单选题To ensure quality, what is the maximum end-to-end transit time in milliseconds on a voice network?()A 50B 100C 150D 200E 250

单选题
To ensure quality, what is the maximum end-to-end transit time in milliseconds on a voice network?()
A

 50

B

 100

C

 150

D

 200

E

 250


参考解析

解析: 暂无解析

相关考题:

In the project environment, the individual ultimately responsible for quality control is:A . The line workers who must strive "to do things right the first time" to avoid quality problems.B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.D . The project manager who has ultimate responsibility for the entire project.E . the customer who must ensure that he is receiving a quality product from the vendor.

41 In the project environment, the individual ultimately responsible for quality control is:A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.D. The project manager who has ultimate responsibility for the entire project.E.the customer who must ensure that he is receiving a quality product from the vendor

● (73)is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.(73)A. Quality assurance (QA)B. Quality planningC. Quality control (QC)D. Quality costs

______is the application of planned,systematic quality activities to ensure that the project will employ all processes needed to meet requirements.A.euality assurance(QA)B.Quality planningC.Quality control(QC)D.Quality costs

● ()is the application ion of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.()A. Quality assurance (QA) B. Quality planningC. Quality control (QC) D. Quality costs

In the Junos OS, what handles transit traffic?() A. Transit traffic is handled by the RE onlyB. Transit traffic is handled by the PFE onlyC. Transit traffic is handled by both the RE and the PFED. Transit traffic is not handled by the RE or the PFE

A user reports poor picture quality with a laptop connected to an LCD. Which of the followingshould the technician check FIRST for optimal picture quality?() A. Native resolutionB. Color depthC. Minimum brightnessD. Maximum brightness

When designing a converged network, which measures can be taken at the building access layer to help eliminate latency and ensure end-to-end quality of service can be maintained? () A. rate limit voice trafficB. configure spanning-tree for fast link convergenceC. isolate voice traffic on separate VLANsD. classify and mark traffic close to the source

( ) is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.A.Quality assurance(QA) B.Quality planningC.Quality control(QC)D.Quality costs

()is the application of planned,systematic quality activities to ensure thatthe project will employ all processes needed to meet requirements.A.Quality assurance(QA)B.Quality planningC.Quality control(QC)D.Quality costs

()is the application of planned,systematic.quality activities to ensure that the project will employ all processes to meet requirements.A.Quality assuranceB.Quality planningC.Quality controlD.Quality cost

What is jitter?()A、The total end-to-end delayB、The variations of delay.C、The delay caused by placing the bits on the wire.D、The time it takes for the bits to transit the physical media.

A user reports poor picture quality with a laptop connected to an LCD. Which of the followingshould the technician check FIRST for optimal picture quality?()A、Native resolutionB、Color depthC、Minimum brightnessD、Maximum brightness

The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()A、Evaluate phase exit milestones using sufficiency criteriaB、Flexible entry and exit criteria to minimize schedule delaysC、Quality measures reported only to the project steering committeeD、Many work teams with few members to maximize the number of deliverable hand-offs

In the Junos OS, what handles transit traffic?()A、Transit traffic is handled by the RE onlyB、Transit traffic is handled by the PFE onlyC、Transit traffic is handled by both the RE and the PFED、Transit traffic is not handled by the RE or the PFE

A company is installing IP phones. The phones and office computers connect to the same device. To ensure maximum throughput for the phone data, the company needs to make sure that the phone traffic is on a different network from that of the office computer data traffic. What is the best network device to which to directly connect the phones and computers, and what technology should be implemented on this device? (Choose two.)()A、hubB、routerC、switchD、STPE、subinterfacesF、VLAN

To ensure quality, what is the maximum end-to-end transit time in milliseconds on a voice network?()A、50B、100C、150D、200E、250

What statement about Transit AS is true?()A、Traffic and prefixes originating from Source AS are carried across a Transit AS to reach theirdestination ASB、Traffic and prefixes originating from Transit AS are carried across a Stub AS to their destination ASC、Traffic and prefixes originating from Transit AS are carried across a Stub AS to their Source ASD、None of the above

A company is installing IP phones. The phones and office computers connect to the same devicE.To ensure maximum throughput for the phone data, the company needs to make sure that the phone traffic is on a different network from that of the office computer data traffiC.What is the best network device to which to directly connect the phones and computers, and what technology should be implemented on this device? ()A、hubB、routerC、switchD、STPE、subinterfacesF、VLAN

When designing a converged network, which measures can be taken at the building access layerto help eliminate latency and ensure end-to-end quality of service can be maintained?()A、 rate limit voice trafficB、 configure spanning-tree for fast link convergenceC、 isolate voice traffic on separate VLANsD、 classify and mark traffic close to the source

The "1000" in 1000BaseT cabling represents which of the following?()A、The theoretical maximum cable lengthB、The theoretical maximum bandwidthC、The theoretical port limit of the cableD、The quality level of the copper wiring used

What are the three steps you should take to tune a JDBC Connection pool in WebLogic from the  initial settings in a production environment?()A、Ensure the maximum size is increased to an appropriate setting.B、Set the minimum and maximum size of the connection pool to the same value.C、Increase the statement cache size.D、Add more heap to the JVM.E、Add more nodes to the cluster.

单选题What is jitter?()AThe total end-to-end delayBThe variations of delay.CThe delay caused by placing the bits on the wire.DThe time it takes for the bits to transit the physical media.

单选题The "1000" in 1000BaseT cabling represents which of the following?()AThe theoretical maximum cable lengthBThe theoretical maximum bandwidthCThe theoretical port limit of the cableDThe quality level of the copper wiring used

多选题A company is installing IP phones. The phones and office computers connect to the same device. To ensure maximum throughput for the phone data, the company needs to make sure that the phone traffic is on a different network from that of the office computer data traffic. What is the best network device to which to directly connect the phones and computers, and what technology should be implemented on this device (Choose two.)()。AhubBrouterCswitchDSTPEsubinterfacesFVLAN

多选题A company is installing IP phones. The phones and office computers connect to the same devicE.To ensure maximum throughput for the phone data, the company needs to make sure that the phone traffic is on a different network from that of the office computer data traffiC.What is the best network device to which to directly connect the phones and computers, and what technology should be implemented on this device? ()AhubBrouterCswitchDSTPEsubinterfacesFVLAN

单选题The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()AEvaluate phase exit milestones using sufficiency criteriaBFlexible entry and exit criteria to minimize schedule delaysCQuality measures reported only to the project steering committeeDMany work teams with few members to maximize the number of deliverable hand-offs