11 network adapters   ? An estimated 25% growth in the next year   What is the most appropriate response to the customer?()
A

The p655 is much more expensive than the other solutions.

B

The p655 would be at full capacity and would have no room for the growth.

C

The p655 is an HPC system and should never be used in a commercial situation.

D

The p655 does not support more than 20 adapters so could not accommodate the requirements.


参考解析

解析: 暂无解析

相关考题:

A customer is looking for a low-cost pSeries solution.  The pSeries technical specialist is recommending several p650 Express Configurations.  When reviewing the options with the customer, the pSeries technical specialist should emphasize which of the following limitations?()A、Some Express Configurations limit the amount of maximum memory at order time.B、The customer must meet minimum system requirements to obtain Express Configuration pricing. C、The Express Configurations offer less than the maximum number of processors.D、The Express Configurations are only offered through the QuickShip Program.

The pSeries technical specialist just finished reviewing the system configurations with the customer. The customer requested that many of the availability options,initially configured,be removed due to budgetary constraints.   What should be done next?()A、Remove the availability options,as requested, and place the systems on order.B、Keep the availability options in the configurations and engage the pricer to provide deep discounting on the solution.C、Remove the availability options and review the new configurations with the customer,highlighting the potential exposures.D、Keep the availability options in the configurations, knowing that these options may prevent a critical situation in the future.

A customer is interested in obtaining an AIX solution from IBM.  They have two primary global requirements:   ? Availability (although HACMP is not required)   ? Low cost   Which of the following approaches should the pSeries technical specialist use to meet the customer’s requirements and ensure customer satisfaction?()A、Design the least-cost solution to prevent the competition from winning the business.B、Design a disaster recovery (DR) solution and convince the customer why DR is important to their business.C、Use the HACMP specialist to design the solution and include HA SmoothStart services as part of the proposal.D、Design a solution with redundant parts and explain to the customer the incremental cost associated with the redundancy.

A customer has a large UNIX environment and has engaged a pSeries technical specialist to work on a solution with them.  Which of the following statements would best establish UNIX credibility with a knowledgeable customer?()A、The technical support specialist has completed a UNIX course at college.B、The technical specialist has supported several similar projects and has earned an IBM AIX certification.C、The technical support specialist’s company sells $3M of UNIX computer systems every year.D、The technical support specialist has sold and installed at least a dozen Apple and iSeries systems with POWER processors.

A customer is putting together a high-performance computing cluster of p655 nodes.  They need a total of 48 processors and want to get the best performance possible out of those systems.  They are evaluating four options and have asked the pSeries technical specialist to recommend which one would provide the best performance based on total rPerf.  Their workload may grow over time. Which of the following should the pSeries technical specialist recommend?()A、Twelve 4-way p655 nodes and add more as neededB、Six 8-way p655 nodes and add more as neededC、Six 4-way p655 nodes with four processors CoD on each node in case of growthD、Three 8-way p655 nodes with eight processors CoD on each node in case of growth

A customer needs three 2-way application servers and is evaluating the purchase of three p5-520s versus one partitioned 6-way p5-570.  They like the benefits provided with dynamic processor sparing.  What information should the pSeries technical specialist emphasize to the customer?()A、The p5-570 offers CoD processors.B、The p5-570 requires more rack space than the three p5-520s.C、Redundant power is standard on the p5-570 and is optional on the p5-520.D、Operating system charges will be less expensive with the p5-520 solution.

A customer is ready to order a pSeries solution.  However, the pSeries technical specialist is unsure whether the customer preferred the fibre channel or the external SCSI disk attachment option.  What is the most appropriate action for the specialist to take next?()A、Ask the customer to confirm which option is best for their environment.B、Order the fibre channel option and purchase a converter later if necessary.C、Order both SCSI and fibre channel adapters to cover both potential options.D、Inform the customer that fibre channel was selected for performance reasons.

When designing a single tier AIX database solution for a customer, what other technical specialist would be most instrumental in putting together a total solution and why?()A、xSeries specialist,as the customer may have some Intel-based systems.B、Hardware customer engineer,as they will be installing the entire solution.C、Services specialist,as they can provide education recommendations for the entire solution. D、Storage specialist,as the customer may need disk to store the data and tape to backup the data.

