预算更新通常在什么时候进行?A、 项目经理知道如果不修订预算则会导致成本超支B、 范围变更得到批准C、 项目的任何一个方面重新制定了基准计划D、 应急或管理储备被动用

预算更新通常在什么时候进行?

A、 项目经理知道如果不修订预算则会导致成本超支

B、 范围变更得到批准

C、 项目的任何一个方面重新制定了基准计划

D、 应急或管理储备被动用


相关考题:

Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent.A . Over, 16.66B . Under, 16.66C . Over, 10.0D . Under, 10.0E . None of the above.

197 Proper implementation of project management will guarantee that:A. Budgets will be met.B. Schedules will be adhered to. "C. Quality/performance will be met.D. The project will be a success.E. None of the above

135 A project manager wants to transmit a complex message to several subordinates. What is the best medium by which the manager can get his message across?A. OralB. WrittenC. NonverbalD. A and B onlyE. A, B, and C

64 An effective Project Manager does not share project _____ with the team members.A. VisionB. responsibilityC. solution to problemsD. accountabilityE. status

74 When comparing the cost of competing projects, which of the following is typically NOT considered?A. Opportunity costs.B. Direct costs.C. Sunk costs.D. Indirect costs.E. Burden rates

134 Which of the statements regarding benefit-cost analysis in the Special window are true?A. 1 and 2B. 2 and 3C. 1 and 3D. 1, 2 and 3E. None of the above

30 Which of the following is a formal invitation that requests a formal response that describes the method of work and associated compensation.A. Request for quotation (RFQ)B. Request for proposal (RFP)C. Request for bids (RFB)D. Invitation for bids (IFB)E. Letter of intent (LOI)

141 Using "I" or "My' instead of "most people" or "our group" ______ message credibility.A. decreasesB. increasesC. has no effect onD. distortsE. A and B

哪个过程是从风险拥有者处接受输入? ( )A.风险管理规划B.风险识别C.风险定性分析D.风险应对规划

本项目中EAC的值是多少?其代表的意义是什么?( )A.12500美元;对整个项目成本修正后的估计值(基于当时的绩效)B.10000美元;对整个项目成本修正后的估计值(基于当时的绩效)C.12500美元;原始的项目预算D.10000美元;原始的项目预算