单选题Which of the following is the most important consideration in locating an alternate computing facility during the development of a disaster recovery plan?在开发灾难恢复计划中,为一个替代的计算机房设施选址时,下列哪一项是最重要考虑?()AIt is close enough to become operational quickly. 足够接近迅速成为运营。BIt is convenient to airports and hotels. 方便到机场和酒店CIt is unlikely to be affected by the same contingency. 不太可能会受到相同的事故影响DIt is close enough to serve its users. 足够接近的用户服务

单选题
Which of the following is the most important consideration in locating an alternate computing facility during the development of a disaster recovery plan?在开发灾难恢复计划中,为一个替代的计算机房设施选址时,下列哪一项是最重要考虑?()
A

It is close enough to become operational quickly. 足够接近迅速成为运营。

B

It is convenient to airports and hotels. 方便到机场和酒店

C

It is unlikely to be affected by the same contingency. 不太可能会受到相同的事故影响

D

It is close enough to serve its users. 足够接近的用户服务


参考解析

解析: 暂无解析

相关考题:

Which of the following is the MOST important step in creating a system classification list?() A. Verifying the OS manufacturersB. Locating a hosting facilityC. Consulting with the system manufacturersD. Interviewing system owners

Which of the following is MOST important to include on the disaster recovery documentation?() A. Emergency exitsB. The test planC. PayrollD. All IT contact numbers

Who should direct short-term recovery actions immediately following a disaster? 谁应当在灾难发生后立即领导短期的灾难恢复行动?()A、Chief Operating Officer. 首席运营官B、Chief Information Officer. 首席信息官C、Chief Executive Officer. 行政总裁CEOD、Disaster Recovery Manager. 灾难恢复经理

Prior to a live disaster test also called a Full Interruption test, which of the following is most important?在现场灾难测试(一个完整的中断测试)之前,下面哪个是最重要的?()A、Conduct of a successful Parallel Test 一个成功的并行测试行为B、Restore all files in preparation for the test. 在准备测试中恢复所有的测试文件C、Document expected findings. 记录预期的结果D、Arrange physical security for the test site. 处理测试场地的物理安全

Operations Security seeks to primarily protect against which of the following? 操作安全的目的主要是防止以下?()A、compromising emanations 损害放射B、facility disaster 设施灾难C、asset threats 资产威胁D、object reuse 对象重用

Contracts and agreements are often times unenforceable or hard to enforce in which of the following alternate facility recovery agreement?在以下哪个备用设施恢复协议中,合同和协议往往不能执行或者难以执行?()A、hot site. 热站B、cold site. 冷站C、reciprocal agreement. 互惠协议D、warm site. 温站

Which of the following is the most important consideration in locating an alternate computing facility during the development of a disaster recovery plan?在开发灾难恢复计划中,为一个替代的计算机房设施选址时,下列哪一项是最重要考虑?()A、It is close enough to become operational quickly. 足够接近迅速成为运营。B、It is convenient to airports and hotels. 方便到机场和酒店C、It is unlikely to be affected by the same contingency. 不太可能会受到相同的事故影响D、It is close enough to serve its users. 足够接近的用户服务

Which of the following is NOT an example of an operational control? 下列哪一项不是一个操作控制的一个例子?()A、Auditing 审计B、operations procedures 操作规程C、backup and recovery 备份和恢复D、contingency planning 应急计划

Which of the following is the MOST important step in creating a system classification list?()A、Verifying the OS manufacturersB、Locating a hosting facilityC、Consulting with the system manufacturersD、Interviewing system owners

Which of the following is the MOST important step in any disaster recovery plan?()A、 Appropriate use of backup media and offsite storageB、 The disaster recovery testing process过程C、 Classifying systems according to operational impactD、 Use appropriate fire suppressant systems

Which of the following is the MOST important consideration when looking at distance requirements when planning a hot site?()A、Avoiding more expensive bandwidth costs for data lines between regionsB、Avoiding a regional disaster that affects both the main site and the hot siteC、Avoiding a second location that has high latency between sitesD、Avoiding a location that is too expensive

