177 Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?A. 5%B. 10%C. 15%D. 25%E. 50%
177 Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?
A. 5%
B. 10%
C. 15%
D. 25%
E. 50%
相关考题:
Which of the following are included in the Acquisition phase(s) of the project life cycle.A . concept and developmentB . development and planningC . execution and phase-outD . planning and implementationE . concept and planning
The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.A.ConceptualB.Development.C.ExecutionD.FinishE.All of the above.
QUEST . Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?A . 5%B . 10%C . 15%D . 25%E . 50%
Typically, during which phase in a project life cycle are most of the project expenses incurred.A . Concept phaseB . Development of design phaseC . Execution phase.D . Termination phase.E . None of the above
It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?A . Direct labor dollarsB . Direct labor hours.C . Overhead rates.D . Procurement costs.E . None of the above.
During which phase of the project life cycle is the amount at stake lowest?A conceptB developmentC executionD conclusionE C and D
Which phase of the project life cycle typically has the highest uncertainty and risk associated with it?A conceptB developmentC executionD conclusionE All of the above.
19 It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?A. Direct labor dollarsB. Direct labor hours.C. Overhead rates.D. Procurement costs.E. None of the above
67 The project stakeholders should be actively involved with the _____ phase(s) of the life cycle. A. ConceptualB. Development.C. ExecutionD. FinishE. All of the above
70 Which phase of the project life cycle typically has the highest uncertainty and risk associated with it? A. conceptB. developmentC. executionD. conclusionE. All of the above
95 Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?A. 5%B. 10%C. 15%D. 25%E. 50%
194 During which phase of the project life cycle is the amount at stake lowest?A. conceptB. developmentC. executionD. conclusionE. C and D
6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phaseB Development of design phaseC. Execution phase.D. Termination phase.E. None of the above
185 Life Cycle Costing:A. is the concept of including all costs within the total life of a project.B. is an activity devoted to optimizing cost/performanceC. is an activity of appraising the cost and technical performance of a completed project.D. is a process of predicting the life of a project.E. None of the above
88 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phaseB. Development of design phaseC. Execution phase.D. Termination phase.E. None of the above
82 Which of the following are included in the Acquisition phase(s) of the project life cycle.A. concept and developmentB. development and planningC. execution and phase-outD. planning and implementationE. concept and planning
67 Life Cycle Costing:A. is the concept of including all costs within the total life of a project.B. is an activity devoted to optimizing cost/performanceC. is an activity of appraising the cost and technical performance of a completed project.D. is a process of predicting the life of a project.E. None of the above.
● Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?A 5%B 10%C 15%D 25%E 50%
● The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.A ConceptualB Development.C ExecutionD FinishE All of the above.
A project life cycle is a collection of generally sequential project (73) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74) for managing the project, regardless of the specific work involved.A.phasesB.processesC.segmentsD.pieces
The (71) defines the phases that connect the beginning of a project to its end.A.milestoneB.scheduleC.temporaryD.project life cycle
The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycleIt is().A.developmentB.conceptC.system analysisD.implementation
A project life cycle is a collection of generally sequential project ()whose name and number are determined by the control needs of the organization or organizations involved in the project.The life cycle provides the basic for managing the project, regardless of the specific work involved.A.phasesB.processesC.segmentsD. pieces
A project life cycle is a collection of generally sequential project whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic () for managing the project, regardless of the specific work involved.A. planB. fractionC. mainD.framework
The life cycle ofa project is a description of the various phases of the project from the beginning to the end.One of the followings is not a phase of the traditional project life cycle,itis_( )A.devclopmentB.conceptC.system analysisD.implementation
The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycle, It is( ).A.developmentB.conceptC.system analysisD.implementation
The life cycle of aproject is a description of the various phases of the project from thebeginning to the end. One of the followings is not a phase of the traditionalproject life cycle, It is( ). A.development B.concept C.system analysis D.implementation