Requirements management is the process of ( 73 ),analyzing, tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. It is a ( 74 ) process throughout a project. A requirement is a capability to which a project outcome (product or service) should conform.A.communicatingB.collectingC.filingD.documenting

Requirements management is the process of ( 73 ),analyzing, tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. It is a ( 74 ) process throughout a project. A requirement is a capability to which a project outcome (product or service) should conform.

A.communicating

B.collecting

C.filing

D.documenting


相关考题:

The Estimate Activity Resource process is closely coordinated with the(73) process.A.Estimate CostsB.Sequence ActivitiesC.Plan CommunicationsD.Conduct Procurements

● The Estimate Activity Resource process is closely coordinated with the (73)process.(73)A. Estimate CostsB. Sequence ActivitiesC. Plan CommunicationsD. Conduct Procurements

The Estimate Activity Resource process is closely coordinated with the(73) process.A.Estimate CostsB.Sequence ActivitiesC.Plan CommunicationsD.Conduct Procurements

Requirements management is the process of (1),analyzing,tracing,prioritizing andagreeing on requirements and then controlling changes and communicating to relevantstakeholders.A.communicatingB.collectingC.filingD.documenting

()is the process of documenting,analyzing,tracing,prioriiting on requirements and then controlling change and communicating to stakeholders it is a continuous process throughout a projectA.integratend managementB.configurationmanagemenC.scopemanagementD.requirementmanagement

The receiving activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understanding is reached on the meaning of the requirements. The result of this analysis and dialog is an(74)set of requirements.A.agreed-toB.agree-toC.agree-to-doD.agree-with

The Estimate Activity Resource process is closely coordinated with the (73)process.(73)A. Estimate CostsB. Sequence ActivitiesC. Plan CommunicationsD. Conduct Procurements

Requirements management is the process of (73) ,analyzing,tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. A.communicating B.collecting C.filing D.documenting

( ) is the process of documenting. Analyzing,tracing,prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project. A.Integrated management B.Configuration management C.Scope management D.Requirements management