单选题Companycom is installing a p5 590 with a HMC to manage LPARs. The customer is very concerned about security and wants to restrict network traffic that is not necessary. What is necessary for communication between the LPARs and the HMC?()AAn administrative VLAN with port 1808BPort 657 which must remain open to TCP/IP and UDP trafficCNetwork addresses are provided by DHCP services on the networkDDHCP on the HMC is required to be on to communicate between LPAR and HMC

单选题
Companycom is installing a p5 590 with a HMC to manage LPARs. The customer is very concerned about security and wants to restrict network traffic that is not necessary. What is necessary for communication between the LPARs and the HMC?()
A

An administrative VLAN with port 1808

B

Port 657 which must remain open to TCP/IP and UDP traffic

C

Network addresses are provided by DHCP services on the network

D

DHCP on the HMC is required to be on to communicate between LPAR and HMC


参考解析

解析: 暂无解析

相关考题:

For the p5 590 and p5 595 servers, the HMC must be directly attached. Why is the use of a private service network between HMC and the p5 590 required?()A、The Bulk Power Controllers are dependent upon the HMC to provide them with DHCP addresses.B、A firewall is required to isolate the private network from any of the open networks to which the HMC is attached.C、Network communications can be implemented through an open network. No private network is required but it is recommended.D、All p5 590 and 595 servers are shipped with one service processor card. A private network is required to manage DHCP addresses.

Companycom has seven days of vmstat data on four p5 590 production LPARs of four processors each. The data shows that all four LPARs have periodic utilizations of 90-95% lasting several minutes in duration. However, the average utilizations of the four LPARs were between 15-30%. The vmstat data shows that the peak utilizations of each LPAR do not occur at the same time. Which of the following should be set up?()A、A shared pool with four capped LPARsB、A shared pool with four uncapped LPARsC、Four dedicated LPARs and use DLPAR to manage resources effectivelyD、The server in SMP mode and use WLM to manage resources effectively

Companycom is installing a p5 595 with AIX 5.3. The DLPAR option for the resources cannot be selected on the HMC menus. However, the daemons are running on both the HMC and LPARs. Which of the following is a prerequisite for DLPAR functionality?()A、The resources must be unallocated in an LPARB、The microcode on the pSeries must be currentC、All network adapters on the LPAR must be definedD、Network connectivity and name resolution capability between HMC and LPARs

Companycom is installing a p5 590 with a HMC to manage LPARs. The customer is very concerned about security and wants to restrict network traffic that is not necessary. What is necessary for communication between the LPARs and the HMC?()A、An administrative VLAN with port 1808B、Port 657 which must remain open to TCP/IP and UDP trafficC、Network addresses are provided by DHCP services on the networkD、DHCP on the HMC is required to be on to communicate between LPAR and HMC

Companycom recently ordered a p5 570 and an HMC. Prior to delivery, two additional p5 570 servers were added to the order. Upon installation, the system administrator noticed that they do not have a method to connect the p5 570 servers to the HMC. Which of the following will allow them to connect all servers to the HMC?()A、An 8-port adapter to the HMCB、A hub for the private networkC、An additional Ethernet card to the HMCD、An additional Ethernet card for each partition

Companycom is considering a partitioned solution which will require cumulative rPerf total of 150. The original sizing came back recommending a 32-way p5 590. However, they have a requirement for future scalability and availability is important. Which of the following would be the best reason to recommend a p5 595?()A、The p5 595 would allow for CODB、The p5 595 includes the Advanced Power Virtualization hardware and softwareC、The p5 595 is priced the same as the p5 590 given the same number/type of CPUsD、The p5 595 performance would be equivalent to the p5 590 given the same number/type of CPUs

Companycom has seven days of vmstat data on a p5 590. The server has a total of four test/dev LPARs and 4 production LPARs of one processor each. On the four test/dev LPARs, the data shows 90-95% peak utilizations with a duration of from 5 to 10 minutes. The average utilizations of all LPARs were between 15-30%. All of the applications have different times when they peak.  What is the best configuration to fully utilize the processor resource?()A、Set up the server in SMP mode and use WLM to manage resources effectivelyB、Set up eight dedicated LPARs and use DLPAR to manage resources effectivelyC、Set up a shared pool with eight capped LPARs including production and test/devD、Set up a shared pool with eight uncapped LPARs with priority weight to Production

Companycom has several CR3 HMCs managing their p690 servers. They have purchased a new p5 570 and would like to manage the new system with an existing HMC. What is required to support this environment?()A、Free up one HMC and update the software for use with the p5 570B、Connect the new p5 570 server to an existing HMC and manage the p690s and p5 570 from that HMCC、Order a new HMC to support the new p5 570 server since the CR3 HMC is not supported for a p5 570D、Backup the HMC to DVD-RAM and select HMC migrate to move all the profile data to the new HMC software

