21 The "buy or make" decision is usually made during the:A. acquisition cycleB. contract evaluation cycleC. requirements cycleD. pre-award cycleE. at any time that is convenient for the project manager
21 The "buy or make" decision is usually made during the:
A. acquisition cycle
B. contract evaluation cycle
C. requirements cycle
D. pre-award cycle
E. at any time that is convenient for the project manager
相关考题:
下列摩托罗拉Handover参数中,哪些是接收质量切换门限参数() A.decision_1_n5B.decision_1_p5C.decision_1_n6D.decision_1_p6E.decision_1_n7F.decision_1_p7
2、()在西门子802D系统中指的是轮廓铣削循环。A.CYCLE72B.CYCLE73C.CYCLE95D.CYCLE81