Your project is behind schedule due to conflict between team members. Having resolved the conflict,to get the project back on schedule,you should consider ( ) . A.crashing the schedule B.performing resource leveling C.conducting reverse resource allocation scheduling D.utilizing the critical chair resources

Your project is behind schedule due to conflict between team members. Having resolved the conflict,to get the project back on schedule,you should consider ( ) .

A.crashing the schedule
B.performing resource leveling
C.conducting reverse resource allocation scheduling
D.utilizing the critical chair resources

参考解析

解析:由于团队成员之间的冲突,造成了项目进度落后于计划,为了解决冲突以使得项目如期完成你应该考虑。A.重新安排时间表 B.执行资源调配C.进行反向资源分配调度 D.利用关键的主要资源

相关考题:

The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost control, schedule, qualityB.Project objectives, dependencies, plan, cost controlC.Project scope, schedule, staffing, cost controlD.Project scope, quality, schedule, dependenciesE.Project budget, schedule, risk factors, work assignments.

When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.A . Reduce features and/or functionalityB . Increase risk.C . Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)D . All of the above.E . A and B only

The project team form. of organization confers both advantages and disadvantages. Disadvantages of the project form. include:A . Conflict in authority between project manager and functional managersB . Dual allegiance on part of team membersC . Complex prioritization of resourcesD . Loss of developed procedures on project dissolutionE . All of the above

A negative cost variance and positive schedule variance means:A The project is under budget and ahead of scheduleB The project is over budget and behind scheduleC The project is over budget and ahead of scheduleD The project will be overrun but ahead of schedule at completion

11 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.A. Reduce features and/or functionalityB Increase risk.C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)D. All of the above.E. A and B only

131 The project team form. of organization confers both advantages and disadvantages. Disadvantages of the project form. include:A. Conflict in authority between project manager and functional managersB. Dual allegiance on part of team membersC. Complex prioritization of resourcesD. Loss of developed procedures on project dissolutionE. All of the above

96 A negative cost variance and positive schedule variance means:A. The project is under budget and ahead of scheduleB. The project is over budget and behind scheduleC. The project is over budget and ahead of scheduleD. The project will be overrun but ahead of schedule at completion

13 The project team form. of organization confers both advantages and disadvantages. Disadvantages of the project form. include:A. Conflict in authority between project manager and functional managersB. Dual allegiance on part of team members "C. Complex prioritization of resourcesD. Loss of developed procedures on project dissolutionE. All of the above

● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.

The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned

● You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .(74)A.Ahead of scheduleB.Behind scheduleC.On scheduleD.Having not enough information provided

You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week perio.As of today, youve spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .A.Ahead of scheduleB.Behind scheduleC.On scheduleD.Having not enough information provided

● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .(73)A. measure, delay, record, distribute, analyze, and directB. plan, schedule, monitor, control, report, and forecastC. promote, highlight, monitor, control, forecast, and reportD. emphasize, visualize, analyze, conceptualize, report, and record

● Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider __(74)__.(74)A.crashing the scheduleB.performing resource levelingC.conducting reverse resource allocation schedulingD.utilizing the critical chair resources

Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider __(74)__.A.crashing the scheduleB.performing resource levelingC.conducting reverse resource allocation schedulingD.utilizing the critical chair resources

In project time management processes,( )involves identifying and documenting the relationships between project activities.A.activity definitionB.activity sequencingC.schedule controlD.Schedule development

Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( )A.fast trackingB.what-if scenario analysisC.resource levelingD.critical chain method

The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()A.Measure, delay, record, distribute, analyze, and directB.Plan, schedule, monitor, control, report, and forecastC.Promote, highlight, monitor, control, forecast, and reportD.Emphasize, visualize, analyze, conceptualize, report and record

Earned value management(EVM)integrates the scope baseline with the()baseline,along with schedule baseline,to form the performance,which helps the project management team assess and measure project performance and progress.A.qulityB.riskC.changeD.cost

Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().A、crashing the scheduleB、performing resource levelingC、conducting reverse resource allocation schedulingD、utilizing the critical chain resources

The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()A、Data flow modelB、The project critical pathC、Resource loading chartD、WBS (Work Breakdown Structure)