A system administrator is installing a p5 590 server with an HMC. After pulling the websm client down, it is not possible to connect to the HMC. The HMC can be pinged from the client. Which of the following settings should be verified next?()A、The routes on the HMCB、The firewall setting of the LAN adapterC、The name resolution protocol on the p5 590 serverD、The subnet mask settings on the Ethernet adapters

Companycom currently has three p650 servers in their environment and they are implementing a p5 595. The p650 servers are running in an SMP environment, but are connected to a pair of HMCs. In order to follow best practices in the enterprise server environment and maintain HMC connectivity to the p650s, what else will needs to be ordered in addition to the p5 595?()A、Include a new HMC in the order to connect to the p5 595B、Include a pair of new HMCs in the order to connect to the p5 595C、Include a media set for POWER5 HMC in the order to upgrade one of the existing HMC’s to POWER5 capabilitiesD、Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC to POWER5 capabilities Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC? To POWER5 capabilities

Companycom has a p690 server with unused fiber (HBA) host bus adapters (feature code 6228) that they would like to reuse. They are interested in implementing Advanced Power Virtualization features particularly Virtual IO. What is the best way to proceed?()A、Upgrade the p690 to a p5 590 server running AIX 5.3B、Upgrade the p690 server to AIX 5.3 and implement Advanced Power VirtualizationC、Purchase a p5 590 with minimum resources and simply reuse the p690 unused fiber HBA adaptersD、Purchase a p5 590 that has all the needed resources and adapters for Advanced Power Virtualization

Companycom purchased a p5 570 with no plans to partition. The customer plans to use the ASMI interface to power on and off the machine. How can ASMI be accessed without a HMC?()A、By typing diags and then going to the ASMI menusB、Through SSH from a TCP/IP connection on the serverC、Through WebSM which is connected to a system Ethernet portD、By connecting through a web browser to an HMC Ethernet port

Companycom is purchasing a p5 590 which was configured with 60 Amp line cords. They have just indicated that their large datacenter is already wired for 100 Amp power circuits in the location where the server will be installed. What would be the recommended action?()A、Use the 60 Amp line cordsB、Change the 100 Amp connector to a 60 Amp circuitC、Submit an RPQ to order the p5 590 with 100 Amp power cordsD、Change the configuration and order the p5 590 with the 100 Amp power cords

During the Solution Assurance for a p5 590, Companycom states there is a plan to install OEM Emulex cards in the p5 590. The customer assumes there will be no problem with the plan since IBM resells the Emulex cards. What is the correct response for the customer?()A、The IBM CE will install the cardB、The card will not be supported by IBMC、The AIX device driver should work fineD、The customer is correct, there should be no problem

单选题During the Solution Assurance for a p5 590, Companycom states there is a plan to install OEM Emulex cards in the p5 590. The customer assumes there will be no problem with the plan since IBM resells the Emulex cards. What is the correct response for the customer?()AThe IBM CE will install the cardBThe card will not be supported by IBMCThe AIX device driver should work fineDThe customer is correct, there should be no problem

单选题Companycom is installing a p5 595 with AIX 5.3. The DLPAR option for the resources cannot be selected on the HMC menus. However, the daemons are running on both the HMC and LPARs. Which of the following is a prerequisite for DLPAR functionality?()AThe resources must be unallocated in an LPARBThe microcode on the pSeries must be currentCAll network adapters on the LPAR must be definedDNetwork connectivity and name resolution capability between HMC and LPARs

单选题Companycom is trying to communicate with the service processor of the a new p5 590. However, the customer can not access the service processor. What needs to be done to fix this problem?()AEnable DHCP server on the HMCBConfigure host name and IP address on DNS serverCManually set the IP address of the service processorDConnect a RS-232 cable from the HMC to the service processor

单选题Companycom has a p5 595 running 12 LPARs. They are interested in high bandwidth, secure communication between two of the LPARs within the p5 595 server. They do not have any unused Ethernet adapters. Which of the following recommendations will best meet this requirement?()AUtilize the integrated 10/100/1000 network interfaceBImplement Virtual Ethernet to enable inter-partition communicationCImplement shared Ethernet with the Ethernet adapters utilized in the other LPARsDImplement a Point to Point protocol serial communication between the p5 595 serial ports

单选题Companycom has a p690 and currently has eight LPARs. They have purchased a p5 590 and wish to migrate their eight LPARs to the new server. The LPARs are running either AIX 5.2 or AIX 5.3 with the current maintenance. What is the LEAST disruptive method for this activity?()ANew install of AIXBMigrate the 7040-61DCUtilize alt_disk_installDUse the enterprise back up strategy

单选题For the p5 590 and p5 595 servers, the HMC must be directly attached. Why is the use of a private service network between HMC and the p5 590 required?()AThe Bulk Power Controllers are dependent upon the HMC to provide them with DHCP addresses.BA firewall is required to isolate the private network from any of the open networks to which the HMC is attached.CNetwork communications can be implemented through an open network. No private network is required but it is recommended.DAll p5 590 and 595 servers are shipped with one service processor card. A private network is required to manage DHCP addresses.

