5 _____ is a narrative description of the work to be accomplished or resource to be supplied. A. Purchase orderB. Level of effort workC. Scope of workD. Contract stipulationE. None of the above
5 _____ is a narrative description of the work to be accomplished or resource to be supplied. A. Purchase order
B. Level of effort work
C. Scope of work
D. Contract stipulation
E. None of the above
相关考题:
Going from Level to Level in the work breakdown structure will result inA.Less estimating accuracyB.Better control of the projectC.Lower status reporting costsD.A greater likelihood that something will fall through the cracksE.None of the above
A legally binding document offered unilaterally is a _____ .A purchase orderB scope of work descriptionC contract stipulationD level of effort proposalE request for proposal
_____ is a formal invitation containing a scope of work which seeks a formal response (proposal) describing both methodology and compensation to form. the basis of a contract.A Request for proposalB Invitation to bidC Request for quotationD Intention for bidE None of the above.
_____ is a method of procurement where a contract results from a bid which may be changed through bargaining.A AcquisitionB Contract negotiationC ProcurementD Purchase negotiationE None of the above.
_____ is a narrative description of the work to be accomplished or resource to be supplied.A Purchase orderB Level of effort workC Scope of workD Contract stipulationE None of the above.
By which process may an unsuccessful supplier seek remedy for unjust awards?A Contract disputeB Stop work orderC Bid protestD Coffective actionE None of the above.
In which of the following contract types is it easier to change the scope of the contract:A firm fixed priceB fixed price plus incentive feeC cost plus percentage of costD letter contractE None of the above.
172 Smoothing out resource requirements from period to period is called resource _____.A. Allocation.B. PartitioningC. Leveling.D. QuantificationE. None of above
33 In which of the following contract types is it easier to change the scope of the contract:A. firm fixed priceB. fixed price plus incentive feeC. cost plus percentage of costD. letter contractE. None of the above
75 By which process may an unsuccessful supplier seek remedy for unjust awards?A. Contract disputeB. Stop work orderC. Bid protestD. Coffective actionE. None of the above
123 _____ is a narrative description of the work to be accomplished or resource to be supplied.A. Purchase orderB. Level of effort workC. Scope of workD. Contract stipulationE. None of the above
131 _____ is a method of procurement where a contract results from a bid which may be changed through bargaining.A. AcquisitionB. Contract negotiationC. ProcurementD. Purchase negotiationE. None of the above
138 _____ is a formal invitation containing a scope of work which seeks a formal response (proposal) describing both methodology and compensation to form. the basis of a contract.A. Request for proposalB. Invitation to bidC. Request for quotationD. Intention for bidE. None of the above
149 Scope Management:A. entails managing the project's work content.B. is a subset of configuration management and as such is performed by CM specialists.C. is concerned with naming all activities performed, the end products which results and the resources consumed.D. is not a concern of the project manager.E. None of the above
13 A legally binding document offered unilaterally is a _____ .A. purchase orderB scope of work descriptionC. contract stipulationD. level of effort proposalE. request for proposal
51 Going from Level 2 to Level 4 in the work breakdown structure will result inA. Less estimating accuracyB. Better control of the projectC. Lower status reporting costsD. A greater likelihood that something will fall through the cracksE. None of the above
86 The contractual statement of work (CSOW)A. Must be the same as the proposal statement of workB. Does not identify reporting requirementsC. Can be at a different level of detail (i.e. WBS level) than the proposal statement of workD. Identifies the contractor's organizational structure for the projectE. All of the above
95 A legally binding document offered unilaterally is a _____ .A. purchase orderB. scope of work descriptionC. contract stipulationD. level of effort proposalE. request for proposal
115 In which of the following contract types is it easier to change the scope of the contract:A. firm fixed priceB. fixed price plus incentive feeC. cost plus percentage of costD. letter contractE. None of the above.
● Going from Level 2 to Level 4 in the work breakdown structure will result inA Less estimating accuracyB Better control of the projectC Lower status reporting costsD A greater likelihood that something will fall through the cracksE None of the above
It's high time you _____.A. start to workB. would start to workC. started to workD. had started to work
The writer of the passage thinks that ______.A. it is true to say artists fail in their workB. it is untrue to say artists fail in their workC. it is true to say some artists fail in their workD. it is true to say only painters fail in their work
Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.(74)A. milestoneB. baselineC. qualityD. work
Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.A、milestoneB、baselineC、qualityD、work
The SOW (Statement of Work) is another name for the:()A、WBS (Work Breakdown Structure).B、cost benefit analysis.C、requirements specifications.D、narrative description of the work to be accomplished.
单选题The SOW (Statement of Work) is another name for the:()AWBS (Work Breakdown Structure).Bcost benefit analysis.Crequirements specifications.Dnarrative description of the work to be accomplished.