项目促进员和项目协调员的区别在于项目促进员:( )A.可以做更多的决策B.向高层管理汇报C.不能决策D.有一定的权利
项目促进员和项目协调员的区别在于项目促进员:( )
A.可以做更多的决策
B.向高层管理汇报
C.不能决策
D.有一定的权利
相关考题:
140 The three most common types of project cost estimates are:A. Order of magnitude, parametric, and budget.B. Parametric, definitive and top down.C. Order of magnitude, definitive and bottom up.D. Order of magnitude, budget and definitive.E. Analogy, parametric and top down
190 Final risk quantification considers total risk impacts and _____ .A. translates the impacts into economic terms for analysis.B. concentrates on schedule impactsC. may not consider safety and environmental impactsD. A and BE. A and C
61 For communication to occur, there must be:A. Two or more people involvedB. the transmittal of informationC. a communication processD. All of the aboveE. B and C only
141 By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:A. Significantly reduce project risksB. eliminate project risksC. provide a rational basis for better decision makingD. identify risks, their impact(s), and any appropriate responsesE. None of the above
● Assume that you have a network where an activity on the critical path can be crashed by two weeks. If the activity is actually crashed by two weeks, then:A The project's schedule will be reduced by 2 weeks.B The available slack on the noncritical paths will increase.C A new critical path may appear after the crash.D All of the above.E A and B only.
对项目进行总结后你发现按进度计划要花28000小时,已经挣得25000小时,支付26000小时,正确结论应该是:A、 项目的成本效率非常有利B、 我们需要趋势分析报告C、 项目滞后于进度计划D、 项目超前于进度计划