Which of the following is MOST important to include on the disaster recovery documentation?()A、 Emergency exitsB、 The test planC、 PayrollD、 All IT contact numbers

Which of the following is the MOST important step in preparing for disaster recovery?()A、 Test the disaster recovery plan processB、 Identify key disaster recovery personnelC、 Ensure that all backup data is kept off-siteD、 Assist management with IT backup policy decisions

A customer has a large amount of data stored on three database servers and is concerned that at present there is no disaster recovery plan in place.  They have an existing tape backup solution that meets their backup window.  In order to analyze potential disaster recovery plans, which of the following questions is the most important?()A、What is the minimum critical backup window?B、Which server is handling the most critical data?C、How much data is stored on each server?D、What is the throughput of the hard drives?

单选题Which of the following is the MOST important consideration when looking at distance requirements when planning a hot site?()AAvoiding more expensive bandwidth costs for data lines between regionsBAvoiding a regional disaster that affects both the main site and the hot siteCAvoiding a second location that has high latency between sitesDAvoiding a location that is too expensive

单选题Which of the following is the MOST important step in any disaster recovery plan?()A Appropriate use of backup media and offsite storageB The disaster recovery testing process过程C Classifying systems according to operational impactD Use appropriate fire suppressant systems

单选题Contracts and agreements are often times unenforceable or hard to enforce in which of the following alternate facility recovery agreement?在以下哪个备用设施恢复协议中,合同和协议往往不能执行或者难以执行?()Ahot site. 热站Bcold site. 冷站Creciprocal agreement. 互惠协议Dwarm site. 温站

单选题Which of the following is NOT an example of an operational control? 下列哪一项不是一个操作控制的一个例子?()AAuditing 审计Boperations procedures 操作规程Cbackup and recovery 备份和恢复Dcontingency planning 应急计划

单选题Which of the following is the MOST important step in creating a system classification list? ()A Verifying the OS manufacturersB Locating a hosting facilityC Consulting with the system manufacturersD Interviewing system owners

单选题A company has just implemented a disaster recovery plan in which critical business must be restored in a four hour window.  Which of the following methods should be used to backup theservers?()AIncremental backupBData only backupsCSAN replicationDFull backup

单选题Which of the following is MOST important to include on the disaster recovery documentation?()A Emergency exitsB The test planC PayrollD All IT contact numbers

单选题A customer is considering a second p690 at a second site for Disaster Recovery purposes.  Which of the following On Demand offerings is most applicable in this environment?()AOn/Off CoDBReserve CoDCPermanent CUoDDCapacity Backup

单选题Which of the following is the MOST important step in preparing for disaster recovery?()A Test the disaster recovery plan processB Identify key disaster recovery personnelC Ensure that all backup data is kept off-siteD Assist management with IT backup policy decisions

单选题Which of the following is the MOST important consideration when purchasing a new server for a mission critical application?()ARAID 0 compliantBNotifying all stakeholders of the server upgradeCService Level AgreementDKVM access

单选题Which of the following is MOST important to include on the disaster recovery documentation?()AEmergency exitsBThe test planCPayrollDAll IT contact numbers

单选题A customer has a large amount of data stored on three database servers and is concerned that at present there is no disaster recovery plan in place.  They have an existing tape backup solution that meets their backup window.  In order to analyze potential disaster recovery plans, which of the following questions is the most important?()AWhat is the minimum critical backup window?BWhich server is handling the most critical data?CHow much data is stored on each server?DWhat is the throughput of the hard drives?

单选题Prior to a live disaster test also called a Full Interruption test, which of the following is most important?在现场灾难测试(一个完整的中断测试)之前,下面哪个是最重要的?()AConduct of a successful Parallel Test 一个成功的并行测试行为BRestore all files in preparation for the test. 在准备测试中恢复所有的测试文件CDocument expected findings. 记录预期的结果DArrange physical security for the test site. 处理测试场地的物理安全