The account team designed a p5-570 solution to strategically position the customer for future IBM announcements.  The customer was dissatisfied upon implementing the solution.  An AIX v5.1 partition was added to the requirements halfway through the solution design process and it was not considered in the final design. What should the pSeries technical specialist have done to prevent this situation?()A、Submitted an RPQ (Request for Quote) for AIX v5.1 support on a p5-570B、Designed a p670 because it supports AIX 5.1 partitionsC、Initially designed a solution supporting AIX 5.1 partitionsD、Gained customer approval for the final design prior to ordering the system

The pSeries technical specialist is discussing a proposed solution for a commercial application that contains the following options: p670, p690, and p5-570. The customer asks why a p655 was not considered as a solution.  The customer’s requirements include the following:   ? Eight 1.5 or 1.7GHz processors   ? 64GB memory   ? 12 fibre adapters   ? 11 network adapters   ? An estimated 25% growth in the next year   What is the most appropriate response to the customer?()A、The p655 is much more expensive than the other solutions.B、The p655 would be at full capacity and would have no room for the growth.C、The p655 is an HPC system and should never be used in a commercial situation.D、The p655 does not support more than 20 adapters so could not accommodate the requirements.

A Sales Specialist receives an email from a customer, requesting information on IBM’s best Server Consolidation solution. How should the Sales Specialist proceed? ()A、Send the customer information on VMwareB、Send the customer information on IBM BladeCenter C、Call the customer to ask why they are consolidatingD、Send the customer information on IBM System P

The pSeries technical specialist is concerned that the installed inventory for a p670 does not match what the customer says is installed.  The specialist discovers that the customer has never updated their VPD.  Which of the following HMC applications is used to gather the current VPD information?()A、Service ProcessorB、Service DirectorC、Inventory Scout ServicesD、Service Focal Point

The sales team has brought in the pSeries technical specialist to recommend the best solution to win the business.   The customer wants the lowest purchase cost four-disk solution using an external I/O solution.  Which of the following offerings provides the required base function at the lowest cost?()A、2104B、ESS800C、FAStT600D、SSA 7133

The account team is putting together a very complex solution for the customer.  During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified.  What should the pSeries technical specialist do to ensure the greatest possible customer satisfaction?()A、Use eConfig to configure and validate each pSeries and p5 system.B、Engage Advanced Technical Support to review any outstanding technical issues.C、Confirm with the customer that the solution design meets their requirements.D、Perform a Pre-Install Solution Assurance Review to validate required power requirements.

单选题When designing a single tier AIX database solution for a customer, what other technical specialist would be most instrumental in putting together a total solution and why?()AxSeries specialist,as the customer may have some Intel-based systems.BHardware customer engineer,as they will be installing the entire solution.CServices specialist,as they can provide education recommendations for the entire solution. DStorage specialist,as the customer may need disk to store the data and tape to backup the data.

单选题The pSeries technical specialist is concerned that the installed inventory for a p670 does not match what the customer says is installed.  The specialist discovers that the customer has never updated their VPD.  Which of the following HMC applications is used to gather the current VPD information?()AService ProcessorBService DirectorCInventory Scout ServicesDService Focal Point

单选题The sales team has brought in the pSeries technical specialist to recommend the best solution to win the business.   The customer wants the lowest purchase cost four-disk solution using an external I/O solution.  Which of the following offerings provides the required base function at the lowest cost?()A2104BESS800CFAStT600DSSA 7133

单选题The pSeries technical specialist just finished reviewing the system configurations with the customer. The customer requested that many of the availability options,initially configured,be removed due to budgetary constraints.   What should be done next?()ARemove the availability options,as requested, and place the systems on order.BKeep the availability options in the configurations and engage the pricer to provide deep discounting on the solution.CRemove the availability options and review the new configurations with the customer,highlighting the potential exposures.DKeep the availability options in the configurations, knowing that these options may prevent a critical situation in the future.

