● Object-oriented analysis (OOA) is a semiformal specification technique for the object-oriented paradigm. Object-oriented analysis consists of three steps. The first step is (71). It determines how the various results are computed by the product and presents this information in the form. of a (72) and associated scenarios. The second is (73) , which determines the classes and their attributes. Then determine the interrelationships and interaction among the classes. The last step is (74) , which determines the actions performed by or to each class or subclass and presents this information in the form. of (75) .(71)A.use-case modelingB. class modelingC. dynamic modelingD. behavioral modeling(72)A. collaboration diagramB. sequence diagramC. use-case diagramD. activity diagram(73)A. use-case modelingB. class modelingC. dynamic modelingD. behavioral modeling(74)A.use-case modelingB. class modelingC. dynamic modelingD. behavioral modeling(75)A. activity diagramB. component diagramC. sequence diagramD. state diagram

● Object-oriented analysis (OOA) is a semiformal specification technique for the object-oriented paradigm. Object-oriented analysis consists of three steps. The first step is (71). It determines how the various results are computed by the product and presents this information in the form. of a (72) and associated scenarios. The second is (73) , which determines the classes and their attributes. Then determine the interrelationships and interaction among the classes. The last step is (74) , which determines the actions performed by or to each class or subclass and presents this information in the form. of (75) .

(71)

A.use-case modeling

B. class modeling

C. dynamic modeling

D. behavioral modeling

(72)

A. collaboration diagram

B. sequence diagram

C. use-case diagram

D. activity diagram

(73)

A. use-case modeling

B. class modeling

C. dynamic modeling

D. behavioral modeling

(74)

A.use-case modeling

B. class modeling

C. dynamic modeling

D. behavioral modeling

(75)

A. activity diagram

B. component diagram

C. sequence diagram

D. state diagram


相关考题:

In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:A Work breakdown structureB milestone review and schedule techniqueC cost/schedule control systemD planning programming budget systemE program and evaluation review technique

Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource. A.PERTB.ResourcelevelingC.SchedulecompressionD.Critical chain method

(71) analysis emphasizes the drawing of pictorial system models to document and validate both existing and/or proposed systems. Ultimately, the system models become the (72)fordesigning and constructing an improved system. (73)is such a technique. The emphasis in this technique is process-centered. Systems analysts draw a series of processmodels called(74). (75)is another such technique that integrates data and processconcerns into constructs called objects.(71)A. PrototypingB. AcceleratedC. Model-drivenD. Iterative(72)A.imageB. pictureC. layoutD. blueprint(73)A. Structured analysisB. Information EngineeringC. Discovery PrototypingD. Object-Oriented analysis(74)A.PERTB. DFDC. ERDD. UML(75)A. Structured analysisB. Information EngineeringC. Discovery PrototypingD. Object-Oriented analysis

Object-oriented analysis(OOA)is a semiformal specification technique for the object-oriented paradigm. Object-oriented analysis consists of three steps. The first step is(71). It determines how the various results are computed by the product and presents this information in the form. of a(72)and associated scenarios. The second is(73), which determines the classes and their attributes. Then determine the interrelationships and interaction among the classes. The last step is(74), which determines the actions performed by or to each class or subclass and presents this information in the form. of(75).A.use-case modelingB.class modelingC.dynamic modelingD.behavioral modeling

● Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.(72)A.PERTB.Resource levellingC.Schedule compressionD.Critical chain method

System analysis is traditionally done top-down using structured analysis based on( ). Object-oriented analysis focuses on creation of models. The three types of theanalysis model are( ). There are two substages of object-oriented analysis.( )focuses on real-world things whose semantics the application captures. The object constructedin the requirement analysis shows the( )of the real-world system and organizes it intoworkable pieces.( )addresses the computer aspects of the application that are visible tousers. The objects are those which can be expected to vary from time to time quite rapidly.A.functional decomposition B.object abstraction C.data inheritance D.information generalization A.function model,class model and state model B.class model,interaction model and state model C.class model,interaction model and sequence model D.function model,interaction model and state model A.Static analysis B.Semantic analysis C.Scope analysis D.Domain analysis A.static structure B.system components C.data flows D.program procedures A.Program analysis B.Function requirement C.Application analysis D.Physical model

试题(71)~(75)Object-oriented analysis (OOA) is a semiformal specification technique for the object-oriented paradigm. Object-oriented analysis consists of three steps. The first step is (71). It determines how the various results are computed by the product and presents this information in the form. of a (72) and associated scenarios. The second is (73) , which determines the classes and their attributes. Then determine the interrelationships and interaction among the classes. The last step is (74) , which determines the actions performed by or to each class or subclass and presents this information in the form. of (75) .(71)A. use-case modelingB. class modelingC. dynamic modelingD. behavioral modeling(72)A. collaboration diagramB. sequence diagramC. use-case diagramD. activity diagram(73)A. use-case modelingB. class modelingC. dynamic modelingD. behavioral modeling(74)A. use-case modelingB. class modelingC. dynamic modelingD. behavioral modeling(75)A. activity diagramB. component diagramC. sequence diagramD. state diagram