单选题Companycom has seven days of vmstat data on four p5 590 production LPARs of four processors each. The data shows that all four LPARs have periodic utilizations of 90-95% lasting several minutes in duration. However, the average utilizations of the four LPARs were between 15-30%. The vmstat data shows that the peak utilizations of each LPAR do not occur at the same time. Which of the following should be set up?()AA shared pool with four capped LPARsBA shared pool with four uncapped LPARsCFour dedicated LPARs and use DLPAR to manage resources effectivelyDThe server in SMP mode and use WLM to manage resources effectively

单选题One of the key decision making factors in a very competitive opportunity will be cost. Companycom needs an aggregate rPerf rating of 120. What is the best solution?()ATwo p5 570 16 way 1.9 MHz machinesBOne p5 590 32 way 1.65 MHz machinesCOne p5 595 32 way 1.65 MHz machinesDTwo p5 570 16 way 1.65 MHz machines

单选题A system administrator is installing a p5 590 server with an HMC. After pulling the websm client down, it is not possible to connect to the HMC. The HMC can be pinged from the client. Which of the following settings should be verified next?()AThe routes on the HMCBThe firewall setting of the LAN adapterCThe name resolution protocol on the p5 590 serverDThe subnet mask settings on the Ethernet adapters

单选题Companycom recently ordered a p5 570 and an HMC. Prior to delivery, two additional p5 570 servers were added to the order. Upon installation, the system administrator noticed that they do not have a method to connect the p5 570 servers to the HMC. Which of the following will allow them to connect all servers to the HMC?()AAn 8-port adapter to the HMCBA hub for the private networkCAn additional Ethernet card to the HMCDAn additional Ethernet card for each partition

单选题Companycom purchased a p5 570 with no plans to partition. The customer plans to use the ASMI interface to power on and off the machine. How can ASMI be accessed without a HMC?()ABy typing diags and then going to the ASMI menusBThrough SSH from a TCP/IP connection on the serverCThrough WebSM which is connected to a system Ethernet portDBy connecting through a web browser to an HMC Ethernet port

单选题Companycom wants to reduce the number of copper, Ethernet adapters on their 4 way p5 570 running AIX 5.3 used in each of the four LPARs. Companycom has one database LPAR, two application LPARs, and one web LPAR. Only the Web LPAR needs to communicate with the outside world. What is the minimum number of Ethernet adapters that should be provided to ensure redundancy and no single point of failure?()AOne single port Ethernet adapterBFour dual port Ethernet adaptersCTwo single port Ethernet adaptersDEight single port Ethernet adapters

单选题Companycom has a p5 590 that has their production LPAR, their Tivoli Storage Manager (TSM) LPAR, and several other LPARs. What method would provide connectivity between the production LPAR, and the TSM LPAR, but be isolated from the other LPARs in the system without utilizing a Virtual IO Server or physical adapter resources?()AUse shared memory and semaphores to transfer the data to the TSM LPARBProvide gigabit Ethernet adapters in each LPAR and run a crossover cableCCreate a Virtual Ethernet between the production server and the TSM LPARsDCreate a Virtual Ethernet between the TSM server LPAR and the non-production LPARs

单选题Companycom has a 16 way 1.65 GHz p5 590 and wants to install a i5/OS partition on their server. The customer wants to keep installation costs to a minimum by sharing devices between all LPARs. Before the operating system can be installed in this partition, the customer was told that there are certain limitations that must be observed. What are these limitations?()AWhen the i5/OS partition is housed in the p5 590, the HMC allows seamless installation in a partition as long as the minimum one processor, 256 MB of memory, one Ethernet and one boot adapter/disk is available from internal hardware. BV5R3 and later releases of i5/OS can be installed on a POWER5 server partition. Only one processor can be assigned to the i5/OS. A special expansion tower must be ordered. This expansion tower and its devices can be shared with other OS partitions. CWhen the i5/OS partition is housed in the p5 590, the 5250 Twinaxial console must be used to set up the partition. Only one processor can be assigned to the i5/OS partition. A special expansion tower must be ordered to house the IOPs. Devices in the special expansion tower can be shared with other Linux partitions.  DV5R3 and later releases of i5/OS can be installed on IBM eServer p5 servers. i5/OS can run on two processors in the p5 590. A special expansion tower must be ordered. This expansion tower and its devices cannot be shared with other OS partitions. The iSeries expansion towers are seen by the IBM eServer p5 server as an I/O subsystem.