103 The "buy or make" decision is usually made during the:A. acquisition cycleB. contract evaluation cycleC. requirements cycleD. pre-award cycleE. at any time that is convenient for the project manager
103 The "buy or make" decision is usually made during the:
A. acquisition cycle
B. contract evaluation cycle
C. requirements cycle
D. pre-award cycle
E. at any time that is convenient for the project manager