30 Network schedules are prepared during the _____ phase and updated during the _____ phase. A. Conceptual, execution.B. Development, implementation.C. Development, close-out.D. Implementation, close-out.E. Planning, finishing
30 Network schedules are prepared during the _____ phase and updated during the _____ phase. A. Conceptual, execution.
B. Development, implementation.
C. Development, close-out.
D. Implementation, close-out.
E. Planning, finishing