● System analysis is traditionally done top-down using structured analysis based on (71). Object-oriented analysis focuses on creation of models. The three types of theanalysis model are (72). There are two substages of object-oriented analysis. (73) focuses on real-world things whose semantics the application captures. The object constructedin the requirement analysis shows the (74) of the real-world system and organizes it intoworkable pieces.(75)addresses the computer aspects of the application that are visible tousers. The objects are those which can be expected to vary from time to time quite rapidly.(71)A. functional decompositionB. object abstractionC. data inheritanceD. information generalization(72)A. function model,class model and state modelB. class model,interaction model and state modelC. class model,interaction model and sequence modelD. function model,interaction model and state model(73)A. Static analysisB. Semantic analysisC. Scope analysisD. Domain analysis(74)A. static structureB. system componentsC. data flowsD. program procedures(75)A. Program analysisB. Function requirementC. Application analysisD. Physical model

Traditional structured analysis techniques focus upon the flow of(1)within a system. Object-oriented analysis emphasizes the building of real-world models, It examines requirements from the perspective of the classes and objects found in the vocabulary of the(2)domain.Traditional system design method emphasizes the proper and effective structure of a complex system. Object-oriented design method encompasses the process of object- oriented decomposition and a(3)for depicting both logical and physical as well as static and dynamic models of the system under design.Object-oriented programming is a method of implementation in which programs are organized as cooperative collections of objects, each of which represents an(4)of some class, and whose classes are all members of a hierarchy of classes united via(5)relationships.A.controlB.programC.dataD.reference

analysis emphasizes the drawing of pictorial system models to document and validate both existing and/or proposed systems. Ultimately, the system models become the(72)for designing and constructing an improved system.(73)is such a technique. The emphasis in this technique is process-centered. Systems analysts draw a series of process models called(74).(75)is another such technique that integrates data and process concerns into constructs called objects.A.PrototypingB.AcceleratedC.Model-drivenD.Iterative

OOA(Object-Oriented Analysis)模型由5个层次和5个活动组成,5个层次不包括(51),5个活动不包括(52)。OOA在定义属性的同时,还要识别实例连接。实例连接是一个实例对象与另一个实例对象的(53)关系。A.主题层B.对象类层C.动态层D.结构层

A variety of tools is available to help the analyst to discover the users true needs. These tools are grouped into three broad techniques that are based on the degree of change anticipated in the to-be system - Business process( )is used when the basic business Requirements outlined in the system request focus on employing computer technology in some aspect of the business process. Two popular activities used in the technique are( ). Business process( )means that the basic business requirements target moderate changes to the organization s operations. ( )are three popular activities in the technique. Business process( )means changing the current way of doing business and making major changes to take advantage of new ideas and new technology.A.automation B.modeling C.improvement D.reengineering A.duration analysis and outcome analysis B.problem analysis and root cause analysis C.technology analysis and activity elimination D.activity-based costing and informal benchmarking A.automation B.modeling C.improvement D.reengineering A.Duration analysis, activity-based costing and informal benchmarking B.Outcome analysis, technology analysis and activity elimination C.Problem analysis, root cause analysis and critical path analysis D.Cost-benefit analysis, schedule analysis and risk analysis A.automation B.modeling C.improvement D.reengineering

??Many useful tools and techniques are used in developing schedule.( 73) is a schedulenetwork analysis technique that modifies the project schedule to account for limited resource??A.PERTB. Resource levellingC.Schedule compressionD.Critical chain method

System analysis is traditionally done top-down using structured analysis based on (71) .Object-oriented analysis focuses on creation of models.The three types of the analysis model are (72) .There are two substages of object-oriented analysis. (73) focuses on real-world things whose semantics the application captures.The object constructed in the requirement analysis shows the (74) of the real-world system and organizes it into workable pieces. (75) addresses the computer aspects ofthe application that are visible to users.The objects are those which can be expected to vary from time to time quite rapidly.(71)A.functional decompositionB.object abstractionC.data inheritanceD.information generalization

Object-oriented analysis(OOA.is a semiformal specification technique for the object-oriented paradigm.Object-oriented analysis consists of three steps.The first step is( ).It determines how the various results are computed by the product and presents this information in the form of a( )and associated scenarios.The second is(请作答此空),which determines the classes and their attributes.Then determine the interrelationships and interaction among the classes.The last step is( ),which determines the actions performed by or to each class or subclass and presents this information in the form of( ).A.use-case modelingB.class modelingC.dynamic modelingD.behavioral modeling

System analysis is traditionally done top-down using structured analysis based on( ).Object-oriented analysis focuses on creation of models.The three types of theanalysis model are( ).There are two substages of object-oriented analysis.( )focuses on real-world things whose semantics the application captures.The object constructedin the requirement analysis shows the(请作答此空)of the real-world system and organizes it intoworkable pieces.( )addresses the computer aspects of the application that are visible tousers.The objects are those which can be expected to vary from time to time quite rapidly.A.static structureB.system componentsC.data flowsD.program procedures