You work as a network Exchange administrator at Company.com.The Company.com network currently consists of a single Active Directory forest containing a single domain named Company.com.The Company.com organization makes use of Microsoft Exchange Server 2010 as their messaging solution.During the course of the day a network user named Mia Hamm reports that certain meetings are missing from her calendar.Company.com requested that you recover the missing calendar items for Mia Hamm whilst ensuring your solution recovers the missing items automatically.What should you do?()A、You should consider having the Set-MailboxCalendarConfiguration cmdlet run.B、You should consider having the schedule set for the Calendar Repair Assistant (CRA).C、You should consider having a Sharing policy created and configured.D、You should consider having the schedule set for the Managed Folder Assistant.

You work as a network exchange administrator at company.com.the company.com network currently consists of a single active directory forest containing a single domain named company.com.the company.com organization makes use of microsoft exchange server 2010 as their messaging solution.thecompany.com organization currently makes use of a computer named -ex01.during the course of the business week you receive instruction from company.com to configure a retention period of 30 days for all deleted message items whilst ensuring that each item which passes the retention period are removed between 3:00 and 5:00 on a daily basis. What should you do?()A、you should consider having the maintenance schedule of king database changed for the retention and removal of message items.B、you should consider having the messaging record management (mrm) schedule for-ex01 changed for the retention and removal of message items.C、you should consider having the set-retention policy cmdlet run to schedule the retention and removal of message items.D、you should consider having the start-managed folder assistant cmdlet run to schedule the retention and removal of message items.

You work as a network Exchange administrator at Company.com.The Company.com network currently consists of a single Active Directory forest containing a single domain named Company.com.The Company.com organization makes use of Microsoft Exchange Server 2010 as their messaging solution.During the course of the business week you receive instruction from Company.com to ensure that all the network users are able to automatically schedule the use of a projector.What should you do?()A、You should consider having the schedule for the Managed Folder Assistant modified.B、You should consider having the properties of the Calendar managed default folder modified.C、You should consider having a new Sharing policy created.D、You should consider having an equipment mailbox created.

单选题You work as a network Exchange administrator at Company.com.The Company.com network currently consists of a single Active Directory forest containing a single domain named Company.com.The Company.com organization makes use of Microsoft Exchange Server 2010 as their messaging solution.During the course of the day a network user named Mia Hamm reports that certain meetings are missing from her calendar.Company.com requested that you recover the missing calendar items for Mia Hamm whilst ensuring your solution recovers the missing items automatically.What should you do?()AYou should consider having the Set-MailboxCalendarConfiguration cmdlet run.BYou should consider having the schedule set for the Calendar Repair Assistant (CRA).CYou should consider having a Sharing policy created and configured.DYou should consider having the schedule set for the Managed Folder Assistant.

单选题You work as a network Exchange administrator at Company.com.The Company.com network currently consists of a single Active Directory forest containing a single domain named Company.com.The Company.com organization makes use of Microsoft Exchange Server 2010 as their messaging solution.During the course of the business week you receive instruction from Company.com to ensure that all the network users are able to automatically schedule the use of a projector.What should you do?()AYou should consider having the schedule for the Managed Folder Assistant modified.BYou should consider having the properties of the Calendar managed default folder modified.CYou should consider having a new Sharing policy created.DYou should consider having an equipment mailbox created.

单选题You work as a network exchange administrator at company.com.the company.com network currently consists of a single active directory forest containing a single domain named company.com.the company.com organization makes use of microsoft exchange server 2010 as their messaging solution.thecompany.com organization currently makes use of a computer named -ex01.during the course of the business week you receive instruction from company.com to configure a retention period of 30 days for all deleted message items whilst ensuring that each item which passes the retention period are removed between 3:00 and 5:00 on a daily basis. What should you do?()Ayou should consider having the maintenance schedule of king database changed for the retention and removal of message items.Byou should consider having the messaging record management (mrm) schedule for-ex01 changed for the retention and removal of message items.Cyou should consider having the set-retention policy cmdlet run to schedule the retention and removal of message items.Dyou should consider having the start-managed folder assistant cmdlet run to schedule the retention and removal of message items.