Opportunity cost 机会成本
Opportunity cost 机会成本
相关考题:
Project trade-offs vary betweenA . risk, cost and schedule.B . direct cost, indirect cost, and resource availabilityC . quality, schedule and timeD . cost, quality and scheduleE . contract terms, scope and budget
When comparing the cost of competing projects, which of the following is typically NOT considered?A.Opportunity costs.B.Direct costs.C.Sunk costs.D.Indirect costs.E.Burden rates.
The Cost Performance Index is computed as:A . budget cost of work performed divided by actual cost of work performedB . budget cost of work performed minus actual cost of work performedC . budget cost of work performed minus budget cost of work scheduledD . budget cost of work scheduled divided by budget cost of work performedE . actual cost of work scheduled divided by budget cost of work performed
Which of the following types of cost are relevant to making financial decisions:A . sunk costB . opportunity costC . material costD . A and C onlyE . B and C only
In which of the following cost estimating techniques are statistics models used:A . nonparametric cost estimatingB . parametric cost estimatingC . life cycle cost estimatingD . bottom-up estimatingE . All of the above.
Cost management includes:A . Cost estimating/forecasting.B . Cost budgeting/cost control.C . Cost applications.D . All of the above.E . A and B only.
98 Cost management includes:A. Cost estimating/forecasting.B. Cost budgeting/cost control.C. Cost applications.D. All of the above.E. A and B only
96 Which of the following types of cost are relevant to making financial decisions:A. sunk costB. opportunity costC. material costD. A and C onlyE. B and C only
114 The Cost Performance Index is computed as:A. budget cost of work performed divided by actual cost of work performedB. budget cost of work performed minus actual cost of work performedC. budget cost of work performed minus budget cost of work scheduledD. budget cost of work scheduled divided by budget cost of work performedE. actual cost of work scheduled divided by budget cost of work performed
You are working on the cost budget for one project. Which of the following is true() A.This process assigns cost estimates to project activities including risks and contingency plans.B.The cost baseline will be used to measure variances and future project performance.C.This process assigns cost estimates for expected future period operating costs.D.The cost baseline is the expected cost for the project.
We shall be happy to have () reciprocating to you on a similar occasion.A、opportunities onB、opportunity ofC、the opportunities ofD、 an opportunity of
The cost performance index(CPI) is the ratio of earned value to () and can be used to estimate the projected cost of completing the project.A.cost varianceB.planned costC.planned costD.actual cost
Much of the effort cost control involves analyzing the relationship between the consumption of project funds and the work being accomplished for such expenditures . The key to effective cost control is the management of the approved ( ) .A.Schedule baselineB.Cost baselineC.Cost outputD.Cost input
The cost performance index(CPI) is the ratio of earned value to ( ) and can be used to estimate the projected cost of completing the project.A.cost variance B.planned cost C.Planned valueD.actual cost
The difference value between Budgeted Cost for Work Performed and Actual Cost for Work Performed is ( ). A.Cost Variance B.Schedule Variance C.EarneD.Value D.Cost PerformeD.Index
The cost performance index(CPI) is the ratio of earned value to ( ) and can be used to estimate the projected cost of completing the project. A. cost variance B.planneD.cost C.PlanneD.value D.actual cost
What is true about the Cisco SBR methodology?()A、provides an opportunity to build short-term consultative relationships with customersB、provides an opportunity to build long-term consultative relationships with customersC、provides an opportunity to build consultative relationships with customersD、provides an opportunity to sell more products
Which two statements about spanning tree path cost are true?()A、The path cost can be changed for an interface using the spanning-tree cost commandB、The path cost can be changed for an interface using the stp path-cost commandC、The SPT default path cost depends on the interface speedD、The STP default path cost is similar for all interface
What is one of the most important ways in which Cisco network integration can provide great opportunity in the healthcare market?()A、 converging voice, video, and data onto one networkB、 using IT services to improve revenueC、 minimizing the total cost of ownershippf the networkD、 updating obsolete infrastructure
You are working on the cost budget for one project. Which of the following is true()A、This process assigns cost estimates to project activities including risks and contingency plans.B、The cost baseline will be used to measure variances and future project performance.C、This process assigns cost estimates for expected future period operating costs.D、The cost baseline is the expected cost for the project.
Generally speaking,logistics can be divided into direct cost and()。A、packing costB、cost of salesC、indirect costD、warehouse cost
Zero stock is the best way for()A、cost controlB、inventory controlC、storage cost controlD、warehouse cost control
多选题Which two statements about spanning tree path cost are true?()AThe path cost can be changed for an interface using the spanning-tree cost commandBThe path cost can be changed for an interface using the stp path-cost commandCThe SPT default path cost depends on the interface speedDThe STP default path cost is similar for all interface
单选题One of the key decision making factors in a very competitive opportunity will be cost. Companycom needs an aggregate rPerf rating of 120. What is the best solution?()ATwo p5 570 16 way 1.9 MHz machinesBOne p5 590 32 way 1.65 MHz machinesCOne p5 595 32 way 1.65 MHz machinesDTwo p5 570 16 way 1.65 MHz machines
单选题What is one of the most important ways in which Cisco network integration can provide great opportunity in the healthcare market?()A converging voice, video, and data onto one networkB using IT services to improve revenueC minimizing the total cost of ownershippf the networkD updating obsolete infrastructure
名词解释题机会成本(opportunity cost)