System analysis is traditionally done top-down using structured analysis based on( ).Object-oriented analysis focuses on creation of models.The three types of theanalysis model are( ).There are two substages of object-oriented analysis.(请作答此空)focuses on real-world things whose semantics the application captures.The object constructedin the requirement analysis shows the( )of the real-world system and organizes it intoworkable pieces.( )addresses the computer aspects of the application that are visible tousers.The objects are those which can be expected to vary from time to time quite rapidly.A.Static analysisB.Semantic analysisC.Scope analysisD.Domain analysis

( )analysis emphasizes the drawing of pictorial system models to document and validate both existing and/or proposed systems.Ultimately,the system models become the( )for designing and constructing an improved system.( )is such a technique.The emphasis in this technique is process-centered.Systems analysts draw a series of process models called( )、(请作答此空)is another such technique that integrates data and process concerns into constructs called objects.A.Structured analysisB.Information EngineeringC.Discovery PrototypingD.Object-Oriented analysis

Object-oriented analysis(OOA.is a semiformal specification technique for the object-oriented paradigm.Object-oriented analysis consists of three steps.The first step is( ).It determines how the various results are computed by the product and presents this information in the form of a( )and associated scenarios.The second is( ),which determines the classes and their attributes.Then determine the interrelationships and interaction among the classes.The last step is( ),which determines the actions performed by or to each class or subclass and presents this information in the form of(请作答此空).A.activity diagramB.component diagramC.sequence diagramD.state diagram

System analysis is traditionally done top-down using structured analysis based on( ).Object-oriented analysis focuses on creation of models.The three types of theanalysis model are(请作答此空).There are two substages of object-oriented analysis.( )focuses on real-world things whose semantics the application captures.The object constructedin the requirement analysis shows the( )of the real-world system and organizes it intoworkable pieces.( )addresses the computer aspects of the application that are visible tousers.The objects are those which can be expected to vary from time to time quite rapidly.A.function model,class model and state modelB.class model,interaction model and state modelC.class model,interaction model and sequence modelD.function model,interaction model and state model

System analysis is traditionally done top-down using structured analysis based on____.Object-oriented analysis focuses on creation of models.The three types of the analysis model are____.There are two substages of object-oriented analysis.____focuses on real-world things whose semantics the application captures.The object constructed in the requirement analysis shows the__请作答该选项__of the real-world system and organizes it into workable pieces.____addresses the computer aspects of the application that are visible to users.The objects are those which can be expected to vary from time to time quite rapidly.A.static structureB.system componentsC.data flowsD.program procedures

System analysis is traditionally done top-down using structured analysis based on____.Object-oriented analysis focuses on creation of models.The three types of the analysis model are___.There are two substages of object-oriented analysis.__请作答次选项__focuses on real-world things whose semantics the application captures.The object constructed in the requirement analysis shows the____of the real-world system and organizes it into workable pieces.____addresses the computer aspects of the application that are visible to users.The objects are those which can be expected to vary from time to time quite rapidly.A.Static analysisB.Semantic analysisC.Scope analysisD.Domain analysis

System analysis is traditionally done top-down using structured analysis based on____.Object-oriented analysis focuses on creation of models.The three types of the analysis model are__请作答此选项__.There are two substages of object-oriented analysis.____focuses on real-world things whose semantics the application captures.The object constructed in the requirement analysis shows the____of the real-world system and organizes it into workable pieces.____addresses the computer aspects of the application that are visible to users.The objects are those which can be expected to vary from time to time quite rapidly.A.function model,class model and state modelB.class model,interaction model and state modelC.class model,interaction model and sequence modelD.function model,interaction model and state model

A variety of tools is available to help the analyst to discover the users' true needs.These tools are grouped into three broad techniques that are based on the degree of change anticipated in the to-be system . Business process(71) is used when the basic business Requirements outlined in the system request focus on employing computer technology in some aspect of the business process. Two popular activities used in the technique are(72). Business process(73)means that the basic business requirements target moderate changes to the organization' s operations.(74)are three popular activities in the technique. Business process (75)means changing the current way of doing business and making major changes to take advantage of new ideas and new technology.A. Duration analysis,activity-baseD.costing anD.informal bench markingB.Outcome analysis, technology analysis anD.activity eliminationC.Problem analysis, root cause analysis anD.critical path analysisD.Cost-benefit analysis, schedule analysis anD.risk analysis

Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERTB.Resource levellingC.Schedule compressionD.Critical chain methoD.

System analysis is traditionally done top-down using structured analysis based on( ). Object-oriented analysis focuses on creation of models. The three types of theanalysis model are( ). There are two substages of object-oriented analysis.( ) focuses on real-world things whose semantics the application captures. The object constructedin the requirement analysis shows the( )of the real-world system and organizes it intoworkable pieces.(请作答此空)addresses the computer aspects of the application that are visible tousers. The objects are those which can be expected to vary from time to time quite rapidly. A. Program analysisB. Function requirementC. Application analysisD. Physical model

Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.A、PERTB、ResourcelevelingC、SchedulecompressionD、Critical chain method

Which of the following techniques is used for tracking the project risks?()A、Probability-Impact matrixB、Pareto chartC、R-ChartD、PERT (Program Evaluation and Review Technique) analysis