单选题A customer has a large UNIX environment and has engaged a pSeries technical specialist to work on a solution with them.  Which of the following statements would best establish UNIX credibility with a knowledgeable customer?()AThe technical support specialist has completed a UNIX course at college.BThe technical specialist has supported several similar projects and has earned an IBM AIX certification.CThe technical support specialist’s company sells $3M of UNIX computer systems every year.DThe technical support specialist has sold and installed at least a dozen Apple and iSeries systems with POWER processors.

单选题A customer is putting together a high-performance computing cluster of p655 nodes.  They need a total of 48 processors and want to get the best performance possible out of those systems.  They are evaluating four options and have asked the pSeries technical specialist to recommend which one would provide the best performance based on total rPerf.  Their workload may grow over time. Which of the following should the pSeries technical specialist recommend?()ATwelve 4-way p655 nodes and add more as neededBSix 8-way p655 nodes and add more as neededCSix 4-way p655 nodes with four processors CoD on each node in case of growthDThree 8-way p655 nodes with eight processors CoD on each node in case of growth

单选题A customer is ready to order a pSeries solution.  However, the pSeries technical specialist is unsure whether the customer preferred the fibre channel or the external SCSI disk attachment option.  What is the most appropriate action for the specialist to take next?()AAsk the customer to confirm which option is best for their environment.BOrder the fibre channel option and purchase a converter later if necessary.COrder both SCSI and fibre channel adapters to cover both potential options.DInform the customer that fibre channel was selected for performance reasons.

单选题A customer is looking for a low-cost pSeries solution.  The pSeries technical specialist is recommending several p650 Express Configurations.  When reviewing the options with the customer, the pSeries technical specialist should emphasize which of the following limitations?()ASome Express Configurations limit the amount of maximum memory at order time.BThe customer must meet minimum system requirements to obtain Express Configuration pricing. CThe Express Configurations offer less than the maximum number of processors.DThe Express Configurations are only offered through the QuickShip Program.

单选题The account team is putting together a very complex solution for the customer.  During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified.  What should the pSeries technical specialist do to ensure the greatest possible customer satisfaction?()AUse eConfig to configure and validate each pSeries and p5 system.BEngage Advanced Technical Support to review any outstanding technical issues.CConfirm with the customer that the solution design meets their requirements.DPerform a Pre-Install Solution Assurance Review to validate required power requirements.

单选题A Sales Specialist receives an email from a customer, requesting information on IBM’s best Server Consolidation solution. How should the Sales Specialist proceed? ()ASend the customer information on VMwareBSend the customer information on IBM BladeCenter CCall the customer to ask why they are consolidatingDSend the customer information on IBM System P

单选题A customer is interested in obtaining an AIX solution from IBM.  They have two primary global requirements:   ? Availability (although HACMP is not required)   ? Low cost   Which of the following approaches should the pSeries technical specialist use to meet the customer’s requirements and ensure customer satisfaction?()ADesign the least-cost solution to prevent the competition from winning the business.BDesign a disaster recovery (DR) solution and convince the customer why DR is important to their business.CUse the HACMP specialist to design the solution and include HA SmoothStart services as part of the proposal.DDesign a solution with redundant parts and explain to the customer the incremental cost associated with the redundancy.

单选题A customer needs three 2-way application servers and is evaluating the purchase of three p5-520s versus one partitioned 6-way p5-570.  They like the benefits provided with dynamic processor sparing.  What information should the pSeries technical specialist emphasize to the customer?()AThe p5-570 offers CoD processors.BThe p5-570 requires more rack space than the three p5-520s.CRedundant power is standard on the p5-570 and is optional on the p5-520.DOperating system charges will be less expensive with the p5-520 solution.

单选题The account team designed a p5-570 solution to strategically position the customer for future IBM announcements.  The customer was dissatisfied upon implementing the solution.  An AIX v5.1 partition was added to the requirements halfway through the solution design process and it was not considered in the final design. What should the pSeries technical specialist have done to prevent this situation?()ASubmitted an RPQ (Request for Quote) for AIX v5.1 support on a p5-570BDesigned a p670 because it supports AIX 5.1 partitionsCInitially designed a solution supporting AIX 5.1 partitionsDGained customer approval for the final design prior to ordering the system